Event Notification Report for December 24, 2022

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
12/23/2022 - 12/24/2022

EVENT NUMBERS
56286
Power Reactor
Event Number: 56286
Facility: Salem
Region: 1     State: NJ
Unit: [2] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: Edward Kane
HQ OPS Officer: Ernest West
Notification Date: 12/24/2022
Notification Time: 05:08 [ET]
Event Date: 12/24/2022
Event Time: 02:22 [EST]
Last Update Date: 12/24/2022
Emergency Class: Non Emergency
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS Actuation - Critical 50.72(b)(3)(iv)(A) - Valid Specif Sys Actuation
Person (Organization):
Eve, Elise (R1DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 A/R Y 100 Power Operation 0 Hot Standby
Event Text
AUTOMATIC REACTOR TRIP

The following information was provided by the licensee via email:

"At 0222 [EST] on 12/24/22, with Unit 2 at 100 percent power during steady state operation, the reactor automatically tripped and a safety injection actuated due to steam generator differential pressure. The trip and safety injection were not complex, with all systems responding normally post-trip. An actuation of the auxiliary feedwater system occurred following the reactor trip as expected due to low level in the steam generators. The unit is stable in Mode 3. The turbine bypass steam dumps and auxiliary feedwater system are removing decay heat. Salem Unit 1 was not affected.

"Due to the actuation of the reactor protection system while critical, this event is being reported as a four hour, non-emergency notification per 10 CFR 50.72(b)(2)(iv)(B). This event is also being reported as an eight hour non-emergency notification in accordance with 10 CFR 50.72(b)(3)(iv)(A) as an event that results in a valid actuation of the auxiliary feedwater system.

"There was no impact to the health and safety of the public or plant personnel.

"The NRC Resident Inspector has been notified."