The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for December 9, 2006

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100     *  
Indian Point 3 100     *  
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 93   FLUX SHAPING AND CONDENSER BAY MAINTENANCE *  
Peach Bottom 2 100        
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 100   GENERATOR VOLTAGE REGULATOR IN MANUAL    
Susquehanna 2 100        
Three Mile Island 1 100     *  
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 03/03/1985 DEFUELED    
Browns Ferry 2 100   1 OF 2 161 KV LINES OOS AND 1 OF 7 500 KV LINES OOS FOR PLANNED MAINTENANCE    
Browns Ferry 3 15   1 OF 2 161 KV LINES OOS AND 1 OF 7 500 KV LINES OOS FOR PLANNED MAINTENANCE. DRYWELL LEAK INSPECTION AND 3 "B" RECIRC RBCC MAINTENANCE *  
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 0 11/10/2006 DEFUELED    
Catawba 2 64   MAIN FEED PUMP REPAIR *  
Crystal River 3 100        
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 0 10/06/2006 COMING OUT OF REFUELING OUTAGE - HEATUP IN PROGRESS *  
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 0 11/26/2006 LOADING FUEL *  
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 0 10/30/2006 REACTOR CRITICAL AT 0425 12/9/06 *  
Vogtle 1 100   100% ELECTRICAL CAPABILITY *  
Vogtle 2 100        
Watts Bar 1 85   HOLDING FOR FUEL PRECONDITIONING *  

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 96   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100   MAINTENANCE ON 69 KV OFFSITE SUPPLY LINE *  
D.C. Cook 2 100   MAINTENANCE ON 69 KV OFFSITE SUPPLY LINE *  
Davis-Besse 100        
Dresden 2 97   100% ELECTRICAL CAPABILITY    
Dresden 3 67   ROD PATTERN ADJUSTMENT *  
Duane Arnold 98   100% ELECTRICAL CAPABILITY    
Fermi 2 100        
Kewaunee 99        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 0 11/14/2006 REFUELING OUTAGE    
Quad Cities 1 97   100% ELECTRICAL CAPABILITY    
Quad Cities 2 95   100% ELECTRICAL CAPABILITY *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100   SWITCHYARD MAINTENANCE UNTIL 12/9    
Columbia Generating Station 100        
Comanche Peak 1 100     *  
Comanche Peak 2 100     *  
Cooper 100        
Diablo Canyon 1 100   MAINTENANCE ON 500 KV OUTPUT BREAKER *  
Diablo Canyon 2 100   MAINTENANCE ON 500 KV OUTPUT BREAKER *  
Fort Calhoun 70   HOLDING POWER WHILE TROUBLESHOOTING RPS TRIP UNIT    
Grand Gulf 1 100        
Palo Verde 1 99   REDUCED FOR S/G BLOWDOWNS *  
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
San Onofre 2 99   STEAM GENERATOR TUBE PLUGGING LIMITATION    
San Onofre 3 0 10/16/2006 PREPARING FOR STARTUP *  
South Texas 1 100        
South Texas 2 100        
Waterford 3 0 11/25/2006 REFUELING OUTAGE    
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.