Power Reactor Status Report for November 12, 2010

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 100        
Ginna 100        
Hope Creek 1 18   INCREASING POWER *  
Indian Point 2 0 11/07/2010 FORCED OUTAGE    
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 0 11/10/2010 FORCED OUTAGE - AUTO RX SCRAM - SEE EN #46409 *  
Nine Mile Point 2 100        
Oyster Creek 0 10/31/2010 REFUELING OUTAGE    
Peach Bottom 2 100   ONE OF THREE STARTUP LINES OOS FOR TRANSFORMER MAINTENANCE    
Peach Bottom 3 100   ONE OF THREE STARTUP LINES OOS FOR TRANSFORMER MAINTENANCE    
Pilgrim 1 100     *  
Salem 1 100        
Salem 2 100        
Seabrook 1 100     *  
Susquehanna 1 99   MAX ELECTRICAL OUTPUT *  
Susquehanna 2 94   100% ELECTRICAL CAPABILITY    
Three Mile Island 1 100        
Vermont Yankee 74   INCREASING POWER *  

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 11/06/2010 REFUELING OUTAGE    
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Crystal River 3 0 09/25/2009 DEFUELED    
Farley 1 0 10/10/2010 REFUELING OUTAGE    
Farley 2 100        
Harris 1 7   HOLD FOR GENERATOR TEST *  
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 0 10/22/2010 CORE RELOAD COMPLETED    
Robinson 2 0 10/06/2010 MAINTENANCE OUTAGE    
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 0 10/01/2010 EXIT REFUELING OUTAGE *  
Sequoyah 2 100        
Summer 100        
Surry 1 0 10/23/2010 DEFUELED    
Surry 2 98   100% ELECTRICAL CAPABILITY    
Turkey Point 3 80   INCREASING POWER *  
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 96   HOLDING POWER FOR FUEL SOAK    
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 50   REDUCING POWER TO 20-25% FOR CONTAINMENT ENTRY BETWEEN 0600-0700 HRS *  
D.C. Cook 2 0 10/05/2010 DEFUELED    
Davis-Besse 100        
Dresden 2 100        
Dresden 3 0 10/31/2010 REFUELING OUTAGE    
Duane Arnold 0 10/23/2010 REFUELING OUTAGE    
Fermi 2 0 10/24/2010 REFUELING OUTAGE    
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 48   REDUCED POWER TO ISOLATE THE 'B' HIGH PRESSURE FEEDWATER HEATER STRING *  
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 95   REDUCED POWER FOR REPAIR OF HEATER DRAIN TANK PUMP    
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 100        

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 2   HOLDING POWER TO RESOLVE AUX FEED ISSUE - 500KV DIABLO MIDWAY LINE #2 OOS FROM 0600 HRS 11/12 TIL 11/14 *  
Diablo Canyon 2 100   500KV DIABLO MIDWAY LINE #2 OOS FROM 0600 HRS 11/12 TIL 11/14 *  
Fort Calhoun 100        
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 25   INCREASING POWER TO 100% *  
River Bend 1 100        
San Onofre 2 100   SWITCHYARD RESTRICTIONS - NO MAINTENANCE WITHOUT SHIFT MANAGER APPROVAL    
San Onofre 3 0 10/09/2010 DEFUELED - SWITCHYARD RESTRICTIONS - NO MAINTENANCE WITHOUT SHIFT MANAGER APPROVAL    
South Texas 1 100        
South Texas 2 0 11/03/2010 MAINTENANCE OUTAGE *  
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.