Power Reactor Status Report for October 3, 2002
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BEAVER VALLEY 1 | 100 | | | | |
BEAVER VALLEY 2 | 100 | | | | |
CALVERT CLIFFS 1 | 100 | | | | |
CALVERT CLIFFS 2 | 100 | | | | |
FITZPATRICK 1 | 55 | | Power Operation REDUCED REACTOR POWER FOR REACTOR FEEDWATER PUMP "A" MAINTENANCE.
| * | |
GINNA 1 | 100 | | | | |
HOPE CREEK 1 | 100 | | | | |
INDIAN POINT 2 | 100 | | | | |
INDIAN POINT 3 | 100 | | | | |
LIMERICK 1 | 100 | | | | |
LIMERICK 2 | 100 | | | | |
MILLSTONE 2 | 100 | | | | |
MILLSTONE 3 | 0 | 09/06/2002 | Hot Standby REFUELING OUTAGE
| * | |
NINE MILE POINT 1 | 100 | | | | |
NINE MILE POINT 2 | 100 | | | | |
OYSTER CREEK 1 | 98 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| | |
PEACH BOTTOM 2 | 15 | | Power Operation INCREASING POWER
| * | |
PEACH BOTTOM 3 | 100 | | | | |
PILGRIM 1 | 100 | | | | |
SALEM 1 | 100 | | | | |
SALEM 2 | 100 | | | | |
SEABROOK 1 | 100 | | | | |
SUSQUEHANNA 1 | 100 | | Power Operation UNUSUAL EVENT DECLARED. FOR DETAILS SEE EVENT # 39241.
| * | |
SUSQUEHANNA 2 | 0 | 10/03/2002 | Hot Shutdown UNUSUAL EVENT. FOR DETAILS SEE EVENT # 39241
| * | 1 |
THREE MILE ISLAND 1 | 100 | | | | |
VERMONT YANKEE 1 | 93 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BROWNS FERRY 1 | 0 | 03/03/1985 | Refueling DEFUELED
| | |
BROWNS FERRY 2 | 90 | | Power Operation HOLDING AT REDUCED POWER DUE TO FUEL LEAKAGE
| | |
BROWNS FERRY 3 | 100 | | | | |
BRUNSWICK 1 | 89 | | Power Operation INCREASING POWER
| * | |
BRUNSWICK 2 | 100 | | | | |
CATAWBA 1 | 100 | | | | |
CATAWBA 2 | 100 | | | | |
CRYSTAL RIVER 3 | 100 | | | | |
FARLEY 1 | 100 | | | | |
FARLEY 2 | 0 | 09/13/2002 | Refueling REFUELING OUTAGE - LOADING FUEL
| | |
HARRIS 1 | 100 | | | | |
HATCH 1 | 100 | | | | |
HATCH 2 | 100 | | | | |
MCGUIRE 1 | 0 | 09/13/2002 | Refueling REFUELING OUTAGE
| | |
MCGUIRE 2 | 100 | | | | |
NORTH ANNA 1 | 100 | | Power Operation UE DECLARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.3FT.
| | |
NORTH ANNA 2 | 0 | 09/07/2002 | Refueling UE DECLARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.3FT REFUELING OUTAGE - DEFUELED
| | |
OCONEE 1 | 100 | | | | |
OCONEE 2 | 99 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| | |
OCONEE 3 | 100 | | | | |
ROBINSON 2 | 98 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| * | |
SAINT LUCIE 1 | 0 | 09/29/2002 | Cold Shutdown REFUELING OUTAGE
| | |
SAINT LUCIE 2 | 100 | | | | |
SEQUOYAH 1 | 100 | | | | |
SEQUOYAH 2 | 100 | | | | |
SUMMER 1 | 100 | | | | |
SURRY 1 | 100 | | | | |
SURRY 2 | 100 | | | | |
TURKEY POINT 3 | 100 | | | | |
TURKEY POINT 4 | 100 | | | | |
VOGTLE 1 | 100 | | | | |
VOGTLE 2 | 94 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| | |
WATTS BAR 1 | 100 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BRAIDWOOD 1 | 100 | | | | |
BRAIDWOOD 2 | 100 | | | | |
BYRON 1 | 100 | | | | |
BYRON 2 | 0 | 09/16/2002 | Hot Standby GOING TO MODE 4 - TURBINE PROBLEM.
| * | |
CLINTON 1 | 93 | | Power Operation 100% ELECTRICAL CAPABILITY
| | |
COOK 1 | 100 | | | | |
COOK 2 | 100 | | | | |
DAVIS BESSE 1 | 0 | 02/15/2002 | Refueling REFUELING OUTAGE - DEFUELED
| | |
DRESDEN 2 | 98 | | Power Operation 100% ELECTRICAL CAPABILITY
| | |
DRESDEN 3 | 86 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| | |
DUANE ARNOLD 1 | 94 | | Power Operation 100% ELECTRICAL CAPABILITY
| | |
FERMI 2 | 0 | 10/02/2002 | Hot Shutdown AUTOMATIC REACTOR SCRAM DUE TO LOSS OF CONDENSER VACUUM. SEE EVENT # 39239FOR DETAILS.
| * | 1 |
KEWAUNEE 1 | 100 | | | | |
LASALLE 1 | 100 | | | | |
LASALLE 2 | 100 | | | | |
MONTICELLO 1 | 100 | | | | |
PALISADES 1 | 100 | | | | |
PERRY 1 | 0 | 09/21/2002 | Cold Shutdown FORCED OUTAGE
| | |
POINT BEACH 1 | 0 | 09/13/2002 | Refueling REFUELING OUTAGE
| | |
POINT BEACH 2 | 100 | | | | |
PRAIRIE ISLAND 1 | 100 | | | | |
PRAIRIE ISLAND 2 | 100 | | | | |
QUAD CITIES 1 | 100 | | | | |
QUAD CITIES 2 | 97 | | Power Operation 100% ELECTRICAL CAPABILITY
| | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
ARKANSAS NUCLEAR 1 | 73 | | Power Operation COASTDOWN TO REFUELING OUTAGE
| * | |
ARKANSAS NUCLEAR 2 | 100 | | | | |
CALLAWAY 1 | 100 | | | | |
COLUMBIA GENERATING | 100 | | | | |
COMANCHE PEAK 1 | 0 | 09/27/2002 | Cold Shutdown REFUELING OUTAGE
| | |
COMANCHE PEAK 2 | 99 | | | | |
COOPER 1 | 100 | | | | |
DIABLO CANYON 1 | 98 | | Power Operation LIMITED DUE TO HIGH TURBINE GENERATOR VIBRATION
| | |
DIABLO CANYON 2 | 100 | | | | |
FT CALHOUN 1 | 100 | | | | |
GRAND GULF 1 | 0 | 09/13/2002 | Refueling REFUELING OUTAGE
| | |
PALO VERDE 1 | 0 | 09/27/2002 | Cold Shutdown REFUELING OUTAGE
| | |
PALO VERDE 2 | 98 | | Power Operation TEMPERATURE LIMITED
| | |
PALO VERDE 3 | 99 | | Power Operation TEMPERATURE LIMITED
| | |
RIVER BEND 1 | 100 | | | | |
SAN ONOFRE 2 | 100 | | | | |
SAN ONOFRE 3 | 100 | | | | |
SOUTH TEXAS 1 | 100 | | | | |
SOUTH TEXAS 2 | 0 | 10/01/2002 | Hot Standby REFUELING OUTAGE
| | |
WATERFORD 3 | 100 | | | | |
WOLF CREEK 1 | 100 | | | | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.