Morning Report for August 25, 2006

Headquarters Daily Report

REGION I

MANAGEMENT CHANGE AT THREE MILE ISLAND

Licensee/Facility:

AMERGEN ENERGY CO., LLC
Three Mile Island 1, Three Mile Island 2
MIDDLETOWN, Pennsylvania
Dockets: 05000289, 05000320
[1] B&W-L-LP, [2] B&W-L-LP
License No:
Notification:

MR Number: 1-2006-0006
Date: 08/25/2006

E-MAIL

Discussion:

On August 24, Exelon Nuclear announced that Glen Chick, Plant Manager at Three Mile Island Unit 1, has been named Vice President, Projects and Craft Labor, and will report to Amir Shahkarmi, Senior Vice President Engineering and Technical Services. Mr. Chick will be replacing Tyler Anthony, who was named Vice President, Outage Services. Ed Eilola, Three Mile Island Director of Site Engineering, will be the acting Plant Manager at Three Mile Island until permanent replacement is named.

Accession Numbers:

Accession No Accession Date
ML062370216 08/25/2006

Contacts:

Name Office Abbrev Phone No E-Mail
FUHRMEISTER, ROY L R1 (610) 337-5059 RLF1@nrc.gov