Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BEAVER VALLEY 1 | 100.00000 | | | | |
BEAVER VALLEY 2 | 100.00000 | | | | |
CALVERT CLIFFS 1 | 100.00000 | | | | |
CALVERT CLIFFS 2 | 90.00000 | | G WATERBOXESCLEANING WATERBOXES
| * | |
FITZPATRICK 1 | 100.00000 | | | | |
GINNA 1 | 100.00000 | | | | |
HOPE CREEK 1 | 100.00000 | | | | |
INDIAN POINT 2 | 100.00000 | | | | |
INDIAN POINT 3 | 100.00000 | | | | |
LIMERICK 1 | 100.00000 | | | | |
LIMERICK 2 | 100.00000 | | | | |
MILLSTONE 2 | 100.00000 | | | | |
MILLSTONE 3 | 0.00000 | 09/06/2002 | NG OUTAGEREFUELING OUTAGE
| * | |
NINE MILE POINT 1 | 100.00000 | | | | |
NINE MILE POINT 2 | 100.00000 | | | | |
OYSTER CREEK 1 | 100.00000 | | | | |
PEACH BOTTOM 2 | 87.00000 | | WN TO REFUELING OUTAGECOASTDOWN TO REFUELING OUTAGE
| | |
PEACH BOTTOM 3 | 65.00000 | | ING SCRAM TIME TESTINGPERFORMING SCRAM TIME TESTING
| * | |
PILGRIM 1 | 100.00000 | | | | |
SALEM 1 | 100.00000 | | | | |
SALEM 2 | 100.00000 | | | | |
SEABROOK 1 | 100.00000 | | | | |
SUSQUEHANNA 1 | 100.00000 | | | | |
SUSQUEHANNA 2 | 100.00000 | | | | |
THREE MILE ISLAND 1 | 100.00000 | | | | |
VERMONT YANKEE 1 | 100.00000 | | | | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BROWNS FERRY 1 | 0.00000 | 03/03/1985 | DDEFUELED
| | |
BROWNS FERRY 2 | 63.00000 | | UPPRESSION TESTINGPOWER SUPPRESSION TESTING
| * | |
BROWNS FERRY 3 | 100.00000 | | | | |
BRUNSWICK 1 | 94.00000 | | ECTRICAL CAPABILITY100% ELECTRICAL CAPABILITY
| | |
BRUNSWICK 2 | 100.00000 | | | | |
CATAWBA 1 | 100.00000 | | | | |
CATAWBA 2 | 100.00000 | | | | |
CRYSTAL RIVER 3 | 100.00000 | | | | |
FARLEY 1 | 100.00000 | | | | |
FARLEY 2 | 98.00000 | | WN FOR REFUELING OUTAGECOASTDOWN FOR REFUELING OUTAGE
| * | |
HARRIS 1 | 100.00000 | | | | |
HATCH 1 | 100.00000 | | | | |
HATCH 2 | 69.00000 | | UENCE EXCHANGEROD SEQUENCE EXCHANGE
| * | |
MCGUIRE 1 | 99.00000 | | | | |
MCGUIRE 2 | 100.00000 | | | | |
NORTH ANNA 1 | 100.00000 | | ARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.7 FT.UE DECLARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.7 FT.
| * | |
NORTH ANNA 2 | 100.00000 | | ARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.7 FTUE DECLARED DUE TO LAKE LEVEL BELOW 246.0 FT - CURRENT LAKE LEVEL IS 245.7 FT
| * | |
OCONEE 1 | 100.00000 | | | | |
OCONEE 2 | 100.00000 | | | | |
OCONEE 3 | 100.00000 | | | | |
ROBINSON 2 | 100.00000 | | | | |
SAINT LUCIE 1 | 100.00000 | | | | |
SAINT LUCIE 2 | 100.00000 | | | | |
SEQUOYAH 1 | 100.00000 | | | | |
SEQUOYAH 2 | 100.00000 | | | | |
SUMMER 1 | 100.00000 | | | | |
SURRY 1 | 74.00000 | | G POWER TO PERFORM FEED PUMP MAINTENANCEREDUCING POWER TO PERFORM FEED PUMP MAINTENANCE
| * | |
SURRY 2 | 100.00000 | | | | |
TURKEY POINT 3 | 100.00000 | | | | |
TURKEY POINT 4 | 100.00000 | | | | |
VOGTLE 1 | 100.00000 | | | | |
VOGTLE 2 | 100.00000 | | | | |
WATTS BAR 1 | 100.00000 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BRAIDWOOD 1 | 100.00000 | | | | |
BRAIDWOOD 2 | 100.00000 | | | | |
BYRON 1 | 100.00000 | | | | |
BYRON 2 | 99.00000 | | WN TO REFUELING OUTAGECOASTDOWN TO REFUELING OUTAGE
| * | |
CLINTON 1 | 94.00000 | | ECTRICAL CAPABILITY100% ELECTRICAL CAPABILITY
| | |
COOK 1 | 100.00000 | | | | |
COOK 2 | 100.00000 | | | | |
DAVIS BESSE 1 | 0.00000 | 02/15/2002 | NG OUTAGE - DEFUELEDREFUELING OUTAGE - DEFUELED
| | |
DRESDEN 2 | 98.00000 | | ECTRICAL CAPABILITY100% ELECTRICAL CAPABILITY
| | |
DRESDEN 3 | 90.00000 | | WN TO REFUELING OUTAGECOASTDOWN TO REFUELING OUTAGE
| * | |
DUANE ARNOLD 1 | 0.00000 | 09/02/2002 | HUTDOWN FOR MAINTENANCE. SEE EVENT # 39164.PLANT SHUTDOWN FOR MAINTENANCE. SEE EVENT # 39164.
| | |
FERMI 2 | 100.00000 | | | | |
KEWAUNEE 1 | 100.00000 | | | | |
LASALLE 1 | 100.00000 | | | | |
LASALLE 2 | 60.00000 | | UPPRESSION TESTINGPOWER SUPPRESSION TESTING
| * | |
MONTICELLO 1 | 100.00000 | | | | |
PALISADES 1 | 100.00000 | | | | |
PERRY 1 | 100.00000 | | | | |
POINT BEACH 1 | 100.00000 | | | | |
POINT BEACH 2 | 100.00000 | | | | |
PRAIRIE ISLAND 1 | 100.00000 | | | | |
PRAIRIE ISLAND 2 | 100.00000 | | | | |
QUAD CITIES 1 | 95.00000 | | WN TO REFUELING OUTAGECOASTDOWN TO REFUELING OUTAGE
| * | |
QUAD CITIES 2 | 98.00000 | | ECTRICAL CAPABILITY100% ELECTRICAL CAPABILITY
| | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
ARKANSAS NUCLEAR 1 | 99.00000 | | | * | |
ARKANSAS NUCLEAR 2 | 100.00000 | | | | |
CALLAWAY 1 | 100.00000 | | | | |
COLUMBIA GENERATING | 100.00000 | | | | |
COMANCHE PEAK 1 | 100.00000 | | | | |
COMANCHE PEAK 2 | 99.00000 | | ECTRICAL CAPABILITY100% ELECTRICAL CAPABILITY
| | |
COOPER 1 | 100.00000 | | | | |
DIABLO CANYON 1 | 98.00000 | | due to high turbine vibrationLimited due to high turbine vibration
| | |
DIABLO CANYON 2 | 100.00000 | | | | |
FT CALHOUN 1 | 100.00000 | | | * | |
GRAND GULF 1 | 87.00000 | | WN TO REFUELING OUTAGECOASTDOWN TO REFUELING OUTAGE
| | |
PALO VERDE 1 | 99.00000 | | | | |
PALO VERDE 2 | 98.00000 | | | | |
PALO VERDE 3 | 99.00000 | | | | |
RIVER BEND 1 | 100.00000 | | | | |
SAN ONOFRE 2 | 100.00000 | | | | |
SAN ONOFRE 3 | 100.00000 | | | | |
SOUTH TEXAS 1 | 100.00000 | | | | |
SOUTH TEXAS 2 | 100.00000 | | | | |
WATERFORD 3 | 100.00000 | | | * | |
WOLF CREEK 1 | 100.00000 | | | | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours