Power Reactor Status Report for April 21, 2016
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Calvert Cliffs 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Indian Point 2 | 0 | 03/07/2016 | REFUELING OUTAGE | ||
| Indian Point 3 | 100 | ||||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | ||||
| Millstone 3 | 0 | 04/09/2016 | REFUELING OUTAGE | ||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 0 | 04/10/2016 | REFUELING OUTAGE | ||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | 100 MVAR RESTRICTION DUE TO TURBINE BEARING VIBRATIONS | |||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 0 | 04/14/2016 | REFUELING OUTAGE - CORE OFFLOAD IN PROGRESS | ||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | ||||
| Susquehanna 1 | 1 | COMMENCE STARTUP - HIGH SYSTEM VOLTAGE ACTION | * | ||
| Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 86 | REDUCED POWER PER LOAD DISPATCHER | |||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Farley 1 | 100 | ||||
| Farley 2 | 0 | 04/10/2016 | REFUELING OUTAGE | ||
| Harris 1 | 100 | * | |||
| Hatch 1 | 0 | 04/19/2016 | FORCED OUTAGE - SAFETY RELIEF VALVE ISSUE | ||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 93 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 100 | ||||
| Turkey Point 4 | 0 | 03/29/2016 | REFUELING OUTAGE | ||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 | ||||
| Watts Bar 2 | 0 | MODE CHANGE TO SUPPORT AUX FEED REPAIRS |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 0 | 04/18/2016 | REFUELING OUTAGE | ||
| Clinton | 85 | ONE TURBINE DRIVEN FEED PUMP REMOVED FROM SERVICE | |||
| D.C. Cook 1 | 0 | 03/22/2016 | REFUELING OUTAGE - HIGH SYSTEM VOLTAGE ACTION | * | |
| D.C. Cook 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | * | ||
| Davis-Besse | 0 | 03/25/2016 | REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION | ||
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | ||||
| Fermi 2 | 62 | REDUCED POWER FOR POWER SUPPRESSION TESTING | |||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 100 | ||||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 100 |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 0 | 04/02/2016 | REFUELING OUTAGE | ||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 74 | REDUCED POWER FOR HCU REPAIRS | * | ||
| Palo Verde 1 | 0 | 04/08/2016 | REFUELING OUTAGE | ||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| South Texas 1 | 100 | ||||
| South Texas 2 | 100 | ||||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |
Page Last Reviewed/Updated Thursday, August 27, 2026