Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Beaver Valley 1 | 0 | 09/23/2007 | DEFUELED | | |
Beaver Valley 2 | 100 | | | | |
Calvert Cliffs 1 | 100 | | | | |
Calvert Cliffs 2 | 100 | | | | |
FitzPatrick | 100 | | | | |
Ginna | 100 | | | | |
Hope Creek 1 | 89 | | COASTDOWN TO REFUELING OUTAGE. 500 KV INFEED LINE (5023) OOS | * | |
Indian Point 2 | 100 | | | | |
Indian Point 3 | 100 | | | | |
Limerick 1 | 100 | | | | |
Limerick 2 | 100 | | | | |
Millstone 2 | 100 | | | | |
Millstone 3 | 100 | | | | |
Nine Mile Point 1 | 100 | | | | |
Nine Mile Point 2 | 100 | | | | |
Oyster Creek | 100 | | | | |
Peach Bottom 2 | 100 | | | | |
Peach Bottom 3 | 0 | 09/23/2007 | REFUELING OUTAGE | | |
Pilgrim 1 | 100 | | | | |
Salem 1 | 100 | | 500 KV HOPE CREEK TIE LINE (5023) OOS TILL 10/9 | | |
Salem 2 | 100 | | 500 KV HOPE CREEK TIE LINE (5023) OOS TILL 10/9 | | |
Seabrook 1 | 100 | | POWER REDUCTION THREAT DUE TO GRID WORK IN NEW ENGLAND UNTIL JANUARY | | |
Susquehanna 1 | 97 | | INCREASING POWER VOLTAGE REGULATOR IN MANUAL | * | |
Susquehanna 2 | 100 | | VOLTAGE REGULATOR IN MANUAL | | |
Three Mile Island 1 | 99 | | COASTDOWN TO REFUELING OUTAGE | | |
Vermont Yankee | 81 | | DOWNPOWER DUE TO LIMITED HOTWELL TEMP TO CONTROL COPPER CONTENT AND RIVER TEMPERATURE INCREASE | * | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Browns Ferry 1 | 100 | | | | |
Browns Ferry 2 | 100 | | | | |
Browns Ferry 3 | 75 | | CONDENSER TUBE LEAK REPAIR | * | |
Brunswick 1 | 100 | | | | |
Brunswick 2 | 100 | | | | |
Catawba 1 | 100 | | | | |
Catawba 2 | 0 | 09/14/2007 | DEFUELED | | |
Crystal River 3 | 100 | | | | |
Farley 1 | 0 | 09/28/2007 | REFUELING OUTAGE | * | |
Farley 2 | 100 | | | * | |
Harris 1 | 0 | 09/28/2007 | DEFUELED | * | |
Hatch 1 | 100 | | | | |
Hatch 2 | 100 | | | | |
McGuire 1 | 100 | | | | |
McGuire 2 | 100 | | | | |
North Anna 1 | 0 | 09/08/2007 | REFUELING OUTAGE | | |
North Anna 2 | 100 | | | | |
Oconee 1 | 100 | | | | |
Oconee 2 | 100 | | | | |
Oconee 3 | 100 | | | | |
Robinson 2 | 100 | | | | |
Saint Lucie 1 | 100 | | | | |
Saint Lucie 2 | 0 | 09/30/2007 | REFUELING OUTAGE | * | |
Sequoyah 1 | 0 | 10/03/2007 | REFUELING OUTAGE | | |
Sequoyah 2 | 100 | | | | |
Summer | 100 | | | | |
Surry 1 | 100 | | | | |
Surry 2 | 100 | | | | |
Turkey Point 3 | 0 | 09/02/2007 | REFUELING OUTAGE | | |
Turkey Point 4 | 100 | | | | |
Vogtle 1 | 97 | | 100% ELECTRICAL CAPABILITY | | |
Vogtle 2 | 98 | | 100% ELECTRICAL CAPABILITY | | |
Watts Bar 1 | 100 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Braidwood 1 | 0 | 10/01/2007 | REFUELING OUTAGE | | |
Braidwood 2 | 100 | | | | |
Byron 1 | 100 | | | | |
Byron 2 | 100 | | SYSTEM AUX TRANSFORMER (242) OFFLINE FOR PLANNED MAINTENANCE | | |
Clinton | 97 | | 100% ELECTRICAL CAPABILITY | | |
D.C. Cook 1 | 100 | | | | |
D.C. Cook 2 | 0 | 09/14/2007 | DEFUELED | | |
Davis-Besse | 100 | | | | |
Dresden 2 | 100 | | | * | |
Dresden 3 | 100 | | | | |
Duane Arnold | 98 | | 100% ELECTRICAL CAPABILITY | | |
Fermi 2 | 0 | 09/29/2007 | REFUELING OUTAGE. PLANNED MAINTENANCE ON 345 KV BROWNSTOWN LINES 2 AND 3 STARTING 9/30/07. | | |
Kewaunee | 0 | 10/04/2007 | PLANNED SHUTDOWN TO REPAIR LEAKING HYDROGEN COOLERS IN THE MAIN GENERATOR | * | |
La Salle 1 | 100 | | | | |
La Salle 2 | 100 | | | | |
Monticello | 100 | | | | |
Palisades | 0 | 09/09/2007 | REFUELING OUTAGE | | |
Perry 1 | 100 | | | | |
Point Beach 1 | 100 | | | | |
Point Beach 2 | 100 | | | * | |
Prairie Island 1 | 100 | | | | |
Prairie Island 2 | 100 | | | | |
Quad Cities 1 | 98 | | 100% ELECTRICAL CAPABILITY | | |
Quad Cities 2 | 97 | | 100% ELECTRICAL CAPABILITY | | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Arkansas Nuclear 1 | 100 | | | | |
Arkansas Nuclear 2 | 100 | | | | |
Callaway | 100 | | | | |
Columbia Generating Station | 100 | | | | |
Comanche Peak 1 | 100 | | | | |
Comanche Peak 2 | 100 | | | | |
Cooper | 100 | | | | |
Diablo Canyon 1 | 100 | | | | |
Diablo Canyon 2 | 100 | | | | |
Fort Calhoun | 100 | | | | |
Grand Gulf 1 | 100 | | | | |
Palo Verde 1 | 100 | | | | |
Palo Verde 2 | 0 | 10/06/2007 | MANUAL TRIP DUE TO CONDENSER TUBE RUPTURE. SEE EN# 43697 | * | 1 |
Palo Verde 3 | 0 | 09/29/2007 | REFUELING OUTAGE | | |
River Bend 1 | 79 | | DOWNPOWER AS A RESULT OF POWER INTERRUPTION TO MAKEUP WATER PUMPS. UNIT IS INCREASING POWER | * | |
San Onofre 2 | 99 | | STEAM GENERATOR LIMITATIONS | * | |
San Onofre 3 | 100 | | | | |
South Texas 1 | 100 | | | | |
South Texas 2 | 100 | | | | |
Waterford 3 | 100 | | | | |
Wolf Creek 1 | 100 | | | | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes: