Power Reactor Status Report for November 10, 1999
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BEAVER VALLEY 1 | 100 | ||||
| BEAVER VALLEY 2 | 100 | ||||
| CALVERT CLIFFS 1 | 100 | ||||
| CALVERT CLIFFS 2 | 100 | ||||
| FITZPATRICK 1 | 0 | 11/05/1999 | STARTUP IN PROGRESS AFTER PERFORMING NOBLE METAL INJECTION | * | |
| GINNA 1 | 100 | ||||
| HOPE CREEK 1 | 100 | ||||
| INDIAN POINT 2 | 99 | ||||
| INDIAN POINT 3 | 100 | ||||
| LIMERICK 1 | 100 | ||||
| LIMERICK 2 | 100 | ||||
| MILLSTONE 2 | 99 | ||||
| MILLSTONE 3 | 100 | ||||
| NINE MILE POINT 1 | 0 | 10/28/1999 | PLANNED MAINTENANCE OUTAGE FOR RECIRC PUMP SEAL REPLACEMENT | * | |
| NINE MILE POINT 2 | 100 | ||||
| OYSTER CREEK 1 | 98 | PERFORMING A CORE SPRAY SURVEILLANCE | * | ||
| PEACH BOTTOM 2 | 100 | ||||
| PEACH BOTTOM 3 | 100 | ||||
| PILGRIM 1 | 100 | ||||
| SALEM 1 | 100 | ||||
| SALEM 2 | 100 | ||||
| SEABROOK 1 | 100 | ||||
| SUSQUEHANNA 1 | 100 | ||||
| SUSQUEHANNA 2 | 100 | ||||
| THREE MILE ISLAND 1 | 100 | ||||
| VERMONT YANKEE 1 | 0 | 10/29/1999 | REFUELING OUTAGE - FIRST FUEL SHUFFLE COMPLETED | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | ||
| BROWNS FERRY 2 | 100 | ||||
| BROWNS FERRY 3 | 100 | ||||
| BRUNSWICK 1 | 100 | ||||
| BRUNSWICK 2 | 100 | ||||
| CATAWBA 1 | 100 | ||||
| CATAWBA 2 | 100 | ||||
| CRYSTAL RIVER 3 | 0 | 10/01/1999 | EXITING REFUELING OUTAGE | ||
| FARLEY 1 | 100 | ||||
| FARLEY 2 | 0 | 10/15/1999 | REFUELING OUTAGE - DEFUELED | ||
| HARRIS 1 | 100 | ||||
| HATCH 1 | 100 | ||||
| HATCH 2 | 98 | MAXIMUM OPERATING POWER | |||
| MCGUIRE 1 | 100 | ||||
| MCGUIRE 2 | 100 | ||||
| NORTH ANNA 1 | 100 | ||||
| NORTH ANNA 2 | 100 | ||||
| OCONEE 1 | 100 | ||||
| OCONEE 2 | 0 | 11/04/1999 | REFUELING OUTAGE - HEAD DETENSIONING IN PROGRESS | * | |
| OCONEE 3 | 100 | ||||
| ROBINSON 2 | 100 | ||||
| SAINT LUCIE 1 | 100 | ||||
| SAINT LUCIE 2 | 100 | ||||
| SEQUOYAH 1 | 100 | ||||
| SEQUOYAH 2 | 100 | ||||
| SUMMER 1 | 100 | ||||
| SURRY 1 | 100 | ||||
| SURRY 2 | 100 | ||||
| TURKEY POINT 3 | 100 | ||||
| TURKEY POINT 4 | 60 | HOLDING POWER AT THIS LEVEL TO PERFORM CONDENSER WATERBOX CLEANING | * | ||
| VOGTLE 1 | 100 | ||||
| VOGTLE 2 | 100 | * | |||
| WATTS BAR 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| BRAIDWOOD 1 | 100 | ||||
| BRAIDWOOD 2 | 100 | ||||
| BYRON 1 | 100 | ||||
| BYRON 2 | 0 | 10/23/1999 | REFUELING OUTAGE | ||
| CLINTON 1 | 100 | ||||
| COOK 1 | 0 | 09/08/1997 | REFUELING OUTAGE - DEFUELED | ||
| COOK 2 | 0 | 09/09/1997 | REFUELING OUTAGE - DEFUELED | ||
| DAVIS BESSE 1 | 100 | ||||
| DRESDEN 2 | 100 | ||||
| DRESDEN 3 | 100 | ||||
| DUANE ARNOLD 1 | 0 | 10/22/1999 | REFUELING OUTAGE - FUEL SHUFFLE IN PROGRESS | * | |
| FERMI 2 | 97 | ||||
| KEWAUNEE 1 | 97 | ||||
| LASALLE 1 | 0 | 10/22/1999 | REFUELING OUTAGE - FUEL SHUFFLE IN PROGRESS | * | |
| LASALLE 2 | 100 | ||||
| MONTICELLO 1 | 100 | ||||
| PALISADES 1 | 0 | 10/15/1999 | REFUELING OUTAGE | ||
| PERRY 1 | 100 | ||||
| POINT BEACH 1 | 0 | 10/15/1999 | REFUELING OUTAGE - DEFUELED | ||
| POINT BEACH 2 | 100 | ||||
| PRAIRIE ISLAND 1 | 100 | ||||
| PRAIRIE ISLAND 2 | 100 | ||||
| QUAD CITIES 1 | 100 | ||||
| QUAD CITIES 2 | 90 | HOLDING POWER AT THIS LEVEL TO PERFORM PLANNED SURVEILLANCE TESTING (CONTROL | * |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
|---|---|---|---|---|---|
| ARKANSAS NUCLEAR 1 | 100 | ||||
| ARKANSAS NUCLEAR 2 | 0 | 11/06/1999 | MID-CYCLE STEAM GENERATOR INSPECTION OUTAGE | * | |
| CALLAWAY 1 | 95 | HOLDING POWER AT THIS LEVEL TO PERFORM FLUX MAPPING | * | ||
| COMANCHE PEAK 1 | 100 | ||||
| COMANCHE PEAK 2 | 100 | ||||
| COOPER 1 | 100 | ||||
| DIABLO CANYON 1 | 100 | ||||
| DIABLO CANYON 2 | 100 | ||||
| FT CALHOUN 1 | 0 | 10/01/1999 | EXITING REFUELING OUTAGE - PREPARING TO GO CRITICAL | * | |
| GRAND GULF 1 | 0 | 10/22/1999 | REFUELING OUTAGE - FUEL SHUFFLE/RELOAD IN PROGRESS | * | |
| PALO VERDE 1 | 19 | UNIT ON LINE AFTER EXITING A REFUELING OUTAGE | * | ||
| PALO VERDE 2 | 100 | ||||
| PALO VERDE 3 | 100 | ||||
| RIVER BEND 1 | 100 | ||||
| SAN ONOFRE 2 | 100 | ||||
| SAN ONOFRE 3 | 100 | ||||
| SOUTH TEXAS 1 | 100 | ||||
| SOUTH TEXAS 2 | 47 | INCREASING POWER TO 48% TO PERFORM NUCLEAR INSTRUMENT CALIBRATIONS AFTER EXI | * | ||
| WASHINGTON NUCLEAR 2 | 100 | ||||
| WATERFORD 3 | 100 | ||||
| WOLF CREEK 1 | 100 |