Power Reactor Status Report for November 7, 2010
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | * | |||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | ||||
| Calvert Cliffs 2 | 85 | REDUCED POWER FOR WATER BOX CLEANING | * | ||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 0 | 10/15/2010 | REFUELING OUTAGE | ||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 100 | ||||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 0 | 10/31/2010 | REFUELING OUTAGE | ||
| Peach Bottom 2 | 100 | ONE OF THREE STARTUP LINES OOS FOR TRANSFORMER MAINTENANCE | |||
| Peach Bottom 3 | 100 | ONE OF THREE STARTUP LINES OOS FOR TRANSFORMER MAINTENANCE | |||
| Pilgrim 1 | 100 | * | |||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | ||||
| Susquehanna 1 | 99 | GENERATOR LIMITED | |||
| Susquehanna 2 | 94 | 100% ELECTRICAL CAPABILITY | |||
| Three Mile Island 1 | 100 | ||||
| Vermont Yankee | 81 | POWER REDUCED PER ISO FOR OFFSITE LINE OUTAGE MAINTENANCE | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 0 | 11/06/2010 | REFUELING OUTAGE | ||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED | ||
| Farley 1 | 0 | 10/10/2010 | REFUELING OUTAGE | ||
| Farley 2 | 100 | ||||
| Harris 1 | 0 | 10/01/2010 | REFUELING OUTAGE | ||
| Hatch 1 | 100 | ||||
| Hatch 2 | 96 | INCREASING POWER AFTER TURBINE TESTING AND ROD PATTERN ADJUSTMENT | * | ||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 0 | 11/06/2010 | MAINTENANCE OUTAGE SHUTDOWN TO REPAIR MAIN GENERATOR HYDROGEN LEAK | * | |
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 0 | 10/22/2010 | CORE RELOAD IN PROGRESS | ||
| Robinson 2 | 0 | 10/06/2010 | MAINTENANCE OUTAGE | ||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 0 | 10/01/2010 | REFUELING OUTAGE - MAKING PREPARATIONS TO ENTER MODE 4 | ||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 0 | 10/23/2010 | DEFUELED | ||
| Surry 2 | 98 | 100% ELECTRICAL CAPABILITY | |||
| Turkey Point 3 | 0 | 09/25/2010 | REFUELING OUTAGE | ||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 61 | INCREASING POWER | * | ||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 100 | ||||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 0 | 10/05/2010 | DEFUELED | ||
| Davis-Besse | 45 | TROUBLESHOOTING OUT OF POSITION CONTROL ROD | * | ||
| Dresden 2 | 100 | ||||
| Dresden 3 | 0 | 10/31/2010 | REFUELING OUTAGE | ||
| Duane Arnold | 0 | 10/23/2010 | REFUELING OUTAGE | ||
| Fermi 2 | 0 | 10/24/2010 | REFUELING OUTAGE | ||
| Kewaunee | 100 | ||||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 50 | REDUCED POWER TO ISOLATE THE 'B' HIGH PRESSURE FEEDWATER HEATER | |||
| Palisades | 100 | ||||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 94 | REDUCED POWER FOR REPAIR OF HEATER DRAIN TANK PUMP | * | ||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 100 |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 100 | ||||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 0 | 10/02/2010 | HEATUP FOLLOWING REFUELING OUTAGE | ||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 100 | ||||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | * | |||
| Palo Verde 3 | 0 | 10/01/2010 | EXITING REFUELING OUTAGE - HEATUP IN PROGRESS | * | |
| River Bend 1 | 100 | * | |||
| San Onofre 2 | 100 | ||||
| San Onofre 3 | 0 | 10/09/2010 | DEFUELED | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 0 | 11/03/2010 | FORCED OUTAGE - DUE TO A BREAKER FAULT IN THE PA AFFECTING NORMAL OPS - SEE EN #46387 | ||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |