Part 21 Report - 1995-206
ACCESSION #: 9509210131 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402-2801 O. J. "Ike" Zeringue Senior Vice President, Nuclear Operations SEP 14 1995 CDR-50-390/95-05 10 CFR 50.55(e) CDR-50-391/95-05 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen: In the Matter of the Application of ) Docket Nos. 50-390 Tennessee Valley Authority ) 50-391 WATTS BAR NUCLEAR PLANT (WBN) UNITS 1 AND 2 CONSTRUCTION DEFICIENCY REPORT (CDR) 50-390, 391/95-05 - DEFICIENCY INVOLVING VENDOR WIRED SAFETY-RELATED ELECTRICAL PANELS - FINAL REPORT The purpose of this letter is to provide a final report for the subject deficiency in accordance with 10 CFR 50.55(e). The subject deficiency was initially reported to the NRC Operations Center on August 18, 1995, as Finding Identification Report WBFIR930012307. The subject deficiency was subsequently upgraded to Significant Corrective Action Report WBSCA950014. The Enclosure 1 contains a final report for the subject deficiency. Enclosure 2 contains a list of commitments made in this submittal. If there are any questions, please telephone P. L. Pace at (615) 365- 1824. Sincerely, O. J. Zeringue Enclosures cc: See page 2 U.S. Nuclear Regulatory Commission Page 2 SEP 14 1995 cc (Enclosures): INPO Record Center 700 Galleria Parkway Atlanta, Georgia 30339 NRC Resident Inspector Watts Bar Nuclear Plant Rt. 2, Box 700 Spring City, Tennessee 37381 Mr. P. S. Tam, Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852 U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNITS 1 AND 2 VENDOR WIRED SAFETY RELATED ELECTRICAL PANELS SIGNIFICANT CORRECTIVE ACTION REPORT WBSCA950014 10CFR50.55(e) CONSTRUCTION DEFICIENCY REPORT (CDR) CDR 50-390, 391/95-05 FINAL REPORT DESCRIPTION OF DEFICIENCY Loose connections have been identified in vendor wired safety-related electrical panels. The loose connections involve both the termination of incoming field cables as well as vendor terminations. BACKGROUND Deficiencies in vendor wired safety-related electrical panels had been identified during a configuration control walkdown of 40 Unit 1 panels in 1984. The deficiencies were documented in Nonconformance Report (NCR) W- 205-P. The deficiencies can be categorized as: (1) labeling deficiencies (primarily on vendor wiring); (2) wiring/configuration control deficiencies (e.g., wires on different terminal than shown on drawings); or (3) physical problems (e.g., nicks on insulation and loose terminal connections). The deficiencies which required correction were resolved through rework or drawing changes. The NCR was determined to not be significant and was closed in 1985 without requiring a walkdown of any additional panels. In 1987 an Employee Concerns Special Project (ECSP) review team did not recognize that the physical deficiencies associated with NCR W-205-P had not been adequately dispositioned for the uninspected panels. However, in January 1993, WBN Site Quality Assurance personnel reviewed the ECSP evaluation of NCR W-205-P during an audit (WBA93307). In February 1993 the significance determination of the NCR was questioned and documented in Finding Identification Report (FIR) WBFIR930012307. An action was initiated against that FIR to evaluate any deficiencies identified through the walkdown inspection of the previously uninspected vendor wired safety-related electrical panels required for Unit 1 operation and determine whether they could have created a substantial safety hazard, if left uncorrected. That action has been completed. SAFETY IMPLICATIONS Based on a review of the work implementing documents associated with deficiencies identified during the above walkdowns, four categories of deficiencies were identified: (1) terminal blocks; (2) loose connections; (3) cables/conductors; and (4) cable/conductor insulation gaps. Categories 1, 3, and 4 have been evaluated as not having an adverse impact on plant safety. However, Category 2 was determined to potentially have an adverse impact on plant safety. Although some of the identified loose connections could involve nonsafety-related circuits fed from the safety-related panel, a significant portion of the loose connections have been confirmed to be associated with safety- related circuits in various safety-related systems (e.g. Component Cooling System, Safety Injection System, Ventilating System, Essential Raw Cooling Water System, Residual Heat Removal System, etc.), and involve redundant divisions of safety-related circuits. Assurance cannot be provided that the identified loose connections would maintain circuit continuity during a seismic event. Therefore, those loose connections would be assumed to create an open circuit during a seismic event. The resulting condition may affect the capability to mitigate the consequences of design basis events or safely shut down the reactor and maintain it in a safe shutdown condition. CAUSE OF THE DEFICIENCY The cause for the deficiencies existing past closure of NCR W-205-P was personnel error. A configuration walkdown of vendor wired safety-related electrical panels was conducted in 1984. The walkdown was designed to identify and correct electrical deficiencies. After inspecting 40 vendor wired safety-related electrical panels, numerous identified deficiencies were documented in NCR W-205-P. The responsible organization incorrectly determined that the NCR was non-significant. By the procedure in effect at the time, non-significant NCRs were not required to be reviewed for Unit 2 generic applicability, extent of condition, root cause, or recurrence controls. Therefore, the incorrect significance determination resulted in the remaining vendor wired safety-related electrical panels not being inspected. CORRECTIVE ACTIONS The cause for this construction deficiency was the subject of Notice of Violation (NOV) 50-390, 391/93-24-01. TVA initially replied to that NOV on June 8, 1993. The loose connections identified in previously uninspected vendor wired safety-related electrical panels required for Unit 1 operation have been corrected as part of the Unit 1 closure of WBFIR930012307. Unit 2 vendor wired safety-related electrical panels not inspected by NCR W-205-P or WBFIR930012307 will be dispositioned prior to Unit 2 fuel load. ENCLOSURE 2 LIST OF COMMITMENTS Unit 2 vendor wired safety-related electrical panels not inspected by NCR W-205-P or WBFIR930012307 will be dispositioned prior to Unit 2 fuel load. *** END OF DOCUMENT ***
Page Last Reviewed/Updated Wednesday, March 24, 2021
Page Last Reviewed/Updated Wednesday, March 24, 2021