The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for April 16, 2007

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100        
Indian Point 3 0 04/06/2007 SHUTDOWN DUE TO TRANSFORMER ISSUE    
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 0 04/07/2007 REFUELING OUTAGE    
Nine Mile Point 1 23   STARTUP TESTING IN PROGRESS *  
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 100        
Peach Bottom 3 100        
Pilgrim 1 0 04/06/2007 REFUELING OUTAGE *  
Salem 1 0 03/27/2007 REFUELING OUTAGE    
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 100        
Susquehanna 2 36   GENERATOR VOLTAGE REGULATOR IN MANUAL. HOLDING POWER TO INVESTIGATE CONDENSER AIR INLEAKAGE *  
Three Mile Island 1 100        
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 03/03/1985      
Browns Ferry 2 0 02/20/2007 STARTUP IN PROGRESS, LESS THAN 1% POWER. *  
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 0 03/02/2007 STARTUP IN PROGRESS - APPROACHING CRITICALITY *  
Catawba 1 100        
Catawba 2 100        
Crystal River 3 100        
Farley 1 100        
Farley 2 0 04/09/2007 REFUELING OUTAGE    
Harris 1 100   SILER CITY 230 KV LINE OOS STARTING AT 0800 EDT. *  
Hatch 1 100        
Hatch 2 100        
McGuire 1 0 03/10/2007 RELOADING FUEL *  
McGuire 2 100        
North Anna 1 100        
North Anna 2 0 03/17/2007 REFUELING OUTAGE    
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 0 04/06/2007 DEFUELED *  
Saint Lucie 1 0 04/01/2007 DEFUELED    
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 98   100% ELECTRICAL CAPABILITY. *  
Vogtle 2 0 03/03/2007 CORE RELOAD COMPLETE *  
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 0 04/01/2007 DEFUELED    
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100   JULIET BUS AND STARTUP XFRMR#1 OOS *  
Dresden 2 97   100% ELECTRICAL CAPABILITY    
Dresden 3 98   100% ELECTRICAL CAPABILITY    
Duane Arnold 98   100% ELECTRICAL CAPABILITY    
Fermi 2 100        
Kewaunee 100        
La Salle 1 100        
La Salle 2 75   REDUCED POWER FOR TURBINE CONTROL VALVE MAINTENANCE *  
Monticello 0 03/13/2007 REFUELING OUTAGE    
Palisades 100        
Perry 1 0 04/01/2007 REFUELING OUTAGE    
Point Beach 1 0 03/31/2007 DEFUELED.    
Point Beach 2 100        
Prairie Island 1 100   345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY    
Prairie Island 2 100   345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY.    
Quad Cities 1 83   COASTDOWN TO REFUELING OUTAGE    
Quad Cities 2 96   100% ELECTRICAL CAPABILITY *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 95   COASTDOWN TO REFUELING OUTAGE *  
Arkansas Nuclear 2 100        
Callaway 0 04/01/2007 DEFUELED    
Columbia Generating Station 92   INCREASING POWER *  
Comanche Peak 1 0 02/24/2007 REFUELING OUTAGE    
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 65   HOLDING POWER FOR REACTOR FEED PUMP MAINTENANCE *  
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 0 04/12/2007 MAINTENANCE OUTAGE TO REPAIR TURBINE LUBE OIL PROBLEM    
River Bend 1 65   WATER BOX CLEANING    
San Onofre 2 99   100% ELECTRICAL CAPABILITY    
San Onofre 3 100        
South Texas 1 100        
South Texas 2 0 03/25/2007 CORE RELOAD COMPLETE *  
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021