Power Reactor Status Report for November 3, 2001
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BEAVER VALLEY 1 | 100 | | | * | |
BEAVER VALLEY 2 | 100 | | | | |
CALVERT CLIFFS 1 | 100 | | | | |
CALVERT CLIFFS 2 | 100 | | | | |
FITZPATRICK 1 | 100 | | | | |
GINNA 1 | 100 | | | | |
HOPE CREEK 1 | 0 | 10/09/2001 | REFUELING OUTAGE - STARTUP IN PROGRESS | * | |
INDIAN POINT 2 | 0 | 10/26/2001 | MAINTENANCE OUTAGE | | |
INDIAN POINT 3 | 100 | | | | |
LIMERICK 1 | 100 | | | | |
LIMERICK 2 | 100 | | | | |
MILLSTONE 2 | 100 | | | | |
MILLSTONE 3 | 100 | | | | |
NINE MILE POINT 1 | 100 | | | | |
NINE MILE POINT 2 | 100 | | | | |
OYSTER CREEK 1 | 100 | | | | |
PEACH BOTTOM 2 | 100 | | | | |
PEACH BOTTOM 3 | 74 | | INCREASING POWER AFTER DECREASING TO 60% TO PERFORM A ROD PATTERN ADJUSTMENT | * | |
PILGRIM 1 | 100 | | | | |
SALEM 1 | 100 | | | | |
SALEM 2 | 100 | | | | |
SEABROOK 1 | 100 | | | | |
SUSQUEHANNA 1 | 100 | | | | |
SUSQUEHANNA 2 | 100 | | | | |
THREE MILE ISLAND 1 | 0 | 10/08/2001 | REFUELING OUTAGE - FUEL RELOAD IN PROGRESS | * | |
VERMONT YANKEE 1 | 100 | | | | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | | |
BROWNS FERRY 2 | 100 | | | | |
BROWNS FERRY 3 | 100 | | | | |
BRUNSWICK 1 | 100 | | | | |
BRUNSWICK 2 | 100 | | | | |
CATAWBA 1 | 100 | | | | |
CATAWBA 2 | 100 | | | | |
CRYSTAL RIVER 3 | 100 | | | | |
FARLEY 1 | 0 | 10/05/2001 | REFUELING OUTAGE - HEAD DETENSIONED - PREPARING FOR HEAD LIFT | * | |
FARLEY 2 | 100 | | | | |
HARRIS 1 | 0 | 09/21/2001 | REFUELING OUTAGE - DEFUELED | | |
HATCH 1 | 100 | | | | |
HATCH 2 | 100 | | | * | |
MCGUIRE 1 | 100 | | | | |
MCGUIRE 2 | 100 | | | | |
NORTH ANNA 1 | 100 | | | | |
NORTH ANNA 2 | 0 | 10/28/2001 | MAINTENANCE OUTAGE - HEAD DETENSIONED - PREPARING TO LIFT HEAD FOR INSPECTION | * | |
OCONEE 1 | 100 | | | | |
OCONEE 2 | 100 | | | | |
OCONEE 3 | 100 | | | | |
ROBINSON 2 | 100 | | | | |
SAINT LUCIE 1 | 100 | | | | |
SAINT LUCIE 2 | 100 | | | | |
SEQUOYAH 1 | 0 | 10/21/2001 | REFUELING OUTAGE - DEFUELED | | |
SEQUOYAH 2 | 100 | | | | |
SUMMER 1 | 100 | | | | |
SURRY 1 | 0 | 10/14/2001 | REFUELING OUTAGE - FUEL RELOAD IN PROGRESS | * | |
SURRY 2 | 100 | | | | |
TURKEY POINT 3 | 94 | | HOLDING POWER AT THIS LEVEL TO TROUBLESHOOT A TURBINE VALVE PROBLEM | * | |
TURKEY POINT 4 | 100 | | | | |
VOGTLE 1 | 100 | | | | |
VOGTLE 2 | 100 | | | | |
WATTS BAR 1 | 100 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BRAIDWOOD 1 | 100 | | | | |
BRAIDWOOD 2 | 84 | | HOLDING POWER AT THIS LEVEL DUE TO TURBINE GENERATOR VIBRATION | | |
BYRON 1 | 99 | | 100% OF RATED ELECTRICAL CAPABILITY | | |
BYRON 2 | 100 | | | | |
CLINTON 1 | 100 | | | | |
COOK 1 | 100 | | | | |
COOK 2 | 100 | | | | |
DAVIS BESSE 1 | 100 | | | | |
DRESDEN 2 | 0 | 10/20/2001 | REFUELING OUTAGE - PREPARING FOR HYDRO | * | |
DRESDEN 3 | 100 | | | | |
DUANE ARNOLD 1 | 100 | | | | |
FERMI 2 | 0 | 10/27/2001 | REFUELING OUTAGE - FUEL SHUFFLE IN PROGRESS | * | |
KEWAUNEE 1 | 0 | 09/23/2001 | REFUELING OUTAGE - DEFUELED | | |
LASALLE 1 | 100 | | | | |
LASALLE 2 | 100 | | | | |
MONTICELLO 1 | 7 | | PREPARING TO TAKE THE UNIT OFF LINE TO ENTER A REFUELING OUTAGE | * | |
PALISADES 1 | 0 | 06/20/2001 | MAINTENANCE OUTAGE | | |
PERRY 1 | 100 | | | | |
POINT BEACH 1 | 100 | | | | |
POINT BEACH 2 | 100 | | | | |
PRAIRIE ISLAND 1 | 100 | | | | |
PRAIRIE ISLAND 2 | 6 | | INCREASING POWER - PREPARING TO PLACE THE UNIT ON LINE AFTER RECOVERING FROM A MANUAL REACTOR TRIP DUE TO A STEAM LEAK ON 10/31/01 (Refer to event #38448) | * | |
QUAD CITIES 1 | 100 | | | | |
QUAD CITIES 2 | 100 | | | | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
ARKANSAS NUCLEAR 1 | 100 | | | | |
ARKANSAS NUCLEAR 2 | 18 | | HOLDING POWER AT THIS LEVEL TO WAIT FOR AS-TILT VALUES TO COME BACK INTO SPEC AFTER RECOVERING FROM AN AUTOMATIC REACTOR TRIP FROM 22% POWER DURING CEA TROUBLESHOOTING ON 11/01/01 (Refer to event #38457) | * | |
CALLAWAY 1 | 100 | | | | |
COLUMBIA GENERATING | 100 | | | | |
COMANCHE PEAK 1 | 100 | | | | |
COMANCHE PEAK 2 | 100 | | | | |
COOPER 1 | 17 | | PREPARING TO TAKE THE UNIT OFF LINE TO ENTER A REFUELING OUTAGE | * | |
DIABLO CANYON 1 | 100 | | | | |
DIABLO CANYON 2 | 100 | | | | |
FT CALHOUN 1 | 100 | | | | |
GRAND GULF 1 | 100 | | | | |
PALO VERDE 1 | 96 | | HOLDING POWER AT THIS LEVEL TO PERFORM WEEKLY STEAM GENERATOR BLOWDOWNS | * | |
PALO VERDE 2 | 0 | 10/10/2001 | MAINTENANCE OUTAGE | | |
PALO VERDE 3 | 0 | 09/28/2001 | REFUELING OUTAGE | * | |
RIVER BEND 1 | 100 | | | | |
SAN ONOFRE 2 | 100 | | | | |
SAN ONOFRE 3 | 100 | | | | |
SOUTH TEXAS 1 | 100 | | | | |
SOUTH TEXAS 2 | 100 | | | | |
WATERFORD 3 | 100 | | | | |
WOLF CREEK 1 | 100 | | | | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.
Page Last Reviewed/Updated Thursday, March 25, 2021