Morning Report for December 11, 2001
Headquarters Daily Report
DECEMBER 11, 2001
***************************************************************************
REPORT NEGATIVE NO INPUT
ATTACHED INPUT RECEIVED RECEIVED
HEADQUARTERS X
REGION I X
REGION II X
REGION III X
REGION IV X
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III DEC. 11, 2001
Licensee/Facility: Notification:
Firstenergy Nuclear Operating Co. MR Number: 3-01-0039
Davis Besse 1 Date: 12/06/01
Oak Harbor,Ohio SRI phone call
Dockets: 50-346
PWR/B&W-R-LP
Subject: FirstEnergy Nuclear Operating Company (FENOC) Announces
Additional Management Changes.
Discussion:
Robert Saunders, President and CNO of FENOC, announced today that
FirstEnergy (FENOC) will have the following management changes, The
changes will be effective December 24, 2001.
Randy Fast, currently Director-Plant Maintenance at Beaver Valley, will
become the Plant Manager at Davis-Besse. Lonnie Worley, currently the
Director- Support Services at Davis-Besse, will become
Director-Generation Supply Chain. Dave Eshelman, currently the
Manager-Plant Engineering at Davis-Besse, will replace Lonnie Worley and
become the Director-Support Services at Davis-Besse.
Robert Schrauder, currently the Plant Manager at Perry, will become the
FENOC Director-Special Engineering Projects. Bill Kanda, currently the
Director- FENOC Oversight, will return to his prior position as Plant
Manager at Perry. Neal Bonner, currently the Director-Nuclear Maintenance
at Perry, has been named as FENOC loaned executive to INPO in Atlanta.
Tim Rausch, currently the Director-Nuclear Engineering at Perry, will
replace Neal Bonner and become the Director-Work Management and
Maintenance at Perry. Jim Powers, currently Project Manager-Extended
Power Uprate at Perry, will replace Tim Rausch and become
Director-Nuclear Engineering at Perry.
Regional Action:
Information Only
Contact: C. LIPA (630)829-9619
_
REGION III MORNING REPORT PAGE 2 DECEMBER 11, 2001
Licensee/Facility: Notification:
Firstenergy Nuclear Operating Co. MR Number: 3-01-0040
Perry 1 Date: 12/06/01
Perry,Ohio SRI phone call
Dockets: 50-440
BWR/GE-6
Subject: FirstEnergy Nuclear Operating Company (FENOC) Announces
Additional Management Changes
Discussion:
Robert Saunders, President and CNO of FENOC, announced today that
FirstEnergy (FENOC) will have the following management changes, The
changes will be effective December 24, 2001.
Randy Fast, currently Director-Plant Maintenance at Beaver Valley, will
become the Plant Manager at Davis-Besse. Lonnie Worley, currently the
Director- Support Services at Davis-Besse, will become
Director-Generation Supply Chain. Dave Eshelman, currently the
Manager-Plant Engineering at Davis-Besse, will replace Lonnie Worley and
become the Director-Support Services at Davis-Besse.
Robert Schrauder, currently the Plant Manager at Perry, will become the
FENOC Director-Special Engineering Projects. Bill Kanda, currently the
Director- FENOC Oversight, will return to his prior position as Plant
Manager at Perry. Neal Bonner, currently the Director-Nuclear Maintenance
at Perry, has been named as FENOC loaned executive to INPO in Atlanta.
Tim Rausch, currently the Director-Nuclear Engineering at Perry, will
replace Neal Bonner and become the Director-Work Management and
Maintenance at Perry. Jim Powers, currently Project Manager-Extended
Power Uprate at Perry, will replace Tim Rausch and become
Director-Nuclear Engineering at Perry.
Regional Action:
Information Only.
Contact: C. LIPA (630)829-9619