The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Morning Report for November 20, 2000

                       Headquarters Daily Report

                         NOVEMBER 20, 2000

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X
REGION I                               X
REGION II                              X
REGION III          X
REGION IV                              X
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION III  NOV. 20, 2000

Licensee/Facility:                     Notification:

American Electric Power                MR Number: 3-00-0039
Cook 1                                 Date: 11/17/00
Bridgman,Michigan                      RESIDENT INSPECTOR - 11/17/00
Dockets: 50-315
PWR/W-4-LP

Subject: UNIT 1 CORE RELOAD

Discussion:

On November 17, 2000, at 4:46 p.m. (ET), Unit 1 entered Mode 6
(Refueling), when the first fuel assembly for the upcoming fuel cycle was
placed into the Unit 1 reactor vessel. The licensee completed core reload
on Monday, November 20, at 2:33 a.m. Restart of Unit 1 is currently
scheduled for December 2000.

Regional Action:

Information Only

Contact:  ANTON VEGEL                (630)829-9620
_
 