Morning Report for November 20, 2000
Headquarters Daily Report
NOVEMBER 20, 2000
***************************************************************************
REPORT NEGATIVE NO INPUT
ATTACHED INPUT RECEIVED RECEIVED
HEADQUARTERS X
REGION I X
REGION II X
REGION III X
REGION IV X
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III NOV. 20, 2000
Licensee/Facility: Notification:
American Electric Power MR Number: 3-00-0039
Cook 1 Date: 11/17/00
Bridgman,Michigan RESIDENT INSPECTOR - 11/17/00
Dockets: 50-315
PWR/W-4-LP
Subject: UNIT 1 CORE RELOAD
Discussion:
On November 17, 2000, at 4:46 p.m. (ET), Unit 1 entered Mode 6
(Refueling), when the first fuel assembly for the upcoming fuel cycle was
placed into the Unit 1 reactor vessel. The licensee completed core reload
on Monday, November 20, at 2:33 a.m. Restart of Unit 1 is currently
scheduled for December 2000.
Regional Action:
Information Only
Contact: ANTON VEGEL (630)829-9620
_
Page Last Reviewed/Updated Wednesday, March 24, 2021