The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for May 14, 2002

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BEAVER VALLEY 1 100        
BEAVER VALLEY 2 100        
CALVERT CLIFFS 1 0 02/15/2002 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS *  
CALVERT CLIFFS 2 100        
FITZPATRICK 1 100        
GINNA 1 100        
HOPE CREEK 1 91   INCREASING POWER AFTER HOLDING POWER AT APPROXIMATELY 71% FOLLOWING A SIGNIFICANT ELECTRICAL TRANSIENT DUE TO AN UNEXPECTED LIGHTNING STRIKE ON 05/13/02 (Refer to event #38918) *  
INDIAN POINT 2 100        
INDIAN POINT 3 100        
LIMERICK 1 100        
LIMERICK 2 100        
MILLSTONE 2 100        
MILLSTONE 3 100        
NINE MILE POINT 1 100        
NINE MILE POINT 2 100     *  
OYSTER CREEK 1 100        
PEACH BOTTOM 2 100        
PEACH BOTTOM 3 100        
PILGRIM 1 100        
SALEM 1 100        
SALEM 2 0 04/04/2002 REFUELING OUTAGE    
SEABROOK 1 0 05/04/2002 REFUELING OUTAGE - DEFUELED    
SUSQUEHANNA 1 100     *  
SUSQUEHANNA 2 100        
THREE MILE ISLAND 1 100        
VERMONT YANKEE 1 0 05/11/2002 MID-CYCLE MAINTENANCE OUTAGE TO REPLACE FAILED FUEL - REACTOR VESSEL HEAD REMOVED *  

Region 2

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BROWNS FERRY 1 0 03/03/1985 DEFUELED    
BROWNS FERRY 2 100        
BROWNS FERRY 3 100        
BRUNSWICK 1 100        
BRUNSWICK 2 100        
CATAWBA 1 0 04/26/2002 REFUELING OUTAGE    
CATAWBA 2 100        
CRYSTAL RIVER 3 100        
FARLEY 1 100        
FARLEY 2 100        
HARRIS 1 100        
HATCH 1 100        
HATCH 2 100        
MCGUIRE 1 100        
MCGUIRE 2 100        
NORTH ANNA 1 100        
NORTH ANNA 2 100        
OCONEE 1 100        
OCONEE 2 100        
OCONEE 3 100        
ROBINSON 2 100        
SAINT LUCIE 1 100        
SAINT LUCIE 2 100        
SEQUOYAH 1 100        
SEQUOYAH 2 0 04/14/2002 REFUELING OUTAGE    
SUMMER 1 0 04/19/2002 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS *  
SURRY 1 100        
SURRY 2 100        
TURKEY POINT 3 100        
TURKEY POINT 4 100        
VOGTLE 1 100        
VOGTLE 2 100        
WATTS BAR 1 100        

Region 3

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BRAIDWOOD 1 100        
BRAIDWOOD 2 94   INCREASING POWER AFTER EXITING A REFUELING OUTAGE *  
BYRON 1 99     *  
BYRON 2 99   MEASURED STEAM GENERATOR TUBE LEAKAGE = 38 GPD *  
CLINTON 1 8   PREPARING TO PLACE THE UNIT ON LINE AFTER RECOVERING FROM AN AUTOMATIC REACTOR SCRAM FROM 86% POWER ON HIGH WATER LEVEL DUE TO THE FAILURE OF THE STARTUP LEVEL CONTROLLER DURING EXTENDED POWER UPRATE TESTING ON 05/13/02 (Refer to event #38916) *  
COOK 1 0 05/04/2002 REFUELING OUTAGE - DEFUELED *  
COOK 2 0 05/12/2002 AUTOMATIC REACTOR TRIP FROM 100% POWER DUE TO AN INSTRUMENTATION RACK POWER SUPPLY FAILURE WHICH CAUSED A STEAM GENERATOR FEEDWATER REGULATING VALVE TO FAIL CLOSED (Refer to event #38915)    
DAVIS BESSE 1 0 02/15/2002 REFUELING OUTAGE - FUEL SHUFFLE COMPLETE    
DRESDEN 2 97   100% ELECTRICAL CAPABILITY    
DRESDEN 3 100        
DUANE ARNOLD 1 94   100% ELECTRICAL CAPABILITY    
FERMI 2 100        
KEWAUNEE 1 0 05/05/2002 MAINTENANCE OUTAGE    
LASALLE 1 100        
LASALLE 2 100        
MONTICELLO 1 100        
PALISADES 1 100        
PERRY 1 100        
POINT BEACH 1 100        
POINT BEACH 2 15   PREPARING TO PLACE THE UNIT ON LINE TO EXIT A REFUELING OUTAGE *  
PRAIRIE ISLAND 1 100        
PRAIRIE ISLAND 2 100        
QUAD CITIES 1 97   INCREASING POWER AFTER DECREASING TO 95% POWER TO PERFORM A ROD PATTERN ADJUSTMENT *  
QUAD CITIES 2 96   100% ELECTRICAL POWER    

Region 4

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
ARKANSAS NUCLEAR 1 100        
ARKANSAS NUCLEAR 2 97   HOLDING POWER AT THIS LEVEL TO PERFORM POWER UPRATE TESTING AFTER EXITING A REFUELING OUTAGE *  
CALLAWAY 1 100        
COLUMBIA GENERATING 100        
COMANCHE PEAK 1 100        
COMANCHE PEAK 2 86   INCREASING POWER AFTER DECREASING TO 54% POWER TO REPAIR THE 'A' MAIN FEEDWATER PUMP *  
COOPER 1 14   HOLDING POWER AT THIS LEVEL WITH THE UNIT OFF LINE (05/14/02) TO PERFORM GENERATOR TROUBLESHOOTING DUE TO POTENTIAL TRANSFORMER ARCING (FUSE PROBLEM) *  
DIABLO CANYON 1 0 04/28/2002 REFUELING OUTAGE - REFUELED *  
DIABLO CANYON 2 100        
FT CALHOUN 1 0 05/03/2002 REFUELING OUTAGE - FUEL OFFLOAD IN PROGRESS    
GRAND GULF 1 100        
PALO VERDE 1 99        
PALO VERDE 2 97        
PALO VERDE 3 99        
RIVER BEND 1 0 05/12/2002 MAINTENANCE OUTAGE *  
SAN ONOFRE 2 99   COASTDOWN TO REFUELING OUTAGE *  
SAN ONOFRE 3 100        
SOUTH TEXAS 1 98     *  
SOUTH TEXAS 2 100        
WATERFORD 3 100        
WOLF CREEK 1 0 05/13/2002 MAINTENANCE OUTAGE *  

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.