The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Event Notification Report for August 15, 2003






                    U.S. Nuclear Regulatory Commission

                              Operations Center



                              Event Reports For

                           08/14/2003 - 08/15/2003



                              ** EVENT NUMBERS **



39941  40055  40056  40060  40061  40063  40064  40065  40066  40067  40068  40069 

40070  40071  40072  40073  40074  40075  



+------------------------------------------------------------------------------+

|Hospital                                         |Event Number:   39941       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| REP ORG:  GUTHRIE HEALTH CARE                  |NOTIFICATION DATE: 06/16/2003|

|LICENSEE:  GUTHRIE HEALTH CARE                  |NOTIFICATION TIME: 09:20[EDT]|

|    CITY:  SAYRE                    REGION:  1  |EVENT DATE:        06/12/2003|

|  COUNTY:                            STATE:  PA |EVENT TIME:             [EDT]|

|LICENSE#:  37-01893-01           AGREEMENT:  N  |LAST UPDATE DATE:  08/14/2003|

|  DOCKET:                                       |+----------------------------+

|                                                |PERSON          ORGANIZATION |

|                                                |RAYMOND LORSON       R1      |

|                                                |DOUG BROADDUS        NMSS    |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  JOON PARK                    |                             |

|  HQ OPS OFFICER:  FANGIE JONES                 |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|LDIF 35.3045(a)(1)       DOSE <> PRESCRIBED DOSA|                             |

|LOTH 35.3045(a)(3)       DOSE TO OTHER SITE > SP|                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| DISCOVERY THAT PART OF THE IMPLANTED SEEDS WERE NOT IN THE PROPER SITE       |

|                                                                              |

| A patient was referred for treatment, due to reoccurring prostate cancer, to |

| the hospital where he had previously had treatment. Seeds were implanted     |

| around May 2001.  A scan of the previous treatment of implanted seeds        |

| determined that many of the seeds were not located in the prostate, but in   |

| adjacent tissue where they would have been ineffective in treatment.  Also,  |

| a review of the records indicated a scan was performed in early 2002, but    |

| was not followed up on. The patient and referring physician have been        |

| informed.  The hospital is conducting an investigation into the event and    |

| also developing a plan to provide appropriate treatment for the patient.     |

|                                                                              |

| * * * UPDATE ON 07/18/03 AT 1638 FROM JOON PARK TO ARLON COSTA * * *         |

|                                                                              |

| Post-op dosimetry on one patient was determined to be a misadministration.   |

| The dose that covered  the prostate was more than 20 percent different  from |

| the prescription as well as the penile bulb dose being close to 50 percent   |

| of the prescription dose.  Efforts are being made to contact the affected    |

| patient.  The licensee will continue efforts to obtain post-op dosimetry on  |

| the rest of the patients related to this incident so that  evaluations for   |

| misadministration can be performed.                                          |

|                                                                              |

| Notified R1DO (Della Greca) and NMSS EO (Pierson).                           |

|                                                                              |

| * * * UPDATE ON 07/25/03 AT 0921 EDT FROM JOON PARK TO JOHN MACKINNON * * *  |

|                                                                              |

| Post-op dosimetry for two patients were determined to be a                   |

| misadministration.  The patients had their prostates treated some time in    |

| the year 2001.  The iodine-125 seeds were placed  2 to 3 centimeters below   |

| the area where they were supposed to be located.  The improper location of   |

| the iodine-125 seeds caused more than 50% of the prescribed dose to be       |

| delivered to an un-intended organ.  The patients will be notified.           |

|                                                                              |

| Notified R1DO (Dan Holody) and NMSS EO (Trish Holahan).                      |

|                                                                              |

| * * * UPDATE ON 07/30/03 AT 0911 EDT FROM JOON PARK TO ARLON COSTA * * *     |

|                                                                              |

| Two additional patients of a group of seven were identified as having        |

| received a misadministration of iodine-125 to an unintended organ. The       |

| patients will be notified of this misadministration.  The licensee is in the |

| process of clarifying and document the issues related to this incident.      |

|                                                                              |

| Notified R1DO (James Moorman) and NMSS EO (Tom Essig).                       |

|                                                                              |

| * * * UPDATE ON 08/07/03 AT 1535 EDT FROM CHARLES LEE TO NATHAN SANFILIPPO * |

| * *                                                                          |

|                                                                              |

| Another patient has been identified who received a misadministration of      |

| iodine-125 to the prostate.  The prescribed dose was 144 Gy, and it was      |

| delivered using 76 seeds and 27 needles as planned prior to the implant      |

| date.  After reviewing the CT, which was done on Feb. 27, 2001, the V100 of  |

| the prostate received 29% of the prescribed dose.  The penile bulb at 72 Gy  |

| received 44.8%.  The licensee indicated that they have looked into 8         |

| patients who may have been misadministered, of which, one was not declared a |

| misadministration.  The other seven appear in this notification.  There are  |

| 23 total patients that the licensee intends to review.                       |

|                                                                              |

| Notified R1DO (Clifford Anderson) and NMSS EO (Fred Brown).                  |

|                                                                              |

| * * * FINAL UPDATE ON 08/14/03 AT 1150 EDT BY CHARLES LEE TO JOHN MACKINNON  |

| * * *                                                                        |

|                                                                              |

| Twelve more patients have been added to the number of patients. Patients are |

| identified by a six digit number.                                            |

|                                                                              |

| Patient# [deleted]- On this date, March 21, 2001, the former physician,      |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 77 seeds and 26 needles as planned prior to the     |

| implant, The V 100 of the prostate received 39% of the prescribed dose and   |

| the V50 of the penile bulb received 88%.                                     |

| Patient# [deleted]- On this date, May 23, 2001, the former physician,        |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| close was delivered using 53 seeds and 18 needles as planned prior to the    |

| implant. The V100 of the prostate received 62% of the prescribed dose and    |

| the V50 of the penile bulb received 57%,                                     |

| Patient# [deleted]- On this date, December. 13, 2001, the former physician,  |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 86 seeds and 21 needles as planned prior to the     |

| implant. The V 100 of the prostate received 70% of the prescribed dose and   |

| the V50 of the penile bulb received 99%.                                     |

| Patient# [deleted]- On this date, February 22, 2001, the former physician,   |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 77 seeds and 25 needles as planned prior to the     |

| implant. The V100 of the prostate received 52.5% of the prescribed dose and  |

| the V50 of the penile bulb received 80%.                                     |

| Patient# [deleted]- On this date, March 15, 2001, the former physician,      |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 67 seeds and 27 needles as planned prior to the     |

| implant. The V 100 of the prostate received 59% of the prescribed dose and   |

| the V50 of the penile bulb received 86.5%.                                   |

| Patient# [deleted]- On this date, July 5, 2001, the former physician,        |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 62 seeds and 21 needles as planned prior to the     |

| implant. The VI 00 of the prostate received 49% of the prescribed dose.      |

| Patient# [deleted]- On this date, February 8, 2001, the former physician,    |

| prescribed a dose of 144-Gy to the prostate using 1-125 seeds. The           |

| prescribed dose was delivered using 45 seeds and 18 needles as planned prior |

| to the implant. The V 100 of the prostate received 68% of the prescribed     |

| dose.                                                                        |

| Patient# [deleted]- On this date, September 5, 2001, the former physician,   |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds. The prescribed |

| dose was delivered using 58 seeds and 20 needles as planned prior to the     |

| implant. The V100 of the prostate received 59.5% of the prescribed dose.     |

| Patient# [deleted]- On this date, May 31, 2001, the former physician,        |

| prescribed a dose of 14-4Gy to the prostate using 1-125 seeds. The           |

| prescribed dose was delivered using 60 seeds and 17 needles as planned prior |

| to the implant. The V1 00 of the prostate received 68% of the prescribed.    |

| Dose.                                                                        |

| Patient# [deleted]- On this date, January 22, 2001, the former physician,    |

| prescribed a dose of 144Gy to the prostate using I-125 seeds. The prescribed |

| dose was delivered using 54 seeds and 3, 8 needles as planned prior to the   |

| implant. The V100 of the prostate received 73% of the prescribed dose,       |

| Patient# [deleted]- On this date, January 10, 2001, the former physician,    |

| prescribed a dose of 144Gy to the prostate using I-125 seeds. The prescribed |

| dose was delivered using 58 seeds and 19 needles as planned prior to the     |

| implant. The VI 00 of the prostate received 54% of the prescribed dose.      |

| Patient# [deleted]- On this date, June 21, 2001, the former physician,       |

| prescribed a dose of 144Gy to the prostate using 1-125 seeds, The prescribed |

| dose was delivered using 82 seeds 28 needles as planned prior to the         |

| implant, The V 100 of the prostate received 73% of the prescribed dose.      |

|                                                                              |

| Notified R1DO (Glenn Meyer) & NMSS EO (Linda Psyk).                          |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|General Information or Other                     |Event Number:   40055       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| REP ORG:  TEXAS DEPARTMENT OF HEALTH           |NOTIFICATION DATE: 08/11/2003|

|LICENSEE:  ARIAS & KEZAR, INC.                  |NOTIFICATION TIME: 16:32[EDT]|

|    CITY:  AUSTIN                   REGION:  4  |EVENT DATE:        08/08/2003|

|  COUNTY:                            STATE:  TX |EVENT TIME:             [CDT]|

|LICENSE#:  L04964-001            AGREEMENT:  Y  |LAST UPDATE DATE:  08/11/2003|

|  DOCKET:                                       |+----------------------------+

|                                                |PERSON          ORGANIZATION |

|                                                |PHIL HARRELL         R4      |

|                                                |M. WAYNE HODGES      NMSS    |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  JIM OGDEN                    |                             |

|  HQ OPS OFFICER:  HOWIE CROUCH                 |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|NAGR                     AGREEMENT STATE        |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| AGREEMENT STATE REPORT - TEXAS                                               |

|                                                                              |

| "On Friday, August 11, 2003, the Licensee was transporting the gauge in a    |

| Nissan Pickup truck that had a defective tailgate.  The Type 7A package was  |

| locked to the pickup with a chain but was held in place with a very small    |

| and cheap padlock.  Also in the truck were concrete samples being            |

| transported for analysis.  While transiting FM 471, the tailgate failed to   |

| the open position when the concrete samples shifted and pushed the gauge     |

| (Troxler Model 3430, Serial No. 28510, with two sealed sources - Am-241 /Be, |

| nominal 40 millicuries, Serial No. 47-25576; and Cs-137, nominal 8           |

| millicuries, Serial No. 750-2732) out of the bed and broke the lock allowing |

| the gauge to become detached from the truck.  The gauge was found by a       |

| member of the public laying in the middle of Highway FM471 being swerved     |

| around by traffic.  The member of the public stopped and picked up the       |

| package and placed in his vehicle and transported it to his residence at     |

| [address deleted], Helotes, Texas.  He opened the package which was not      |

| secured by a locking device. There is no indication that the member of the   |

| public exposed the sources.  He made notification to the Helotes Fire        |

| Department who in turn notified the Texas Department of Health's Public      |

| Health Region 8, Radiation Control Office in San Antonio.  The Public Health |

| Region responded with a Radioactive Materials Inspector who determined that  |

| the gauge was intact and appeared to have no damage.  The Licensee was       |

| notified and retrieved the gauge."                                           |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|General Information or Other                     |Event Number:   40056       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| REP ORG:  KENTUCKY DEPT OF RADIATION CONTROL   |NOTIFICATION DATE: 08/12/2003|

|LICENSEE:  UNIVERSITY OF KENTUCKY               |NOTIFICATION TIME: 14:10[EDT]|

|    CITY:  LEXINGTON                REGION:  2  |EVENT DATE:        06/23/2003|

|  COUNTY:  FAYETTE                   STATE:  KY |EVENT TIME:        15:30[CDT]|

|LICENSE#:  203-021-72            AGREEMENT:  Y  |LAST UPDATE DATE:  08/12/2003|

|  DOCKET:                                       |+----------------------------+

|                                                |PERSON          ORGANIZATION |

|                                                |DAVID AYRES          R2      |

|                                                |TOM ESSIG            NMSS    |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  ROB GRESHAM                  |                             |

|  HQ OPS OFFICER:  ERIC THOMAS                  |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|NAGR                     AGREEMENT STATE        |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| AGREEMENT STATE REPORT                                                       |

|                                                                              |

| "On June 23, 2003 at 3:30 PM the [University of Kentucky] radiation safety   |

| office received a call from an AU [Authorized User] in the Dept. of Biology, |

| because a shipment of I-125, triiodothyronine, 100 microcuries, had not been |

| received.  Upon review of the records it was found that the package had      |

| arrived on June 18, 2003, and had measured 10 [millirem]/hr at the surface,  |

| 0.1 [millirem]/hr @ 1meter, and no external contamination. The Radiation     |

| Safety Office shipping paper record shows the I-125 package was included for |

| delivery to room 109, Research Building 3, on June 19.  The required         |

| signature of receipt for the package was not obtained.  With the DOT         |

| shipping labels removed, the greatest likelihood is that the package was put |

| into the ordinary trash.  A thorough search of the Radiation Safety Office   |

| facilities and vehicles was conducted on June 23.  On June 24, the           |

| authorized user's lab was searched, including use of a low energy NAI (Tl)   |

| detector, as well as all labs where deliveries were made on June 19.  No     |

| trace of the package or contents has been found.  It was concluded that the  |

| highest probability was that the package entered the normal waste stream and |

| went to a landfill. Once in a landfill, the I-125 will be sequestered from   |

| any contact, and will be essentially non-radioactive in 1.65 years.          |

| Assuming worst case scenarios, the dose rate to the torso would be about 10  |

| [millirem]/hr or less, and would have to be held against the body            |

| continuously by a single individual for 10 hours to produce a dose in excess |

| of 100 [millirem].  Additionally there is no indication or likelihood of     |

| intentional or accidental ingestion of the contents since this is not        |

| intended for human use.  However, if the entire 100 microcuries were         |

| ingested by a single individual, as sodium iodide, the thyroid dose would be |

| 78 rem, and the effective dose would be 2.4 rem.  While no thyroid dose      |

| information has been  found for the triiodothyronine form, the effective     |

| dose from ingestion of 100 microcuries would be 17 [millirem].  Surveys are  |

| conducted on a continual basis, if the package did not go to a landfill it   |

| would likely be found during monthly use area surveys or quarterly           |

| supervisory surveys.  No NOV was issued based on the corrective actions      |

| taken by licensee to correct deficiencies prior to report completion."       |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Other Nuclear Material                           |Event Number:   40060       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| REP ORG:  UNIVERSITY OF PENNSYLVANIA           |NOTIFICATION DATE: 08/14/2003|

|LICENSEE:  UNIVERSITY OF PENNSYLVANIA           |NOTIFICATION TIME: 09:00[EDT]|

|    CITY:  PHILADELPHIA             REGION:  1  |EVENT DATE:        07/01/2003|

|  COUNTY:                            STATE:  PA |EVENT TIME:             [EDT]|

|LICENSE#:                        AGREEMENT:  N  |LAST UPDATE DATE:  08/14/2003|

|  DOCKET:                                       |+----------------------------+

|                                                |PERSON          ORGANIZATION |

|                                                |GLENN MEYER          R1      |

|                                                |JOHN HICKEY          NMSS    |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  ROBERT FORREST               |                             |

|  HQ OPS OFFICER:  RICH LAURA                   |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|BLO2 20.2201(a)(1)(ii)   LOST/STOLEN LNM>10X    |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| MISSING SOURCE AT UNIVERSITY OF PENNSYLVANIA                                 |

|                                                                              |

| "During a routine sealed source inventory in July 2003, a technician from    |

| the University of Pennsylvania's Office of Environmental Health and          |

| Radiation Safety (EHRS) found that a Hewlett-Packard 6890 gas chromatograph  |

| (GC) containing a generally licensed 15 millicuries source of Ni-63 was      |

| missing from a laboratory undergoing renovations. EHRS contacted faculty and |

| staff associated with the laboratory trying to locate the instrument. After  |

| an extensive search, it was determined that the GC was most likely sent to a |

| scrap metal dealer. According to NUREG-1717, Systematic Radiological         |

| Assessment of Exemptions for Source and Byproduct Materials, the dose to any |

| individual from a scrapped Ni-63 gas chromatograph source would be less than |

| 0.01 millisievert (1 millirem)"                                              |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40061       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: KEWAUNEE                 REGION:  3  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  WI |NOTIFICATION TIME: 10:57[EDT]|

|   RXTYPE: [1] W-2-LP                           |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        09:10[CDT]|

| NRC NOTIFIED BY:  ETHAN TREPTOW                |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  RICH LAURA                   +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |SONIA BURGESS        R3      |

|10 CFR SECTION:                                 |                             |

|ACOM 50.72(b)(3)(xiii)   LOSS COMM/ASMT/RESPONSE|                             |

|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       100      Power Operation  |100      Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| EP SIRENS OUT OF SERVICE IN KEWAUNEE COUNTY                                  |

|                                                                              |

| "At 0910 on August 14, It was reported to the Control Room that all thirteen |

| Kewaunee County sirens had a communications problem that rendered them out   |

| of service. The percent siren coverage population lost is 68.52%. The State  |

| and County have been notified of the siren failures. The siren vendor has    |

| been contacted to begin troubleshooting the problem.                         |

|                                                                              |

| "This is being reported under 10 CFR 50.72(b)(3)(xiii) as any event that     |

| results in a major loss of emergency assessment capability, offsite response |

| capability, or offsite communications capability (loss of greater than 50%   |

| of emergency sirens). It is also being reported under 10 CFR 50.72(b)(2)(xi) |

| as any event or situation, related to the health and safety of the public or |

| onsite personnel, or protection of the environment, for which a news release |

| is planned or notification to other government agencies has been or will be  |

| made."                                                                       |

|                                                                              |

| The NRC resident inspector was notified.                                     |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40063       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: PERRY                    REGION:  3  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  OH |NOTIFICATION TIME: 16:33[EDT]|

|   RXTYPE: [1] GE-6                             |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:10[EDT]|

| NRC NOTIFIED BY:  JOE KOTAR                    |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |SONIA BURGESS        R3      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER GREATER THAN 15          |

| MINUTES.                                                                     |

|                                                                              |

| Automatic reactor scram due to a loss of offsite power.  All rods fully      |

| inserted.  Supplying power to vital buses via emergency diesel generators.   |

| All system operating properly.                                               |

|                                                                              |

| NRC Resident Inspector was notified of the event by the licensee.            |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40064       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: PALISADES                REGION:  3  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  MI |NOTIFICATION TIME: 17:10[EDT]|

|   RXTYPE: [1] CE                               |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:07[EDT]|

| NRC NOTIFIED BY:  VANDENALLE                   |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |SONIA BURGESS        R3      |

|10 CFR SECTION:                                 |                             |

|AESF 50.72(b)(3)(iv)(A)  VALID SPECIF SYS ACTUAT|                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       100      Power Operation  |100      Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| POWER GRID DISTURBANCE OCCURRED RESULTING IN A MOMENTARY DROP IN VOLTAGE     |

|                                                                              |

| At 1607 EDT a significant electrical power grid disturbance occurred         |

| resulting in a momentary drop in voltage at the site, including both 2400    |

| VAC safety busses 1C and 1D.  The reduced voltage on the 2400VAC safety      |

| busses caused both emergency diesel generators to auto start, but not load.  |

| The plant is stable at pre-event conditions.                                 |

|                                                                              |

| The NRC Resident Inspector was notified.                                     |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40065       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: OYSTER CREEK             REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  NJ |NOTIFICATION TIME: 18:16[EDT]|

|   RXTYPE: [1] GE-2                             |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:11[EDT]|

| NRC NOTIFIED BY:  CIGANIK                      |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |                             |

|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| REACTOR SCRAM FROM 100% POWER DUE TO OFF SITE ELECTRICAL GRID INSTABILITY    |

|                                                                              |

| Reactor scram from 100% due to off site electrical grid instability, but did |

| not lose off site power.  Reactor conditions at 1730 are normal reactor      |

| water level, reactor pressure 850-1000psig, MSIV's closed and all recirc     |

| pumps are off and reactor is in hot shutdown with all rods inserted.         |

|                                                                              |

| The NRC Resident Inspector                                                   |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40066       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: NINE MILE POINT          REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [] [2] []                 STATE:  NY |NOTIFICATION TIME: 17:34[EDT]|

|   RXTYPE: [1] GE-2,[2] GE-5                    |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        17:00[EDT]|

| NRC NOTIFIED BY:  MORAN                        |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |HYMAN                FEMA    |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |STUART RICHARDS      NRR     |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|                                                   |                          |

|2     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| NOUE WAS DECLARED AT 1700 DUE TO LOSS OF OFFSITE POWER                       |

|                                                                              |

| The plant lost off site power due to grid disturbance which resulted in a    |

| reactor trip from 100% power. The NOUE was declared because of loss of off   |

| site power was greater than 15 minutes.                                      |

|                                                                              |

|                                                                              |

| The NRC Resident Inspector was notified.                                     |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40067       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: INDIAN POINT             REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [2] [] []                 STATE:  NY |NOTIFICATION TIME: 16:39[EDT]|

|   RXTYPE: [2] W-4-LP,[3] W-4-LP                |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:25[EDT]|

| NRC NOTIFIED BY:  MARK COX                     |LAST UPDATE DATE:  08/15/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |

|AESF 50.72(b)(3)(iv)(A)  VALID SPECIF SYS ACTUAT|                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|2     A/R        Y       100      Power Operation  |0        Hot Standby      |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER GREATER THAN 15          |

| MINUTES.                                                                     |

|                                                                              |

| Automatic reactor scram due to a loss of offsite power.  All rods fully      |

| inserted.  Supplying power to vital buses via emergency diesel generators.   |

| All systems operating properly.                                              |

|                                                                              |

| NRC Resident Inspector was notified of the event by the licensee.            |

|                                                                              |

| * * * UPDATE 2340EDT ON 8/14/03 FROM ANDY MIHALIK TO S.SANDIN * * *          |

|                                                                              |

| The following information was provided as an update:                         |

|                                                                              |

| "RPS Actuation (loss of flow) due to loss of offsite power.  Auto actuation  |

| of AFW in response to the unit trips.  Auto start & load of Emergency Diesel |

| Generators in response to the loss of offsite power."                        |

|                                                                              |

| The licensee informed the state/local authorities and the NRC resident       |

| inspector.  Notified R1IRC.                                                  |

|                                                                              |

| *****UPDATE ON 8/15/03 AT 0226 FROM CELENTANO TO GOTT*****                   |

|                                                                              |

| The licensee exited the Unusual Event at 0210 upon confirmation of a stable  |

| off-site power.                                                              |

|                                                                              |

| Notified R1 IRC and FEMA(Heyman).                                            |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40068       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: GINNA                    REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  NY |NOTIFICATION TIME: 16:46[EDT]|

|   RXTYPE: [1] W-2-LP                           |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:12[EDT]|

| NRC NOTIFIED BY:  PAUL HARRIS                  |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Standby      |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER GREATER THAN 15          |

| MINUTES.                                                                     |

|                                                                              |

| Automatic reactor trip due to a loss of offsite power.  All rods fully       |

| inserted into the core.   All emergency systems operated as expected.        |

|                                                                              |

| NRC Resident Inspector was of this event by the licensee.                    |

|                                                                              |

| * * * UPDATE 0510EDT ON 8/15/03 FROM McCOY TO S.SANDIN * * *                 |

|                                                                              |

| Unit exited the UE at 2108EDT on 8/14/03 after restoration of offsite power. |

| The licensee informed state.local agencies and the NRC resident inspector.   |

| Notified R1IRC and FEMA(Heyman).                                             |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40069       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: INDIAN POINT             REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [] [3] []                 STATE:  NY |NOTIFICATION TIME: 16:50[EDT]|

|   RXTYPE: [2] W-4-LP,[3] W-4-LP                |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:23[EDT]|

| NRC NOTIFIED BY:  MESSINA                      |LAST UPDATE DATE:  08/15/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |

|AESF 50.72(b)(3)(iv)(A)  VALID SPECIF SYS ACTUAT|                             |

|ASHU 50.72(b)(2)(i)      PLANT S/D REQD BY TS   |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|                                                   |                          |

|3     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER GREATER THAN 15          |

| MINUTES.                                                                     |

|                                                                              |

| Automatic reactor scram due to a loss of offsite power.  All rods fully      |

| inserted.  Supplying power to vital buses via emergency diesel generators.   |

| All systems operating properly.                                              |

|                                                                              |

| NRC Resident Inspector was notified of the event by the licensee.            |

|                                                                              |

| * * * UPDATE 2340EDT ON 8/14/03 FROM ANDY MIHALIK TO S.SANDIN * * *          |

|                                                                              |

| The following information was provided as an update:                         |

|                                                                              |

| "RPS Actuation (loss of flow) due to loss of offsite power.  Auto actuation  |

| of AFW in response to the unit trips.  Auto start & load of Emergency Diesel |

| Generators in response to the loss of offsite power.  Unit 3 also            |

| experienced a second AFW auto start during the event.  Unit 3 also entered   |

| Tech Spec LCO 3.0.3 for loss of two offsite circuits and one EDG inoperable. |

| #31 EDG was declared inoperable when its associated Fuel oil storage tank    |

| inventory decreased below required."                                         |

|                                                                              |

| The licensee informed the state/local authorities and the NRC resident       |

| inspector.  Notified R1IRC.                                                  |

|                                                                              |

| *****UPDATE ON 8/15/03 AT 0226 FROM CELENTANO TO GOTT*****                   |

|                                                                              |

| The licensee exited the Unusual Event at 0210 upon confirmation of a stable  |

| off-site power.                                                              |

|                                                                              |

| Notified R1 IRC and FEMA(Heyman).                                            |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40070       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: DAVIS BESSE              REGION:  3  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  OH |NOTIFICATION TIME: 16:54[EDT]|

|   RXTYPE: [1] B&W-R-LP                         |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:10[EDT]|

| NRC NOTIFIED BY:  DON BONDY                    |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |SONIA BURGESS        R3      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          N       0        Cold Shutdown    |0        Cold Shutdown    |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO A LOSS OF OFFSITE POWER.                       |

|                                                                              |

| All systems operated as expected.   Decay Heat pumps are available if        |

| needed.                                                                      |

|                                                                              |

| NRC Resident Inspector was notified of this event by the licensee.           |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40071       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: NINE MILE POINT          REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  NY |NOTIFICATION TIME: 17:15[EDT]|

|   RXTYPE: [1] GE-2,[2] GE-5                    |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:35[EDT]|

| NRC NOTIFIED BY:  HELKER                       |LAST UPDATE DATE:  08/15/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER GREATER THAN 15 MINUTES. |

|                                                                              |

|                                                                              |

| Automatic reactor scram due to a loss of offsite power.  All rods fully      |

| inserted into the core.  All emergency core cooling systems are operating    |

| properly and the emergency diesel generators are operating properly.         |

|                                                                              |

| NRC Resident Inspector was notified of this event by the licensee.           |

|                                                                              |

| *****UPDATE 8/15/03 AT 0145 TO LAURA*****                                    |

|                                                                              |

| Offsite electrical power was restored. The licensee exited the Unusual Event |

| at 0123.  Notified R1IRC  and FEMA(Heyman).                                  |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40072       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: FITZPATRICK              REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  NY |NOTIFICATION TIME: 17:17[EDT]|

|   RXTYPE: [1] GE-4                             |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:11[EDT]|

| NRC NOTIFIED BY:  TIM PAGE                     |LAST UPDATE DATE:  08/15/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO A LOSS OF OFFSITE POWER.                       |

|                                                                              |

| Automatic reactor scram due to a loss of offsite power. All rods fully       |

| inserted into the core.  All emergency core cooling systems and the          |

| emergency diesel generators are operating properly.                          |

|                                                                              |

| NRC Resident Inspector was notified of this event by the licensee.           |

|                                                                              |

| *****UPDATE ON 8/15/03 AT 0035 FROM PAGE TO LAURA*****                       |

|                                                                              |

| Reactor vessel pressure is 93 psig.  Plant electrical loads have been        |

| shifted back to offsite power and the EDGs were secured. The licensee exited |

| the Unusual Event at 0039. The licensee tentatively plans to remain shutdown |

| for a brief period to do some maintenance work.                              |

|                                                                              |

| Notified R1IRC  and FEMA(Heyman).                                            |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40073       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: INDIAN POINT             REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [2] [3] []                STATE:  NY |NOTIFICATION TIME: 18:49[EDT]|

|   RXTYPE: [2] W-4-LP,[3] W-4-LP                |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:25[EDT]|

| NRC NOTIFIED BY:  FINUCAH                      |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |                             |

|ACOM 50.72(b)(3)(xiii)   LOSS COMM/ASMT/RESPONSE|                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|2     N          N       0        Hot Shutdown     |0        Hot Shutdown     |

|3     N          N       0        Hot Shutdown     |0        Hot Shutdown     |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| EMERGENCY SIRENS LOST IN FOUR COUNTIES                                       |

|                                                                              |

| Emergency sirens lost in four counties due to a loss of power.  At           |

| approximately 1830 hours power starting to be returned to the sirens.        |

|                                                                              |

| NRC Resident Inspector notified of this event by the licensee.               |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40074       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: GINNA                    REGION:  1  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [1] [] []                 STATE:  NY |NOTIFICATION TIME: 20:07[EDT]|

|   RXTYPE: [1] W-2-LP                           |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:11[EDT]|

| NRC NOTIFIED BY:  Roy Gillow                   |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |GLENN MEYER          R1      |

|10 CFR SECTION:                                 |                             |

|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |

|AESF 50.72(b)(3)(iv)(A)  VALID SPECIF SYS ACTUAT|                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     A/R        Y       100      Power Operation  |0        Hot Standby      |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| REACTOR TRIP/AUXILIARY FEEDWATER ACTUATION                                   |

|                                                                              |

| Received grid disturbance that caused reactor trip at 1611.  The trip        |

| occurred due to over temperature delta set point being reached from load     |

| swings experienced on the generator. Subsequently in the recovery process,   |

| the Auxiliary Feedwater Pumps auto started from a signal from the Main       |

| Feedwater Pumps being secured. As a result of grid problems it was noted     |

| that Ginna did not meet the required number of emergency sirens (greater     |

| than 25% of sirens without power).                                           |

|                                                                              |

|                                                                              |

| NRC Resident Inspector was notified of this event by the licensee.           |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   40075       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: FERMI                    REGION:  3  |NOTIFICATION DATE: 08/14/2003|

|    UNIT:  [2] [] []                 STATE:  MI |NOTIFICATION TIME: 20:08[EDT]|

|   RXTYPE: [2] GE-4                             |EVENT DATE:        08/14/2003|

+------------------------------------------------+EVENT TIME:        16:10[EDT]|

| NRC NOTIFIED BY:  KEVIN DAHM                   |LAST UPDATE DATE:  08/14/2003|

|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          UNUSUAL EVENT         |SONIA BURGESS        R3      |

|10 CFR SECTION:                                 |STUART RICHARDS      NRR     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |HYMAN                FEMA    |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|2     A/R        Y       100      Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| PLANT ENTERED AN NOUE DUE TO THE LOSS OF OFF SITE POWER                      |

|                                                                              |

| The reactor scrammed from 100% power due to fluctuations occurring on the    |

| main generator and a loss of off site power.  All rods fully inserted and    |

| all MSIV's closed.  Reactor level is being maintained in the normal band of  |

| 173 to 214 inches using RCIC.  Reactor pressure is being controlled via      |

| SRV's in lo-lo set mode between 905 and 1017 psig.  Isolations occurred as   |

| expected for level 2 and level 3.  HPCI and RCIC started on level 2 signal.  |

| HPCI has been shutdown but is available.  All 4 EDG's started and loaded.    |

|                                                                              |

| The NRC Resident Inspector was notified.                                     |

+------------------------------------------------------------------------------+





                    

Page Last Reviewed/Updated Wednesday, March 24, 2021