Power Reactor Status Report for October 7, 2012

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 0 09/23/2012 REFUELING OUTAGE - RV HEAD REMOVED    
Calvert Cliffs 1 100   HIGH SYSTEM VOLTAGE *  
Calvert Cliffs 2 100   HIGH SYSTEM VOLTAGE *  
FitzPatrick 0 09/16/2012 REFUELING OUTAGE RV REASSEMBLY ONGOING    
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100   138 KV FEEDER RESTRICTIONS    
Indian Point 3 100   138 kV FEEDER RESTRICTIONS *  
Limerick 1 100        
Limerick 2 100     *  
Millstone 2 0 10/06/2012 ENTERING REFUELING OUTAGE *  
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 0 09/09/2012 DEFUELED    
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 0 09/14/2012 REFUELING OUTAGE - 345KV LINE #3135 OOS MAKING THE NEWINGTON LINE UNAVAILABLE    
Susquehanna 1 65   TURBINE BLADE ISSUES- HIGH SYSTEM VOLTAGE *  
Susquehanna 2 65   TURBINE BLADE ISSUES- HIGH SYSTEM VOLTAGE *  
Three Mile Island 1 100   HIGH SYSTEM VOLTAGE *  
Vermont Yankee 95   REDUCED POWER FOR ON-GOING LINE WORK    

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100        
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Crystal River 3 0 09/25/2009 DEFUELED - CONTAINMENT TENSIONING ON HOLD    
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 98   HOLD FOR FUEL PRE-CONDITION *  
Hatch 2 100        
McGuire 1 100        
McGuire 2 0 09/15/2012 DEFUELED    
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 0 08/05/2012 DEFUELED    
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 88   WATERBOX MAINTENANCE    
Turkey Point 3 29   30% PWR HOLD FOR SECONDARY CHEMISTRY    
Turkey Point 4 100        
Vogtle 1 0 09/16/2012 EXIT REFUELING OUTAGE *  
Vogtle 2 100        
Watts Bar 1 0 09/10/2012 BEGIN CORE RELOAD    

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 0 09/10/2012 EXIT REFUELING OUTAGE NORMAL OPERATING TEMPERATURE AND PRESSURE *  
Byron 2 100   BUS 4 OOS *  
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100   HIGH VOLTAGE SYSTEM ACTION *  
D.C. Cook 2 100   HIGH VOLTAGE SYSTEM ACTION *  
Davis-Besse 100   HIGH VOLTAGE SYSTEM ACTION *  
Dresden 2 100        
Dresden 3 95   COASTDOWN TO REFUELING OUTAGE *  
Duane Arnold 0 10/05/2012 REFUELING OUTAGE *  
Fermi 2 68   POWER LIMITED TO 68% DUE TO SOUTH REACTOR FEED PUMP OOS    
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 79   TURBINE VALVE FREEDOM TEST *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 0 09/13/2012 REFUELING OUTAGE    
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 0 10/06/2012 REFUELING OUTAGE *  
Cooper 93   COASTDOWN TO REFUELING OUTAGE    
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 0 04/09/2011 DEFUELED *  
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 0 10/05/2012 REFUELING OUTAGE *  
Palo Verde 3 100        
River Bend 1 100        
San Onofre 2 0 01/09/2012 REFUELING OUTAGE    
San Onofre 3 0 01/31/2012 FORCED OUTAGE - S/G REPAIR - DEFUELING *  
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.