| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | ||||
| Calvert Cliffs 2 | 100 | ||||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | ||||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 0 | 04/06/2007 | SHUTDOWN DUE TO TRANSFORMER ISSUE - PLACED UNIT ON RHR COOLING DUE TO AUX FEED PUMP LEAK - STEAM GENERATORS #33 AND 34 ISOLATED. | * | |
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | 345 KV LINE WILL BE REMOVED FROM SERVICE BETWEEN 0600-1800 HRS TODAY (LINE #383) - SOUTH BUS OUTAGE SCHEDULED FOR 0400 HRS ON 4/19 | * | ||
| Millstone 3 | 0 | 04/07/2007 | 345 KV LINE WILL BE REMOVED FROM SERVICE BETWEEN 0600-1800 HRS TODAY (LINE #383) - SOUTH BUS OUTAGE SCHEDULED FOR 0400 HRS ON 4/19 | * | |
| Nine Mile Point 1 | 85 | INCREASING POWER TO 100% | * | ||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | ||||
| Peach Bottom 3 | 100 | * | |||
| Pilgrim 1 | 0 | 04/06/2007 | REFUELING OUTAGE | ||
| Salem 1 | 1 | APPROACHING CRITICALITY | * | ||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | ||||
| Susquehanna 1 | 100 | ||||
| Susquehanna 2 | 40 | GENERATOR VOLTAGE REGULATOR IN MANUAL. HOLDING POWER TO INVESTIGATE CONDENSER AIR INLEAKAGE | |||
| Three Mile Island 1 | 100 | ||||
| Vermont Yankee | 100 | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 0 | 03/03/1985 | |||
| Browns Ferry 2 | 21 | GENERATOR OFFLINE | * | ||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 20 | GENERATOR OFFLINE | * | ||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Crystal River 3 | 100 | ||||
| Farley 1 | 100 | ||||
| Farley 2 | 0 | 04/09/2007 | REFUELING OUTAGE - CORE OFFLOAD IN PROGRESS | * | |
| Harris 1 | 100 | ||||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 0 | 03/10/2007 | REFUELING OUTAGE - CORE RELOAD COMPLETED | * | |
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 0 | 03/17/2007 | REFUELING OUTAGE | ||
| Oconee 1 | 100 | ||||
| Oconee 2 | 99 | COASTDOWN TO REFUELING OUTAGE - WILL BE REDUCING POWER AT APPROX 1%/24 HRS UNTIL RFO IS ENTERED ON 4/28 | * | ||
| Oconee 3 | 100 | ||||
| Robinson 2 | 0 | 04/06/2007 | DEFUELED | ||
| Saint Lucie 1 | 0 | 04/01/2007 | DEFUELED | ||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 100 | ||||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 98 | 100% ELECTRICAL CAPABILITY. | |||
| Vogtle 2 | 0 | 03/03/2007 | REFUELING OUTAGE | ||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 0 | 04/01/2007 | DEFUELED | ||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 100 | ||||
| Davis-Besse | 100 | JULIET BUS AND STARTUP XFRMR#1 OOS | |||
| Dresden 2 | 97 | 100% ELECTRICAL CAPABILITY | |||
| Dresden 3 | 98 | 100% ELECTRICAL CAPABILITY | |||
| Duane Arnold | 98 | 100% ELECTRICAL CAPABILITY | * | ||
| Fermi 2 | 100 | ||||
| Kewaunee | 100 | ||||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 0 | 03/13/2007 | REFUELING OUTAGE | ||
| Palisades | 100 | ||||
| Perry 1 | 0 | 04/01/2007 | REFUELING OUTAGE | ||
| Point Beach 1 | 0 | 03/31/2007 | RELOADING FUEL | * | |
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | 345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY | |||
| Prairie Island 2 | 100 | 345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY. | |||
| Quad Cities 1 | 83 | COASTDOWN TO REFUELING OUTAGE | |||
| Quad Cities 2 | 96 | 100% ELECTRICAL CAPABILITY |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 94 | COASTDOWN TO REFUELING OUTAGE | |||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 0 | 04/01/2007 | DEFUELED | ||
| Columbia Generating Station | 94 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Comanche Peak 1 | 0 | 02/24/2007 | COMING OUT OF A REFUELING OUTAGE | * | |
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 88 | INCREASING POWER FOLLOWING REACTOR FEED PUMP MAINTENANCE | * | ||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 0 | 04/12/2007 | MAINTENANCE OUTAGE TO REPAIR TURBINE LUBE OIL PROBLEM | ||
| River Bend 1 | 65 | WATER BOX CLEANING | |||
| San Onofre 2 | 99 | 100% ELECTRICAL CAPABILITY | |||
| San Onofre 3 | 100 | ||||
| South Texas 1 | 100 | ||||
| South Texas 2 | 0 | 03/25/2007 | CORE RELOAD COMPLETE | ||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |