Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Morning Report for March 19, 2007

Headquarters Daily Report

To top of page

REGION I

Pilgrim Manual Reactor Shutdown.

Licensee/Facility:

ENTERGY NUCLEAR GENERATION COMPANY
Pilgrim 1
PLYMOUTH, Massachusetts
Dockets: 05000293
[1] GE-3
License No:
Notification:

MR Number: 1-2007-0008
Date: 03/17/2007

Call from Licensee

Discussion:

On March 17, 2007, the Pilgrim reactor was manually shutdown due to increasing unidentified drywell leakage.
Upon drywell entry, a steam leak was identified from the packing of a 6-inch reactor water cleanup valve. The
valve was repacked and will be tested during plant heatup/pressurization. Startup commenced at approximately
6:00 a.m. on March 19, 2007.

Accession Numbers:

Accession No Accession Date
ML070780524 03/19/2007

Contacts:

Name Office Abbrev Phone No E-Mail
POWELL, RAYMOND J R1 (610) 337-6967 RJP@nrc.gov

Page Last Reviewed/Updated Wednesday, March 24, 2021

Page Last Reviewed/Updated Wednesday, March 24, 2021