The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Morning Report for November 18, 2005

Headquarters Daily Report

To top of page

REGION II

CRYSTAL RIVER UNIT 3 - BAFFLE PLATE BOLTING FAILURES

Licensee/Facility:

FLORIDA POWER CORP.
Crystal River 3
CRYSTAL RIVER, Florida
Dockets: 05000302
[3] B&W-L-LP
License No:
Notification:

MR Number: 2-2005-0014
Date: 11/14/2005

Discussion:

On November 13, 2005, while in a refueling outage, Crystal River Unit 3 identified two broken reactor internal baffle plate bolts while investigating fuel grid strap wear concerns. The failed bolts are 7/16" stainless steel baffle-to-baffle bolts used to join individual baffle plates, vice baffle-to-former plate bolts which hold the baffle plates to the horizontal former plates within the core barrel. While the baffle-to-baffle bolts play a role in maintaining the integrity of the baffle assembly, the baffle-to-former bolts are the critical components essentials to support the vendor's structural analysis of the baffle assembly.

The licensee is currently defueling the reactor to facilitate follow on actions. Framatome ANP is assisting the licensee in their determination of follow on actions which will include an analysis of the required bolting for continued operation, and ultrasonic testing of selected baffle-to-former plate bolts.

Contacts:

Name Office Abbrev Phone No E-Mail
LESSER, MARK S R2 (404) 562-4667 MSL1@nrc.gov