Power Reactor Status Report for June 13, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 100 | MINIMUM GENERATION ALERT | * | ||
Beaver Valley 2 | 100 | MINIMUM GENERATION ALERT | * | ||
Calvert Cliffs 1 | 100 | MINIMUM GENERATION ALERT | * | ||
Calvert Cliffs 2 | 100 | MINIMUM GENERATION ALERT | * | ||
FitzPatrick | 100 | ||||
Ginna | 100 | ||||
Hope Creek 1 | 100 | MAIN GENERATOR VOLTAGE REGULATOR IN MANUAL | * | ||
Indian Point 2 | 100 | ||||
Indian Point 3 | 100 | ||||
Limerick 1 | 100 | ||||
Limerick 2 | 100 | ||||
Millstone 2 | 100 | ||||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 100 | ||||
Nine Mile Point 2 | 65 | HOLDING POWER FOR FEED WATER PUMP TESTING | * | ||
Oyster Creek | 100 | ||||
Peach Bottom 2 | 100 | ||||
Peach Bottom 3 | 100 | ||||
Pilgrim 1 | 100 | ||||
Salem 1 | 100 | ||||
Salem 2 | 100 | ||||
Seabrook 1 | 85 | POWER LIMITED TO 85% BASED ON GENERATOR STATOR COOLING DELTA T LIMIT - SWITCHYARD MAINTENANCE ON-GOING UNTIL APPROX. 06/25 | |||
Susquehanna 1 | 100 | MINIMUM GENERATION ALERT | * | ||
Susquehanna 2 | 0 | 05/30/2012 | MAINTENANCE OUTAGE - SHUTDOWN FOR TURBINE BLADE INSPECTION MINIMUM GENERATION ALERT | * | |
Three Mile Island 1 | 100 | ||||
Vermont Yankee | 82 | INCREASING POWER | * |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 100 | ||||
Browns Ferry 2 | 100 | ||||
Browns Ferry 3 | 100 | ||||
Brunswick 1 | 98 | TEMPORARY LOSS OF SPDS | * | ||
Brunswick 2 | 98 | TEMPORARY LOSS OF SPDS | * | ||
Catawba 1 | 100 | ||||
Catawba 2 | 100 | ||||
Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
Farley 1 | 100 | ||||
Farley 2 | 100 | ||||
Harris 1 | 100 | * | |||
Hatch 1 | 100 | ||||
Hatch 2 | 100 | ||||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 100 | ||||
North Anna 2 | 100 | ||||
Oconee 1 | 100 | ||||
Oconee 2 | 100 | ||||
Oconee 3 | 100 | ||||
Robinson 2 | 100 | * | |||
Saint Lucie 1 | 100 | ||||
Saint Lucie 2 | 100 | ||||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 100 | ||||
Summer | 100 | ||||
Surry 1 | 100 | ||||
Surry 2 | 100 | ||||
Turkey Point 3 | 0 | 02/26/2012 | DEFUELED | ||
Turkey Point 4 | 100 | ||||
Vogtle 1 | 100 | ||||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 100 |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 100 | ||||
Braidwood 2 | 100 | ||||
Byron 1 | 100 | * | |||
Byron 2 | 100 | ||||
Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
D.C. Cook 1 | 100 | MINIMUM GENERATION ALERT | * | ||
D.C. Cook 2 | 100 | MINIMUM GENERATION ALERT | * | ||
Davis-Besse | 22 | INCREASING POWER | * | ||
Dresden 2 | 100 | ||||
Dresden 3 | 100 | ||||
Duane Arnold | 99 | REDUCED POWER FOR ROD PATTERN ADJUSTMENT | * | ||
Fermi 2 | 100 | ||||
Kewaunee | 100 | ||||
La Salle 1 | 100 | ||||
La Salle 2 | 100 | ||||
Monticello | 100 | ||||
Palisades | 0 | 06/12/2012 | TECH SPEC REQUIRED SHUTDOWN TO REPAIR REFUELING WATER TANK LEAKS. SEE EN# 48018. | * | |
Perry 1 | 71 | FLOW CONTROL ISSUES ON RX RECIRC FLOW CONTROL VALVE | * | ||
Point Beach 1 | 100 | ||||
Point Beach 2 | 100 | ||||
Prairie Island 1 | 100 | ||||
Prairie Island 2 | 100 | ||||
Quad Cities 1 | 100 | ||||
Quad Cities 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 100 | ||||
Arkansas Nuclear 2 | 100 | ||||
Callaway | 100 | ||||
Columbia Generating Station | 85 | REDUCED POWER FOR ECONOMIC DISPATCH | * | ||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 100 | ||||
Cooper | 80 | INCREASING POWER | * | ||
Diablo Canyon 1 | 0 | 04/22/2012 | EXITING REFUELING OUTAGE | * | |
Diablo Canyon 2 | 100 | ||||
Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
Grand Gulf 1 | 3 | STARTUP - HOLDING POWER FOR PLANT TESTING. | * | ||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 100 | ||||
Palo Verde 3 | 100 | ||||
River Bend 1 | 84 | HOLDING POWER AFTER WATER BOX MAINTENANCE | * | ||
San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | ||
San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | ||
South Texas 1 | 100 | ||||
South Texas 2 | 100 | ||||
Waterford 3 | 100 | ||||
Wolf Creek 1 | 100 |