Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for March 9, 2014

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 0 02/16/2014 REFUELING OUTAGE *  
Calvert Cliffs 2 100        
FitzPatrick 100     *  
Ginna 100        
Hope Creek 1 100        
Indian Point 2 0 02/23/2014 REFUELING OUTAGE LINE 95891 OOS FOR SCHEDULED MAINTENANCE    
Indian Point 3 100   LINES 95331, 13W92 AND 13W93 ARE RESTRICTED DUE TO UNIT 2 OUTAGE. LINE 95332 OOS.    
Limerick 1 0 03/04/2014 FORCED OUTAGE - UNIT 1 MANUALLY SCRAMMED DUE TO EHC SYSTEM FAILURE - SEE EN #49871.    
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100     *  
Oyster Creek 100        
Peach Bottom 2 100        
Peach Bottom 3 100   JUMPERS INSTALLED AROUND MAIN GENERATOR DISCONNECT    
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 99   OPERATION LIMITED BY GENERATOR CAPABILITY CURVE *  
Susquehanna 2 0 03/01/2014 MAINTENANCE OUTAGE - PLANNED TURBINE MAINTENANCE    
Three Mile Island 1 100        
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100        
Browns Ferry 2 100     *  
Browns Ferry 3 0 02/14/2014 REFUELING OUTAGE    
Brunswick 1 0 02/28/2014 REFUELING OUTAGE    
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 94   HOLDING POWER FOR 24 HOUR SOAK *  
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 0 03/07/2014 PLANNED SHUTDOWN FOR SG TUBE REPAIRS *  
Saint Lucie 1 100        
Saint Lucie 2 0 03/02/2014 REFUELING OUTAGE    
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 99   COASTDOWN TO REFUELING OUTAGE    
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 86   GENERATOR DISPATCH REQUEST    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 0 01/31/2014 REFUELING OUTAGE    
Dresden 2 100        
Dresden 3 100        
Duane Arnold 100        
Fermi 2 0 02/10/2014 REFUELING OUTAGE    
La Salle 1 100        
La Salle 2 100        
Monticello 91   ENGINEERING HOLD FOR EPU TESTING *  
Palisades 0 01/19/2014 REFUELING OUTAGE    
Perry 1 58   FW HEATER WORK AND ROD SEQUENCE EXCHANGE *  
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 100     *  
Quad Cities 2 94   COASTDOWN TO REFUELING OUTAGE *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 70   MSIV AND STOP VALVE TESTING *  
Diablo Canyon 1 0 02/08/2014 EXITING REFUELING OUTAGE    
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 0 02/09/2014 REFUELING OUTAGE    
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 0 03/07/2014 MID CYCLE PLANNED MAINTENANCE OUTAGE *  