Power Reactor Status Report for December 14, 2008

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 100   500KV LINE #5007 OUTAGE 12/1 THRU 12/19 - NO IMPACT ON SITE    
Peach Bottom 3 100   500KV LINE #5007 OUTAGE 12/1 THRU 12/19 - NO IMPACT ON SITE    
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100   ISO NEW ENGLAND CONTINGENCY MAY REDUCE POWER < 800 MWE, IF NECESSARY, ON 12/1 TO 12/15    
Susquehanna 1 94   100% ELECTRICAL CAPABILITY    
Susquehanna 2 100        
Three Mile Island 1 100        
Vermont Yankee 83   HOLDING DUE TO OFFSITE LINE OUTAGE *  

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 98   INCREASING POWER *  
Browns Ferry 2 100     *  
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 98   INCREASING POWER *  
Catawba 1 100     *  
Catawba 2 100        
Crystal River 3 100        
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 98   INCREASING POWER *  
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 51   INCREASING POWER *  
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 80   HOLDING FOR MAINTENANCE ON 345 KV TRANSMISSION LINE #4571    
D.C. Cook 1 0 09/20/2008 SEE EN #44507.    
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 98   100% ELECTRICAL CAPABILITY *  
Dresden 3 99   100% ELECTRICAL CAPABILITY    
Duane Arnold 95   COASTDOWN TO REFUELING OUTAGE    
Fermi 2 100   GRID RESTRICTION CONTINGENCY DUE TO LINE MAINTENANCE    
Kewaunee 100        
La Salle 1 100        
La Salle 2 76   ROD SEQUENCE EXCHANGE *  
Monticello 100        
Palisades 100        
Perry 1 100     *  
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 97   100% ELECTRICAL CAPABILITY    
Quad Cities 2 0 12/12/2008 SHUTDOWN FOR MAINTENANCE OUTAGE *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 65   PHYSICS TESTING *  
Arkansas Nuclear 2 100        
Callaway 95   INCREASING POWER *  
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 100   115KV PORT GIBSON LINE OOS    
Palo Verde 1 100        
Palo Verde 2 0 11/21/2008 GENERATOR REPAIRS COMPLETE; REASSEMBLY ONGOING    
Palo Verde 3 99   HIGH RATE BLOWDOWNS *  
River Bend 1 100        
San Onofre 2 99   STEAM GENERATOR LIMITATIONS    
San Onofre 3 0 10/12/2008 EXITING REFUELING OUTAGE    
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021