Power Reactor Status Report for October 23, 1999

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BEAVER VALLEY 1 100        
BEAVER VALLEY 2 0 10/22/1999 GOING TO A COLD SHUTDOWN CONDITION TO REPAIR A PRESSURIZER SAFETY VALVE *  
CALVERT CLIFFS 1 100     *  
CALVERT CLIFFS 2 100        
FITZPATRICK 1 1   STARTUP IN PROGRESS. RANGE 7 ON IRMs *  
GINNA 1 100        
HOPE CREEK 1 100        
INDIAN POINT 2 99   TURBINE CONTROL VALVES FULLY OPEN    
INDIAN POINT 3 44   HOLDING POWER LEVEL BECAUSE THEY ARE AT THEIR QUADRANT POWER TILT RATIO LIMI *  
LIMERICK 1 100        
LIMERICK 2 95   REDUCING REACTOR POWER LEVEL TO 80% TO PERFORM A ROD PATTERN ADJUSTMENT *  
MILLSTONE 2 100        
MILLSTONE 3 100        
NINE MILE POINT 1 100     *  
NINE MILE POINT 2 100        
OYSTER CREEK 1 100        
PEACH BOTTOM 2 100        
PEACH BOTTOM 3 0 09/29/1999 EXITING REFUELING OUTAGE - REACTOR VESSEL HEAD TENSIONED *  
PILGRIM 1 100        
SALEM 1 0 09/17/1999 EXITING REFUELING OUTAGE    
SALEM 2 100        
SEABROOK 1 100        
SUSQUEHANNA 1 100        
SUSQUEHANNA 2 100        
THREE MILE ISLAND 1 100     *  
VERMONT YANKEE 1 96   COASTDOWN TO REFUELING OUTAGE    

Region 2

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BROWNS FERRY 1 0 03/03/1985 DEFUELED    
BROWNS FERRY 2 100        
BROWNS FERRY 3 100        
BRUNSWICK 1 100        
BRUNSWICK 2 100        
CATAWBA 1 100        
CATAWBA 2 100        
CRYSTAL RIVER 3 0 10/01/1999 REFUELING OUTAGE - DEFUELED    
FARLEY 1 100        
FARLEY 2 0 10/15/1999 ENTERING REFUELING OUTAGE    
HARRIS 1 100        
HATCH 1 100        
HATCH 2 98   MAXIMUM OPERATING POWER    
MCGUIRE 1 0 09/17/1999 REFUELING OUTAGE - DEFUELED    
MCGUIRE 2 100        
NORTH ANNA 1 100        
NORTH ANNA 2 100        
OCONEE 1 100        
OCONEE 2 100        
OCONEE 3 100        
ROBINSON 2 0 09/24/1999 EXITING REFUELING OUTAGE    
SAINT LUCIE 1 100        
SAINT LUCIE 2 100     *  
SEQUOYAH 1 100        
SEQUOYAH 2 100        
SUMMER 1 100        
SURRY 1 100        
SURRY 2 100        
TURKEY POINT 3 100        
TURKEY POINT 4 100        
VOGTLE 1 100        
VOGTLE 2 0 10/03/1999 REFUELING OUTAGE - DEFUELED    
WATTS BAR 1 100        

Region 3

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BRAIDWOOD 1 100        
BRAIDWOOD 2 100        
BYRON 1 100     *  
BYRON 2 0 10/23/1999 ENTERING REFUELING OUTAGE *  
CLINTON 1 100        
COOK 1 0 09/08/1997 REFUELING OUTAGE - DEFUELED    
COOK 2 0 09/09/1997 REFUELING OUTAGE - DEFUELED    
DAVIS BESSE 1 10   MAIN TURBINE OFF LINE - REPAIRING SEAL OIL LEAK ON THE MAIN GENERATOR *  
DRESDEN 2 0 10/01/1999 REACTOR VESSEL HEAD HAS BEEN TENSIONED. *  
DRESDEN 3 100        
DUANE ARNOLD 1 0 10/22/1999 ENTERING REFUELING OUTAGE *  
FERMI 2 97        
KEWAUNEE 1 97        
LASALLE 1 0 10/22/1999 ENTERING REFUELING OUTAGE *  
LASALLE 2 100        
MONTICELLO 1 100        
PALISADES 1 0 10/15/1999 REFUELING OUTAGE - GOING TO MID LOOP OPERATION TO INSTALL STEAM GENERATORN *  
PERRY 1 100        
POINT BEACH 1 0 10/15/1999 ENTERING REFUELING OUTAGE    
POINT BEACH 2 100        
PRAIRIE ISLAND 1 100        
PRAIRIE ISLAND 2 100        
QUAD CITIES 1 100        
QUAD CITIES 2 100        

Region 4

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
ARKANSAS NUCLEAR 1 100        
ARKANSAS NUCLEAR 2 100        
CALLAWAY 1 0 10/02/1999 EXITING REFUELING OUTAGE *  
COMANCHE PEAK 1 0 09/24/1999 EXITING REFUELING OUTAGE *  
COMANCHE PEAK 2 100        
COOPER 1 100        
DIABLO CANYON 1 100        
DIABLO CANYON 2 0 09/25/1999 EXITING REFUELING OUTAGE *  
FT CALHOUN 1 0 10/01/1999 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS *  
GRAND GULF 1 0 10/22/1999 ENTERING REFUELING OUTAGE *  
PALO VERDE 1 0 10/02/1999 REFUELING OUTAGE - DEFUELED    
PALO VERDE 2 100        
PALO VERDE 3 100        
RIVER BEND 1 100        
SAN ONOFRE 2 100        
SAN ONOFRE 3 100        
SOUTH TEXAS 1 100        
SOUTH TEXAS 2 0 10/12/1999 REFUELING OUTAGE - DEFUELED    
WASHINGTON NUCLEAR 2 1   STARTUP IN PROGRESS - CURRENTLY AT RANGE 7 ON IRMs. *  
WATERFORD 3 100        
WOLF CREEK 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.