The NRC is modernizing nrc.gov with an updated design and improved navigation to enhance usability. We are committed to a smooth transition and will work to minimize any disruption. The site may be briefly unavailable at times during launch. Thank you for your patience.
Power Reactor Status Report for May 6, 2016
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Calvert Cliffs 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Indian Point 2 | 0 | 03/07/2016 | REFUELING OUTAGE | ||
| Indian Point 3 | 100 | PROTECTING FEEDER CROSS TIE BREAKER | |||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | ||||
| Millstone 3 | 0 | 04/09/2016 | REFUELING OUTAGE | ||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 25 | INCREASING POWER | * | ||
| Oyster Creek | 0 | 04/24/2016 | WORKING ON REPAIRING SEAL LEAK | * | |
| Peach Bottom 2 | 100 | 100 MVAR RESTRICTION DUE TO TURBINE BEARING VIBRATIONS | |||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 50 | CLEANING INTAKE FOULING | * | ||
| Salem 1 | 0 | 04/14/2016 | REFUELING OUTAGE | ||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | ||||
| Susquehanna 1 | 80 | INCREASING POWER HIGH SYSTEM VOLTAGE ACTION | * | ||
| Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 91 | REDUCED POWER FOR PLANNED MAINTENANCE | * | ||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Farley 1 | 100 | ||||
| Farley 2 | 0 | 04/10/2016 | REFUELING OUTAGE | * | |
| Harris 1 | 100 | ||||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 0 | 04/22/2016 | REFUELING OUTAGE - CORE RELOAD COMPLETE | ||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 35 | DOWNPOWER DUE TO TURBINE VIBRATIONS | * | ||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 100 | ||||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 | ||||
| Watts Bar 2 | 0 | MODE CHANGE TO SUPPORT AUX FEED REPAIRS |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 0 | 04/18/2016 | REFUELING OUTAGE | ||
| Clinton | 94 | COASTDOWN TO REFUELING OUTAGE | |||
| D.C. Cook 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| D.C. Cook 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Davis-Besse | 0 | 03/25/2016 | REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION | * | |
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | * | |||
| Fermi 2 | 0 | 05/03/2016 | MAINTENANCE OUTAGE | ||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 100 | ||||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | * | |||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 87 | REDUCED DUE TO TSO REQUEST | * |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 0 | 04/02/2016 | REFUELING OUTAGE | * | |
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 0 | 05/01/2016 | REFUELING OUTAGE | ||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 0 | 04/30/2016 | REFUELING OUTAGE | ||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 100 | ||||
| Palo Verde 1 | 0 | 04/08/2016 | REFUELING OUTAGE | ||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| South Texas 1 | 13 | HOLDING POWER TO PLACE TURBINE ONLINE | * | ||
| South Texas 2 | 100 | ||||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |
Page Last Reviewed/Updated Thursday, August 27, 2026