The NRC is modernizing nrc.gov with an updated design and improved navigation to enhance usability. We are committed to a smooth transition and will work to minimize any disruption. The site may be briefly unavailable at times during launch. Thank you for your patience.
Power Reactor Status Report for April 11, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 0 | 04/08/2012 | REFUELING OUTAGE | ||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 75 | INCREASING POWER | * | ||
| Calvert Cliffs 2 | 100 | ||||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 95 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 0 | 04/10/2012 | CONTROLLED SHUTDOWN WITH PRE-PLANNED RX SCRAM OUTAGE FOR UNIT AUX TRANSFORMER MAINTENANCE | * | 1 |
| Limerick 1 | 100 | HIGH VOLTAGE ALERT | |||
| Limerick 2 | 100 | HIGH VOLTAGE ALERT | |||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 0 | 04/08/2012 | REFUELING OUTAGE | ||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | SBO LINE OOS FOR PM | |||
| Peach Bottom 3 | 100 | SBO LINE OOS FOR PM | |||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 85 | HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT | |||
| Susquehanna 1 | 0 | 03/31/2012 | REFUELING OUTAGE | ||
| Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Vermont Yankee | 34 | CONDENSER TUBE LEAK | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 0 | 04/07/2012 | REFUELING OUTAGE | ||
| Brunswick 1 | 0 | 02/23/2012 | REFUELING OUTAGE | ||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 0 | 04/04/2012 | FORCED OUTAGE. SEE EN #47805 | ||
| Catawba 2 | 0 | 03/10/2012 | REFUELING OUTAGE | ||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
| Farley 1 | 0 | 04/01/2012 | DEFUELED | ||
| Farley 2 | 100 | ||||
| Harris 1 | 96 | COASTDOWN TO REFUELING OUTAGE | |||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 0 | 03/10/2012 | DEFUELED | * | |
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 80 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 0 | 04/07/2012 | SHUTDOWN FOR WATERBOX REPAIR | ||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | * | |||
| Turkey Point 3 | 0 | 02/26/2012 | DEFUELED | ||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 98 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.6% | |||
| Byron 2 | 100 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.9% | |||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 0 | 03/21/2012 | DEFUELED | ||
| Davis-Besse | 100 | ||||
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | ||||
| Fermi 2 | 0 | 03/25/2012 | REFUELING OUTAGE - 345KV LINES OOS FOR PM | ||
| Kewaunee | 0 | 04/05/2012 | REFUELING OUTAGE | ||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 0 | 04/08/2012 | REFUELING OUTAGE | ||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 0 | 02/21/2012 | DEFUELED | ||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 0 | REFUELING OUTAGE |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 98 | TURBINE CONTROL OSCILLATIONS | |||
| Columbia Generating Station | 100 | * | |||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 99 | 100% TURBINE LOAD | |||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
| Grand Gulf 1 | 0 | 02/19/2012 | REFUELING OUTAGE | ||
| Palo Verde 1 | 80 | REDUCED POWER FOR FEEDWATER HEATER REPAIR | |||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 0 | 03/16/2012 | REFUELING OUTAGE | ||
| River Bend 1 | 100 | ||||
| San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | ||
| San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 0 | 11/28/2011 | HEATUP IN PROGRESS | ||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |
Page Last Reviewed/Updated Tuesday, August 25, 2026
Page Last Reviewed/Updated Tuesday, August 25, 2026