Morning Report for June 26, 2000
Headquarters Daily Report
JUNE 26, 2000
***************************************************************************
REPORT NEGATIVE NO INPUT
ATTACHED INPUT RECEIVED RECEIVED
HEADQUARTERS X
REGION I X
REGION II X
REGION III X
REGION IV X
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III JUNE 26, 2000
Licensee/Facility: Notification:
American Electric Power MR Number: 3-00-0030
Cook 2 Date: 06/26/00
Bridgman,Michigan
Dockets: 50-316
PWR/W-4-LP
Subject: D.C. COOK UNIT 2 SYNCHRONIZATION TO GRID
Discussion:
On June 25, 2000, at 4:16 a.m. (EDT), with the Unit 2 reactor at 9
percent power, plant operators closed the main generator output breaker
and connected the electrical output of the generator to American Electric
Power Company's transmission grid. The licensee encountered no
significant equipment problems. NRC inspectors were onsite monitoring
control room activities and have been observing all of the major
evolutions. The licensee began a controlled ascension to full power,
which includes several hold points for testing and monitoring of plant
equipment.
Regional Action:
Information Only
Contact: ANTON VEGEL (630)829-9620