The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for August 14, 2004

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 97   COASTDOWN TO REFUELING OUTAGE *  
Ginna 100        
Hope Creek 1 99   6A FEEDWATER HEATER OUT OF SERVICE    
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 91   PREPARING TO INCREASE POWER FOLLOWING MOISTURE SEPARATOR REHEATER MAINTENANCE *  
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 92   ROD PATTERN ADJUSTMENTS *  
Peach Bottom 2 100        
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 100        
Susquehanna 2 100        
Three Mile Island 1 100        
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 03/03/1985 DEFUELED    
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 53   TURBINE VALVE TESTING THEN LIMITED TO 630 MW (ABOUT 70%) DUE TO WEATHER RELATED LOSS OF 230KV LINE. WEATHER-RELATED UNUSUAL EVENT DECLARED (EN# 40951) *  
Brunswick 2 96   MAXIMUM OPERATING LIMIT. WEATHER-RELATED UNUSUAL EVENT DECLARED (EN# 40951) *  
Catawba 1 100        
Catawba 2 100        
Crystal River 3 96   PREPARING TO INCREASE POWER FOLLOWING REDUCTION DUE TO WEATHER RELATED GRID INSTABILITIES *  
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 99   FEEDWATER FLOW INSTRUMENTATION PROBLEMS    
Hatch 2 99   MAXIMUM OPERATING LIMIT    
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 99   INCREASING POWER FOLLOWING COMPLETION OF CONTROL ROD TESTING *  
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 95   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 36   SHUTDOWN IN PROGRESS TO REPAIR MAIN GENERATOR *  
Dresden 3 99   100% ELECTRICAL CAPABILITY    
Duane Arnold 94   100% ELECTRICAL CAPABILITY    
Fermi 2 0 08/09/2004 COLD SHUTDOWN DUE TO LCO ACTION STATEMENT FOR AN INOP DIESEL - SEE EVENT # 40932    
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 0 08/11/2004 MAINTENANCE OUTAGE *  
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 97   COASTDOWN TO REFUELING OUTAGE    
Prairie Island 2 100        
Quad Cities 1 85   LIMITED IN POWER (STEAM DRYER MONITORING)    
Quad Cities 2 85   LIMITED IN POWER (STEAM DRYER MONITORING)    

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 0 07/30/2004 MAINTENANCE OUTAGE *  
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 70   REDUCED POWER FOR SCRAM TIME TESTING *  
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 99     *  
Palo Verde 3 100        
River Bend 1 78   INCREASING POWER *  
San Onofre 2 100        
San Onofre 3 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021