The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Morning Report for January 7, 2000

                       Headquarters Daily Report

                         JANUARY 07, 2000

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X
REGION I                               X
REGION II                              X
REGION III                             X
REGION IV           X
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION IV  JANUARY  7, 2000

Licensee/Facility:                     Notification:

Arizona Public Service Co.             MR Number: 4-00-0001
Palo Verde 2                           Date: 01/07/00
Wintersburg,Arizona                    BY TELECON FROM RESIDENT INSPECTOR
Dockets: 50-529
PWR/CE80

Subject: UNPLANNED PLANT SHUTDOWN TO REPAIR MAIN CONDENSER TUBE LEAK

Discussion:

On January 6, 2000, at 1:15 a.m. (MST), Palo Verde Nuclear Generating
Station Unit 2 completed an unplanned reactor shutdown to repair one
ruptured main condenser tube.  The ruptured tube caused the concentration
of sodium in the steam generators to exceed action levels that required a
plant shutdown.  The shutdown was conducted without incident and all
equipment functioned as designed.  Unit 2 is currently in Mode 3 and
repairs are underway.

Unit 2 was scheduled to be shut down on January 7 to repair a previously
identified but separate problem in the main condenser.

Regional Action:

Resident inspectors will monitor activities during the unplanned outage.

Contact:  Phil Harrell               (817)860-8250