Power Reactor Status Report for May 13, 1999
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BEAVER VALLEY 1 | 100 | ||||
BEAVER VALLEY 2 | 100 | ||||
CALVERT CLIFFS 1 | 0 | 05/10/1999 | MAINTENANCE OUTAGE | ||
CALVERT CLIFFS 2 | 97 | HOLDING POWER AT THIS LEVEL TO PERFORM POST-REFUELING OUTAGE TESTING | |||
FITZPATRICK 1 | 100 | ||||
GINNA 1 | 96 | OPERATING AT REDUCED LOAD DUE TO DELTA-T SETPOINT ISSUES | |||
HOPE CREEK 1 | 70 | HOLDING POWER AT THIS LEVEL TO PERFORM CONDENSER TUBE REPAIRS AND PLANNED MA | * | ||
INDIAN POINT 2 | 99 | MAXIMUM OPERATING POWER DUE TO STEAM FLOW DEMAND - TURBINE THROTTLE VALVES F | |||
INDIAN POINT 3 | 100 | ||||
LIMERICK 1 | 100 | ||||
LIMERICK 2 | 0 | 04/16/1999 | REFUELING OUTAGE - FUEL SHUFFLE IN PROGRESS | ||
MILLSTONE 2 | 15 | PREPARING TO TAKE UNIT OFF LINE TO PERFORM TURBINE OVERSPEED TESTING | * | ||
MILLSTONE 3 | 0 | 05/01/1999 | REFUELING OUTAGE - PREPARING TO PERFORM FUEL OFFLOAD | * | |
NINE MILE POINT 1 | 0 | 04/11/1999 | REFUELING OUTAGE - DEFUELED | ||
NINE MILE POINT 2 | 100 | ||||
OYSTER CREEK 1 | 100 | ||||
PEACH BOTTOM 2 | 100 | ||||
PEACH BOTTOM 3 | 100 | ||||
PILGRIM 1 | 0 | 05/08/1999 | REFUELING OUTAGE - PREPARING TO PERFORM FUEL SHUFFLE | * | |
SALEM 1 | 100 | ||||
SALEM 2 | 0 | 04/03/1999 | REFUELING OUTAGE | ||
SEABROOK 1 | 1 | REFUELING OUTAGE - COMPLETED LOW POWER PHYSICS TESTING | * | ||
SUSQUEHANNA 1 | 100 | ||||
SUSQUEHANNA 2 | 100 | ||||
THREE MILE ISLAND 1 | 100 | ||||
VERMONT YANKEE 1 | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | ||
BROWNS FERRY 2 | 95 | HOLDING POWER AT THIS LEVEL TO PERFORM POWER ASCENSION TESTING (SOAK) AFTER | * | ||
BROWNS FERRY 3 | 100 | ||||
BRUNSWICK 1 | 100 | ||||
BRUNSWICK 2 | 0 | 04/16/1999 | REFUELING OUTAGE - VESSEL HYDRO COMPLETE | * | |
CATAWBA 1 | 0 | 04/21/1999 | REFUELING OUTAGE - FUEL RELOAD COMPLETE | ||
CATAWBA 2 | 0 | 05/03/1999 | MAINTENANCE OUTAGE | ||
CRYSTAL RIVER 3 | 100 | ||||
FARLEY 1 | 100 | ||||
FARLEY 2 | 100 | * | |||
HARRIS 1 | 100 | ||||
HATCH 1 | 92 | INCREASING POWER | * | ||
HATCH 2 | 98 | MAXIMUM OPERATING POWER | * | ||
MCGUIRE 1 | 100 | ||||
MCGUIRE 2 | 100 | ||||
NORTH ANNA 1 | 100 | ||||
NORTH ANNA 2 | 100 | ||||
OCONEE 1 | 100 | ||||
OCONEE 2 | 100 | ||||
OCONEE 3 | 100 | ||||
ROBINSON 2 | 100 | ||||
SAINT LUCIE 1 | 100 | ||||
SAINT LUCIE 2 | 100 | ||||
SEQUOYAH 1 | 100 | ||||
SEQUOYAH 2 | 47 | INCREASING POWER AFTER EXITING A REFUELING OUTAGE | * | ||
SUMMER 1 | 20 | INCREASING POWER TO 30% AFTER REPAIRING GENERATOR FIELD REGULATION PROBLEMS | * | ||
SURRY 1 | 100 | ||||
SURRY 2 | 0 | 04/18/1999 | REFUELING OUTAGE | ||
TURKEY POINT 3 | 100 | ||||
TURKEY POINT 4 | 100 | ||||
VOGTLE 1 | 100 | ||||
VOGTLE 2 | 100 | ||||
WATTS BAR 1 | 100 |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
BRAIDWOOD 1 | 100 | ||||
BRAIDWOOD 2 | 0 | 04/23/1999 | REFUELING OUTAGE | ||
BYRON 1 | 100 | ||||
BYRON 2 | 100 | ||||
CLINTON 1 | 2 | REFUELING OUTAGE - STARTUP IN PROGRESS | * | ||
COOK 1 | 0 | 09/08/1997 | MAINTENANCE OUTAGE | ||
COOK 2 | 0 | 09/09/1997 | REFUELING OUTAGE | ||
DAVIS BESSE 1 | 100 | ||||
DRESDEN 2 | 100 | ||||
DRESDEN 3 | 100 | ||||
DUANE ARNOLD 1 | 100 | ||||
FERMI 2 | 97 | ADMINISTRATIVE POWER LIMIT | |||
KEWAUNEE 1 | 97 | POWER LIMITED DUE TO STEAM GENERATOR TUBE PLUGGING | |||
LASALLE 1 | 100 | ||||
LASALLE 2 | 100 | ||||
MONTICELLO 1 | 0 | 05/08/1999 | MAINTENANCE OUTAGE | ||
PALISADES 1 | 0 | 05/07/1999 | MAINTENANCE OUTAGE | ||
PERRY 1 | 100 | ||||
POINT BEACH 1 | 100 | ||||
POINT BEACH 2 | 100 | ||||
PRAIRIE ISLAND 1 | 0 | 04/16/1999 | REFUELING OUTAGE - FUEL RELOAD COMPLETE | ||
PRAIRIE ISLAND 2 | 100 | ||||
QUAD CITIES 1 | 100 | ||||
QUAD CITIES 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
---|---|---|---|---|---|
ARKANSAS NUCLEAR 1 | 100 | ||||
ARKANSAS NUCLEAR 2 | 100 | ||||
CALLAWAY 1 | 100 | ||||
COMANCHE PEAK 1 | 100 | ||||
COMANCHE PEAK 2 | 100 | ||||
COOPER 1 | 100 | ||||
DIABLO CANYON 1 | 100 | ||||
DIABLO CANYON 2 | 100 | ||||
FT CALHOUN 1 | 100 | ||||
GRAND GULF 1 | 100 | ||||
PALO VERDE 1 | 100 | ||||
PALO VERDE 2 | 100 | ||||
PALO VERDE 3 | 100 | ||||
RIVER BEND 1 | 0 | 04/03/1999 | REFUELING OUTAGE - PLAN TO CONTINUE FUEL SHUFFLE ON DAY SHIFT | * | |
SAN ONOFRE 2 | 100 | ||||
SAN ONOFRE 3 | 97 | SLOWLY INCREASING POWER AFTER DECREASING TO 85% DUE TO CLOSURE OF A TURBINE | * | ||
SOUTH TEXAS 1 | 100 | ||||
SOUTH TEXAS 2 | 100 | ||||
WASHINGTON NUCLEAR 2 | 0 | 04/17/1999 | MAINTENANCE OUTAGE | ||
WATERFORD 3 | 100 | ||||
WOLF CREEK 1 | 95 | INCREASING POWER AFTER DECREASING TO 54% TO REPAIR A HIGH PRESSURE FEEDWATER | * |
Page Last Reviewed/Updated Wednesday, March 24, 2021