Part 21 Report - 1997-591

ACCESSION #: 9709050020 Illinois Power Company Clinton Power Station PO Box 678 Clinton IL 61727 ILLINOIS Tel 217 935-6220 POWER Fax 217 935-4632 An Illinova Company Wayne D. Romberg Assistant Vice President Nuclear U-602823 4F.140 August 28, 1997 Docket No. 50-461 10CFR21.21 Document Control Desk Nuclear Regulatory Commission Washington, D. C. 20555 Subject: 10CFR21 Final Report 21-97-015: Improper Clearance for Westinghouse Model 50DHP350 Circuit Breaker Arc Chute Rear Arc Horn Dear Madam or Sir: On May 7, 1997, Illinois Power (IP) identified that five arc chutes, manufacturer part number 567F417G02, for Westinghouse Model 50DHP350, 4160-volt circuit breakers, in stores were different in configuration from the original arc chute and exhibited an inadequate clearance between the rear arc horn and the arc chute molded case during installation. Because of the inadequate clearance, excessive force would be required on the line pole unit to allow the arc chute to attach to the front arc chute support. When attempts were made to install one of the arc chutes in the "A" Residual Heat Removal (RHR) system pump breaker, the line pole unit of the circuit breaker deflected upwards. Attempts were made to install the arc chute on all three phases of the breaker with the same result. A suitable replacement for the RHR pump breaker arc chute was located on an original spare breaker. Condition report 1-97-05-085 was initiated to track investigation and resolution of this issue. This issue was identified as potentially reportable under the provisions of 10CFR, Part 21. IP notified the NRC via letter U-602779, dated July 2, 1997, that the investigation of the arc chute rear arc horn issue was not completed and additional time was needed to complete the investigation. IP has now completed the evaluation of this condition under 10CFR21 and concludes that this issue should be reported under the provisions of 10CFR21. The basis for this conclusion is that installation of the arc chute could cause the line pole unit to deflect, potentially causing the main and arcing contacts to be out of adjustment and potentially affecting the safety related function of the circuit breaker. The failure of the breaker to operate properly could result in the loss of power to safety- related equipment loads. The breaker's function is to supply Class 1E power until a fault occurs (trip open) and shed loads, or close on demand and supply Class 1E power to safety-related equipment. U-602823 Page 2 IP is providing the following information in accordance with 10CFR21.21(c)(4). Initial notification of this matter will be provided by facsimile of this letter to the NRC Operations Center in accordance with 10CFR21.21(c)(3) within two days of the date the responsible officer signs this letter. (i) Wayne D. Romberg, Assistant Vice President of IP, Clinton Power Station, Highway 54, 6 Miles East, Clinton, Illinois, 61727, is informing the Nuclear Regulatory Commission of a condition reportable under the provisions of 10CFR, Part 21. (ii) The basic component involved in this condition is the arc chute, manufacturer part number 567F417G02, for Westinghouse Model 50DHP350, 4160-volt circuit breakers. (iii) The arc chute and rear arc horn were supplied to Clinton Power Station by Westinghouse, Pittsburgh, PA. (iv) The arc chute appears to be different in configuration from the original arc chute and exhibited an inadequate clearance between the rear arc horn and the arc chute molded case during installation. Specifically, the replacement rear arc horn contact currently in production for the breaker appears to be different from the original rear arc horn contact installed in the breaker. The major differences appear to be the position and angle of bend for the contact. Because of the inadequate clearance that occurs during installation, excessive force would be required on the line pole unit to allow the arc chute to attach to the front arc chute support. When attempts were made to install one of the arc chutes in the "A" Residual Heat Removal (RHR) system pump circuit breaker, the line pole unit of the breaker deflected upward, indicating excessive tension on the unit. Attempts were made to install the arc chute on all three phases of the breaker with the same result. IP has concluded that this issue should be reported under the provisions of 10CFR21. The basis for this conclusion is that, despite assurance from the supplier that the arc chute is the correct part, IP is unable to determine if the rear arc horn can be installed without adverse impact on the circuit breaker. Installation of the arc chute could cause the line pole unit to deflect, potentially causing the main and arcing contacts to be out of adjustment and adversely affecting the safety-related function of the circuit breaker. The impact of the additional stress applied to the pole units is not known. However, the failure of the breaker to operate properly could result in the loss of power to safety-related equipment loads. The breaker's function is to supply Class 1E power until a fault occurs (trip open) and shed loads, or close on demand and supply Class 1E power to safety-related equipment. U-602823 Page 3 (v) The improper clearance condition was identified and determined potentially reportable under the provisions of 10CFR21 on May 7, 1997. IP notified the NRC in a letter dated July 2, 1997, that the investigation of the issue was not complete, and additional time was needed for completion. (vi) Clinton Power Station (CPS) has 5 of the potentially affected arc chutes in stores. When attempts to install the deficient arc chute were unsuccessful, a suitable replacement arc chute was located on an original spare circuit breaker. None of the deficient arc chutes have been installed in the plant. IP is not aware of other facilities that could be affected by this deficiency. (vii) The deficient arc chutes are currently on hold and will not be released for installation until appropriate corrective actions are identified that allow proper installation of the arc chute. Discussions between CPS and Westinghouse (Cutler-Hammer) are continuing in an attempt to resolve this issue. (viii) IP has no advice about this issue for other purchasers or licensees. Additional information about this issue may be obtained by contacting D. G. Lukach, Plant Engineering, at (217) 935-8881, extension 3952. Sincerely yours, Wayne D. Romberg Assistant Vice President RSF/krk cc: NRC Clinton Licensing Project Manager NRC Resident Office, V-690 Regional Administrator, Region III, USNRC G. C. Wright, Region III, USNRC Illinois Department of Nuclear Safety INPO Records Center Westinghouse Eaton Cutler-Hammer *** END OF DOCUMENT ***

Page Last Reviewed/Updated Wednesday, March 24, 2021