Power Reactor Status Report for March 26, 2002
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BEAVER VALLEY 1 | 100 | ||||
| BEAVER VALLEY 2 | 100 | ||||
| CALVERT CLIFFS 1 | 0 | 02/15/2002 | REFUELING OUTAGE - DEFUELED | ||
| CALVERT CLIFFS 2 | 100 | ||||
| FITZPATRICK 1 | 100 | ||||
| GINNA 1 | 0 | 03/18/2002 | REFUELING OUTAGE - FUEL OFFLOAD IN PROGRESS | ||
| HOPE CREEK 1 | 100 | * | |||
| INDIAN POINT 2 | 100 | ||||
| INDIAN POINT 3 | 100 | ||||
| LIMERICK 1 | 75 | HOLDING POWER AT THIS LEVEL TO RETURN A CONDENSATE PUMP TO SERVICE FOLLOWING REPAIRS | * | ||
| LIMERICK 2 | 100 | ||||
| MILLSTONE 2 | 0 | 02/15/2002 | REFUELING OUTAGE | ||
| MILLSTONE 3 | 100 | ||||
| NINE MILE POINT 1 | 100 | ||||
| NINE MILE POINT 2 | 0 | 03/15/2002 | REFUELING OUTAGE - FIRST PHASE OF FUEL SHUFFLE COMPLETE | * | |
| OYSTER CREEK 1 | 100 | ||||
| PEACH BOTTOM 2 | 100 | ||||
| PEACH BOTTOM 3 | 82 | HOLDING POWER AT THIS LEVEL DUE TO A CONDENSATE PUMP PROBLEM | |||
| PILGRIM 1 | 100 | ||||
| SALEM 1 | 100 | ||||
| SALEM 2 | 100 | ||||
| SEABROOK 1 | 100 | ||||
| SUSQUEHANNA 1 | 0 | 03/02/2002 | REFUELING OUTAGE - REFUELED | ||
| SUSQUEHANNA 2 | 100 | ||||
| THREE MILE ISLAND 1 | 100 | ||||
| VERMONT YANKEE 1 | 91 | HOLDING POWER AT THIS LEVEL DUE TO FUEL PIN LEAKS | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | ||
| BROWNS FERRY 2 | 94 | INCREASING POWER (PRECONDITIONING) AFTER DECREASING TO 85% POWER TO PERFORM ROD ADJUSTMENTS | * | ||
| BROWNS FERRY 3 | 23 | PREPARING TO ENTER A REFUELING OUTAGE | * | ||
| BRUNSWICK 1 | 0 | 03/01/2002 | REFUELING OUTAGE | ||
| BRUNSWICK 2 | 100 | ||||
| CATAWBA 1 | 100 | ||||
| CATAWBA 2 | 100 | ||||
| CRYSTAL RIVER 3 | 100 | ||||
| FARLEY 1 | 100 | ||||
| FARLEY 2 | 100 | ||||
| HARRIS 1 | 100 | ||||
| HATCH 1 | 0 | 03/23/2002 | REFUELING OUTAGE - PREPARING FOR FUEL SHUFFLE | ||
| HATCH 2 | 100 | ||||
| MCGUIRE 1 | 100 | ||||
| MCGUIRE 2 | 0 | 02/22/2002 | REFUELING OUTAGE | ||
| NORTH ANNA 1 | 100 | ||||
| NORTH ANNA 2 | 100 | ||||
| OCONEE 1 | 0 | 03/23/2002 | REFUELING OUTAGE - PREPARING FOR MID-LOOP OPERATIONS | * | |
| OCONEE 2 | 100 | ||||
| OCONEE 3 | 100 | ||||
| ROBINSON 2 | 100 | ||||
| SAINT LUCIE 1 | 100 | ||||
| SAINT LUCIE 2 | 100 | ||||
| SEQUOYAH 1 | 100 | ||||
| SEQUOYAH 2 | 100 | ||||
| SUMMER 1 | 100 | ||||
| SURRY 1 | 100 | ||||
| SURRY 2 | 0 | 03/24/2002 | REFUELING OUTAGE | ||
| TURKEY POINT 3 | 100 | ||||
| TURKEY POINT 4 | 0 | 03/23/2002 | REFUELING OUTAGE - REACTOR VESSEL HEAD DETENSIONED | * | |
| VOGTLE 1 | 0 | 03/06/2002 | REFUELING OUTAGE - DEFUELED | ||
| VOGTLE 2 | 100 | ||||
| WATTS BAR 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BRAIDWOOD 1 | 100 | ||||
| BRAIDWOOD 2 | 96 | 100% ELECTRICAL CAPABILITY | |||
| BYRON 1 | 0 | 03/11/2002 | REFUELING OUTAGE | ||
| BYRON 2 | 100 | MEASURED STEAM GENERATOR TUBE LEAKAGE LESS THAN 5 GPD | |||
| CLINTON 1 | 98 | COASTDOWN TO REFUELING OUTAGE | |||
| COOK 1 | 100 | ||||
| COOK 2 | 100 | ||||
| DAVIS BESSE 1 | 0 | 02/15/2002 | REFUELING OUTAGE - REFUELED | ||
| DRESDEN 2 | 95 | 100% ELECTRICAL CAPABILITY | |||
| DRESDEN 3 | 100 | ||||
| DUANE ARNOLD 1 | 94 | 100% ELECTRICAL CAPABILITY | |||
| FERMI 2 | 100 | ||||
| KEWAUNEE 1 | 100 | ||||
| LASALLE 1 | 100 | ||||
| LASALLE 2 | 100 | ||||
| MONTICELLO 1 | 100 | ||||
| PALISADES 1 | 100 | ||||
| PERRY 1 | 100 | ||||
| POINT BEACH 1 | 100 | ||||
| POINT BEACH 2 | 100 | ||||
| PRAIRIE ISLAND 1 | 100 | ||||
| PRAIRIE ISLAND 2 | 100 | ||||
| QUAD CITIES 1 | 100 | ||||
| QUAD CITIES 2 | 95 | 100% ELECTRICAL CAPABILITY |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| ARKANSAS NUCLEAR 1 | 100 | ||||
| ARKANSAS NUCLEAR 2 | 99 | * | |||
| CALLAWAY 1 | 100 | ||||
| COLUMBIA GENERATING | 100 | ||||
| COMANCHE PEAK 1 | 100 | ||||
| COMANCHE PEAK 2 | 97 | COASTDOWN TO REFUELING OUTAGE | * | ||
| COOPER 1 | 100 | * | |||
| DIABLO CANYON 1 | 100 | ||||
| DIABLO CANYON 2 | 100 | ||||
| FT CALHOUN 1 | 98 | ||||
| GRAND GULF 1 | 100 | ||||
| PALO VERDE 1 | 99 | ||||
| PALO VERDE 2 | 0 | 03/15/2002 | REFUELING OUTAGE - DEFUELED | * | |
| PALO VERDE 3 | 99 | ||||
| RIVER BEND 1 | 100 | ||||
| SAN ONOFRE 2 | 100 | ||||
| SAN ONOFRE 3 | 100 | ||||
| SOUTH TEXAS 1 | 100 | ||||
| SOUTH TEXAS 2 | 100 | ||||
| WATERFORD 3 | 0 | 03/22/2002 | REFUELING OUTAGE | * | |
| WOLF CREEK 1 | 0 | 03/23/2002 | REFUELING OUTAGE |