Power Reactor Status Report for August 30, 1999
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BEAVER VALLEY 1 | 100 | ||||
BEAVER VALLEY 2 | 100 | ||||
CALVERT CLIFFS 1 | 100 | ||||
CALVERT CLIFFS 2 | 100 | ||||
FITZPATRICK 1 | 100 | ||||
GINNA 1 | 100 | ||||
HOPE CREEK 1 | 0 | 08/28/1999 | PLANNED MAINTENANCE OUTAGE | ||
INDIAN POINT 2 | 99 | ||||
INDIAN POINT 3 | 92 | COASTDOWN TO REFUELING OUTAGE | |||
LIMERICK 1 | 100 | ||||
LIMERICK 2 | 100 | ||||
MILLSTONE 2 | 100 | ||||
MILLSTONE 3 | 100 | ||||
NINE MILE POINT 1 | 100 | ||||
NINE MILE POINT 2 | 100 | ||||
OYSTER CREEK 1 | 100 | * | |||
PEACH BOTTOM 2 | 100 | . | |||
PEACH BOTTOM 3 | 90 | COASTDOWN TO REFUELING OUTAGE | * | ||
PILGRIM 1 | 100 | ||||
SALEM 1 | 86 | COASTDOWN TO REFUELING OUTAGE | * | ||
SALEM 2 | 100 | ||||
SEABROOK 1 | 100 | ||||
SUSQUEHANNA 1 | 100 | ||||
SUSQUEHANNA 2 | 100 | ||||
THREE MILE ISLAND 1 | 100 | ||||
VERMONT YANKEE 1 | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | ||
BROWNS FERRY 2 | 85 | HOLDING POWER AT THIS LEVEL TO PERFORM '2B' CONDENSATE PUMP SEAL MAINTENANCE | |||
BROWNS FERRY 3 | 100 | ||||
BRUNSWICK 1 | 0 | 08/29/1999 | PLANT IN NOUE DUE TO HURRICANE DENNIS SEE EVENT #36084 - PLANT WILL BE COOLE | * | |
BRUNSWICK 2 | 0 | 08/29/1999 | PLANT IN NOUE DUE TO HURRICANE DENNIS SEE EVENT # 36084 - PLANT WILL BE COOL | * | |
CATAWBA 1 | 100 | ||||
CATAWBA 2 | 100 | ||||
CRYSTAL RIVER 3 | 100 | ||||
FARLEY 1 | 100 | * | |||
FARLEY 2 | 100 | ||||
HARRIS 1 | 100 | ||||
HATCH 1 | 100 | ||||
HATCH 2 | 98 | ||||
MCGUIRE 1 | 100 | ||||
MCGUIRE 2 | 100 | ||||
NORTH ANNA 1 | 100 | ||||
NORTH ANNA 2 | 90 | COASTDOWN TO REFUELING OUTAGE | * | ||
OCONEE 1 | 100 | ||||
OCONEE 2 | 100 | ||||
OCONEE 3 | 100 | ||||
ROBINSON 2 | 95 | COASTDOWN TO REFUELING OUTAGE | |||
SAINT LUCIE 1 | 80 | HOLDING TO GET HEATER DRAIN PUMPS OPERATING | * | ||
SAINT LUCIE 2 | 100 | ||||
SEQUOYAH 1 | 100 | ||||
SEQUOYAH 2 | 100 | ||||
SUMMER 1 | 100 | ||||
SURRY 1 | 100 | ||||
SURRY 2 | 100 | ||||
TURKEY POINT 3 | 100 | ||||
TURKEY POINT 4 | 100 | ||||
VOGTLE 1 | 100 | ||||
VOGTLE 2 | 100 | ||||
WATTS BAR 1 | 90 | INCREASING POWER FOLLOWING POWER REDUCTION FOR HEATER DRAIN TANK PUMP REPAIR | * |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BRAIDWOOD 1 | 100 | ||||
BRAIDWOOD 2 | 100 | ||||
BYRON 1 | 100 | ||||
BYRON 2 | 100 | ||||
CLINTON 1 | 100 | ||||
COOK 1 | 0 | 09/08/1997 | REFUELING OUTAGE - DEFUELED | ||
COOK 2 | 0 | 09/09/1997 | REFUELING OUTAGE - DEFUELED | ||
DAVIS BESSE 1 | 100 | ||||
DRESDEN 2 | 100 | * | |||
DRESDEN 3 | 100 | ||||
DUANE ARNOLD 1 | 100 | ||||
FERMI 2 | 97 | ||||
KEWAUNEE 1 | 97 | ||||
LASALLE 1 | 95 | COASTDOWN TO REFUELING OUTAGE | |||
LASALLE 2 | 100 | ||||
MONTICELLO 1 | 100 | ||||
PALISADES 1 | 100 | ||||
PERRY 1 | 90 | HOLDING FOR CONTROL VALVE TEST | * | ||
POINT BEACH 1 | 100 | ||||
POINT BEACH 2 | 100 | * | |||
PRAIRIE ISLAND 1 | 100 | * | |||
PRAIRIE ISLAND 2 | 100 | ||||
QUAD CITIES 1 | 100 | ||||
QUAD CITIES 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
ARKANSAS NUCLEAR 1 | 100 | ||||
ARKANSAS NUCLEAR 2 | 100 | ||||
CALLAWAY 1 | 100 | ||||
COMANCHE PEAK 1 | 100 | ||||
COMANCHE PEAK 2 | 100 | ||||
COOPER 1 | 100 | ||||
DIABLO CANYON 1 | 100 | ||||
DIABLO CANYON 2 | 100 | ||||
FT CALHOUN 1 | 100 | ||||
GRAND GULF 1 | 100 | ||||
PALO VERDE 1 | 100 | ||||
PALO VERDE 2 | 100 | ||||
PALO VERDE 3 | 100 | * | |||
RIVER BEND 1 | 100 | ||||
SAN ONOFRE 2 | 100 | ||||
SAN ONOFRE 3 | 100 | ||||
SOUTH TEXAS 1 | 100 | ||||
SOUTH TEXAS 2 | 100 | ||||
WASHINGTON NUCLEAR 2 | 80 | COASTDOWN TO REFUELING OUTAGE | |||
WATERFORD 3 | 100 | ||||
WOLF CREEK 1 | 100 | * |