Power Reactor Status Report for September 28, 2016
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 0 | 09/23/2016 | REFUELING OUTAGE | ||
Beaver Valley 2 | 100 | ||||
Calvert Cliffs 1 | 100 | ||||
Calvert Cliffs 2 | 100 | ||||
FitzPatrick | 84 | COASTDOWN TO REFUELING OUTAGE | * | ||
Ginna | 100 | ||||
Hope Creek 1 | 100 | ||||
Indian Point 2 | 100 | ||||
Indian Point 3 | 100 | ||||
Limerick 1 | 100 | ||||
Limerick 2 | 100 | ||||
Millstone 2 | 100 | ||||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 100 | ||||
Nine Mile Point 2 | 100 | ||||
Oyster Creek | 0 | 09/18/2016 | REFUELING OUTAGE | ||
Peach Bottom 2 | 99 | 100 MVAR LIMIT FOR TURBINE BEARING VIBRATION - COASTDOWN TO REFUELING OUTAGE | * | ||
Peach Bottom 3 | 100 | ||||
Pilgrim 1 | 100 | ||||
Salem 1 | 100 | ||||
Salem 2 | 100 | ||||
Seabrook 1 | 100 | 1 CONTINGENCY AWAY FROM DOWN POWER DUE TO TRANSMISSION LINE MAINTENANCE | |||
Susquehanna 1 | 100 | ||||
Susquehanna 2 | 100 | ||||
Three Mile Island 1 | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 81 | COASTDOWN TO REFUELING OUTAGE | |||
Browns Ferry 2 | 100 | ||||
Browns Ferry 3 | 100 | ||||
Brunswick 1 | 100 | ||||
Brunswick 2 | 100 | * | |||
Catawba 1 | 100 | ||||
Catawba 2 | 0 | 09/09/2016 | REFUELING OUTAGE - CORE RELOAD IN PROGRESS | * | |
Farley 1 | 100 | ||||
Farley 2 | 100 | ||||
Harris 1 | 96 | COASTDOWN TO REFUELING OUTAGE | * | ||
Hatch 1 | 100 | ||||
Hatch 2 | 100 | ||||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 0 | 09/10/2016 | REFUELING OUTAGE | ||
North Anna 2 | 100 | ||||
Oconee 1 | 100 | ||||
Oconee 2 | 100 | ||||
Oconee 3 | 100 | ||||
Robinson 2 | 100 | ||||
Saint Lucie 1 | 0 | 09/25/2016 | REFUELING OUTAGE | ||
Saint Lucie 2 | 100 | ||||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 100 | ||||
Summer | 100 | ||||
Surry 1 | 100 | ||||
Surry 2 | 100 | ||||
Turkey Point 3 | 100 | ||||
Turkey Point 4 | 100 | ||||
Vogtle 1 | 100 | ||||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 100 | ||||
Watts Bar 2 | 100 | * |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 0 | 09/25/2016 | REFUELING OUTAGE | ||
Braidwood 2 | 100 | ||||
Byron 1 | 92 | LOAD FOLLOW | * | ||
Byron 2 | 100 | ||||
Clinton | 94 | DOWNPOWER DUE TO ENVIRONMENTAL CONDITIONS | * | ||
D.C. Cook 1 | 100 | ||||
D.C. Cook 2 | 100 | ||||
Davis-Besse | 100 | ||||
Dresden 2 | 100 | ||||
Dresden 3 | 84 | COASTDOWN TO REFUELING OUTAGE | * | ||
Duane Arnold | 93 | COASTDOWN TO REFUELING OUTAGE | |||
Fermi 2 | 100 | ||||
LaSalle 1 | 100 | ||||
LaSalle 2 | 100 | ||||
Monticello | 58 | HOLDING FOR FEED PUMP VIBRATION ISSUES | |||
Palisades | 100 | ||||
Perry 1 | 80 | REACTOR FEED BOOSTER PUMP TRIP | |||
Point Beach 1 | 100 | ||||
Point Beach 2 | 100 | ||||
Prairie Island 1 | 100 | ||||
Prairie Island 2 | 100 | ||||
Quad Cities 1 | 100 | ||||
Quad Cities 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 0 | 09/23/2016 | REFUELING OUTAGE | ||
Arkansas Nuclear 2 | 100 | WILL COMMENCE A PLANT SHUTDOWN TODAY FOR MAINTENANCE | * | ||
Callaway | 65 | MAIN FEED PUMP ISSUES | * | ||
Columbia Generating Station | 100 | ||||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 100 | ||||
Cooper | 0 | 09/24/2016 | REFUELING OUTAGE | * | |
Diablo Canyon 1 | 100 | ||||
Diablo Canyon 2 | 100 | ||||
Fort Calhoun | 100 | ||||
Grand Gulf 1 | 0 | 09/08/2016 | FORCED OUTAGE | ||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 100 | ||||
Palo Verde 3 | 100 | * | |||
River Bend 1 | 100 | ||||
South Texas 1 | 100 | ||||
South Texas 2 | 100 | ||||
Waterford 3 | 100 | ||||
Wolf Creek 1 | 0 | 09/02/2016 | REFUELING OUTAGE |