Morning Report for February 25, 2002

                       Headquarters Daily Report

                         FEBRUARY 25, 2002

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X
REGION I                               X
REGION II                              X
REGION III          X
REGION IV                              X
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION III  FEB. 25, 2002

Licensee/Facility:                     Notification:

Indiana                                MR Number: 3-02-0006
Michigan Power Company                 Date: 02/22/02
Cook 1 2                               RESIDENT INSPECTOR
Bridgman,Michigan
Dockets: 50-315,50-316
PWR/W-4-LP,PWR/W-4-LP

Subject: D.C. COOK MANAGEMENT CHANGE

Discussion:

On February 22, 2002, Joseph E. Pollock was named site vice president for
American Electric Power Company's (AEP) Cook Nuclear Plant. Mr. Pollock's
prior position was plant manager at Cook Nuclear Plant. The site vice
president position has been vacant since last October, when A.
Christopher Bakken, III, was named senior vice president and chief
nuclear officer. Michael J. Finissi was named to replace Mr. Pollock as
plant manager. Mr. Finissi is currently attending senior reactor operator
training at Cook, and plans to assume the duties of plant manager in the
Fall 2002 when his training is complete. Mr. Finissi's prior position was
plant engineering director.

Regional Action:

Information Only

Contact:  ANTON VEGEL                (630)829-9620
_
 

Page Last Reviewed/Updated Wednesday, March 24, 2021