Power Reactor Status Report for September 25, 2010
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 98 | FEEDWATER REG. VALVE REPAIR | * | ||
| Calvert Cliffs 2 | 100 | * | |||
| FitzPatrick | 0 | 09/12/2010 | REFUELING OUTAGE | ||
| Ginna | 100 | ||||
| Hope Creek 1 | 97 | COOLING TOWER INEFFECTIVENESS | * | ||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 100 | ||||
| Limerick 1 | 100 | * | |||
| Limerick 2 | 100 | * | |||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 0 | 09/12/2010 | REFUELING OUTAGE | ||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | * | |||
| Salem 2 | 100 | ||||
| Seabrook 1 | 94 | MAIN GENERATOR HIGH VOLTAGE BUSHING REPAIR | * | ||
| Susquehanna 1 | 100 | * | |||
| Susquehanna 2 | 94 | 100% ELECTRICAL CAPABILITY - HOT WEATHER ALERT FOR 09/24 | |||
| Three Mile Island 1 | 100 | ||||
| Vermont Yankee | 100 | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | 161 ATHENS LINE TAGGED OUT FOR MAINTENANCE AND UNION LINE OOS | |||
| Browns Ferry 2 | 81 | INCREASING POWER FOLLOWING CONTROL ROD SEQUENCE EXCHANGE - 161 ATHENS LINE TAGGED OUT FOR MAINTENANCE AND UNION LINE OOS | * | ||
| Browns Ferry 3 | 100 | 161 ATHENS LINE TAGGED OUT FOR MAINTENANCE AND UNION LINE OOS | |||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 0 | 09/17/2010 | REFUELING OUTAGE | ||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED | ||
| Farley 1 | 94 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Farley 2 | 100 | ||||
| Harris 1 | 98 | COASTDOWN TO REFUELING OUTAGE | |||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 0 | 09/11/2010 | DEFUELED. | * | |
| North Anna 2 | 100 | * | |||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 100 | ||||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 84 | COASTDOWN TO REFUELING OUTAGE | |||
| Sequoyah 2 | 100 | ||||
| Summer | 0 | 09/22/2010 | MAINTENANCE OUTAGE - SHUTDOWN TO ADDRESS LOW OIL LEVEL IN RCP "A" - ANTICIPATE RESTART IN 24-48 HOURS. | ||
| Surry 1 | 100 | HOT WEATHER ALERT FOR 09/24 | |||
| Surry 2 | 100 | HOT WEATHER ALERT FOR 09/24 | |||
| Turkey Point 3 | 0 | 09/23/2010 | REACTOR TRIP DUE TO GENERATOR PROTECTION RELAY. SEE EN #46274 | ||
| Turkey Point 4 | 100 | * | |||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 93 | HOLDING POWER FOR RX ENGR EVAL | * | ||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | * | |||
| Byron 2 | 100 | ||||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 100 | ||||
| Davis-Besse | 100 | ||||
| Dresden 2 | 100 | ||||
| Dresden 3 | 90 | COASTDOWN TO REFUELING OUTAGE. REDUCED FOR ROD SEQUENCE EXCHANGE | * | ||
| Duane Arnold | 100 | ||||
| Fermi 2 | 100 | * | |||
| Kewaunee | 100 | ||||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 95 | REDUCED POWER TO EVALUATE FEEDWATER HEATER TUBE LEAKS. | |||
| Palisades | 96 | COASTDOWN TO REFUELING OUTAGE. 345KV (COOK-2) LINE OUT OF SERVICE | * | ||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 100 |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 100 | ||||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 100 | ||||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| San Onofre 2 | 100 | ||||
| San Onofre 3 | 93 | COASTDOWN TO REFUELING OUTAGE | * | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 100 | ||||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |