Power Reactor Status Report for July 15, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | ||||
| Calvert Cliffs 2 | 100 | * | |||
| FitzPatrick | 100 | SOLAR ACTIVITY WARNING | * | ||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | MAIN GENERATOR VOLTAGE REGULATOR IN MANUAL | |||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 100 | SOLAR ACTIVITY WARNING | * | ||
| Limerick 1 | 30 | INCREASING POWER | |||
| Limerick 2 | 100 | ||||
| Millstone 2 | 85 | "B" CIRC WATER PUMP OOS - DAMAGED | * | ||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | SOLAR ACTIVITY WARNING | * | ||
| Nine Mile Point 2 | 14 | STABLE; ROLLING TURBINE; SOLAR ACTIVITY WARNING | * | ||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | COASTDOWN TO REFUELING OUTAGE | |||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 85 | POWER LIMITED TO 85% BASED ON GENERATOR STATOR COOLING DELTA T LIMIT - SWITCHYARD MAINTENANCE ON-GOING UNTIL APPROX. 7/17/12 | |||
| Susquehanna 1 | 100 | ||||
| Susquehanna 2 | 100 | ||||
| Three Mile Island 1 | 100 | SOLAR ACTIVITY WARNING | * | ||
| Vermont Yankee | 100 | SOLAR ACTIVITY WARNING | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
| Farley 1 | 100 | ||||
| Farley 2 | 100 | ||||
| Harris 1 | 100 | * | |||
| Hatch 1 | 100 | * | |||
| Hatch 2 | 100 | * | |||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | HOT WEATHER ALERT | * | ||
| North Anna 2 | 100 | HOT WEATHER ALERT | * | ||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 100 | ||||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 99 | ||||
| Saint Lucie 2 | 83 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | HOT WEATHER ALERT | * | ||
| Surry 2 | 100 | HOT WEATHER ALERT | * | ||
| Turkey Point 3 | 0 | 02/26/2012 | REFUELING OUTAGE | ||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * | ||
| Braidwood 2 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * | ||
| Byron 1 | 88 | DEGRADED NATURAL DRAFT TOWER PERFORMANCE | |||
| Byron 2 | 92 | DEGRADED NATURAL DRAFT TOWER PERFORMANCE | |||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY. | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 100 | ||||
| Davis-Besse | 100 | ||||
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 97 | WILL INCREASE POWER TO 100% ON DAYSHIFT - SOLAR ALERT IN EFFECT UNTIL 0700 EDT | * | ||
| Fermi 2 | 0 | 06/25/2012 | FORCED OUTAGE - SEE EN #48047 | ||
| Kewaunee | 100 | ||||
| La Salle 1 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * | ||
| La Salle 2 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * | ||
| Monticello | 100 | ||||
| Palisades | 100 | ||||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * | ||
| Quad Cities 2 | 100 | HOT WEATHER ALERT IN EFFECT 7/15-7/16 EVENING | * |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 100 | ||||
| Columbia Generating Station | 85 | ECONOMIC DISPATCH | |||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
| Grand Gulf 1 | 100 | ||||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | * | |
| San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 100 | ||||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |