Power Reactor Status Report for November 11, 2012

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 0 11/10/2012 REACTOR SCRAM DUE TO A TRANSFORMER FIRE. SEE EN #48501 * 1
Ginna 0 10/21/2012 REFUELING OUTAGE    
Hope Creek 1 100        
Indian Point 2 100   138 KV FEEDER (LINE 13332) OOS    
Indian Point 3 100   138 KV FEEDER (LINE 13332) OOS    
Limerick 1 100        
Limerick 2 100        
Millstone 2 0 10/06/2012 REFUELING OUTAGE    
Millstone 3 100        
Nine Mile Point 1 100     *  
Nine Mile Point 2 20   HOLDING AT REQUEST OF LOAD DISPATCHER THEN PLANNED MAINTENANCE SHUTDOWN *  
Oyster Creek 0 10/21/2012 REFUELING OUTAGE    
Peach Bottom 2 100        
Peach Bottom 3 77   INCREASING POWER FOLLOWING CONTROL VALVE TESTING *  
Pilgrim 1 100        
Salem 1 100        
Salem 2 0 10/14/2012 REFUELING OUTAGE    
Seabrook 1 100        
Susquehanna 1 89   HOLDING POWER PENDING COMPLETION OF INVESTIGATION INTO UNIT 2 SCRAM    
Susquehanna 2 0 11/08/2012 FORCED OUTAGE - SEE EN#48496    
Three Mile Island 1 100        
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 10/19/2012 REFUELING OUTAGE    
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Crystal River 3 0 09/25/2009 DEFUELED - CONT.TENSIONING ON HOLD    
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 0 09/15/2012 MAINTENANCE OUTAGE    
North Anna 1 100        
North Anna 2 99   INCREASING POWER    
Oconee 1 0 10/26/2012 DEFUELED    
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 0 08/05/2012 REFUELING OUTAGE    
Sequoyah 1 100        
Sequoyah 2 0 10/14/2012 DEFUELED    
Summer 0 10/12/2012 DEFUELED    
Surry 1 100        
Surry 2 0 10/31/2012 REFUELING OUTAGE    
Turkey Point 3 98   HOLDING POWER FOR EPU TESTING    
Turkey Point 4 0 11/04/2012 REFUELING OUTAGE    
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 83   INCREASING POWER TO 100% *  
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 50   MAINTENANCE ON MAIN CONDENSER *  
Dresden 2 100        
Dresden 3 84   COASTDOWN TO REFUELING OUTAGE - SCHEDULED FOR 11/12    
Duane Arnold 0 10/05/2012 REFUELING OUTAGE    
Fermi 2 0 11/07/2012 FORCED OUTAGE - SEE EN#48487    
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 0 10/31/2012 REFUELING OUTAGE    
Prairie Island 1 0 10/22/2012 REFUELING OUTAGE    
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 100        

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 0 11/01/2012 RCP MOTOR WORK COMPLETED - RCP STARTUP IN PROGRESS *  
Comanche Peak 2 75   INCREASING POWER *  
Cooper 0 10/13/2012 REFUELING OUTAGE    
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 0 04/09/2011 DEFUELED    
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 39   HOLDING POWER FOR CONDENSER REPAIRS *  
Palo Verde 3 100        
River Bend 1 100        
San Onofre 2 0 01/09/2012 REFUELING OUTAGE - SWITCHYARD RESTRICTIONS BUT NO GRID RESTRICTIONS    
San Onofre 3 0 01/31/2012 FORCED OUTAGE - S/G REPAIR - DEFUELED - SWITCHYARD RESTRICTIONS BUT NO GRID RESTRICTIONS    
South Texas 1 0 10/20/2012 DEFUELED    
South Texas 2 100        
Waterford 3 0 10/17/2012 DEFUELED    
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021