The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Event Notification Report for July 1, 2003






                    U.S. Nuclear Regulatory Commission

                              Operations Center



                              Event Reports For

                           06/30/2003 - 07/01/2003



                              ** EVENT NUMBERS **



39958  39965  39966  39967  39968  39969  39970  







+------------------------------------------------------------------------------+

|General Information or Other                     |Event Number:   39958       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| REP ORG:  NC DIV OF RADIATION PROTECTION       |NOTIFICATION DATE: 06/25/2003|

|LICENSEE:  BARNHILL CONTRACTING COMPANY         |NOTIFICATION TIME: 10:45[EDT]|

|    CITY:  CHAPEL HILL              REGION:  2  |EVENT DATE:        06/25/2003|

|  COUNTY:                            STATE:  NC |EVENT TIME:        10:20[EDT]|

|LICENSE#:                        AGREEMENT:  Y  |LAST UPDATE DATE:  06/26/2003|

|  DOCKET:                                       |+----------------------------+

|                                                |PERSON          ORGANIZATION |

|                                                |CHARLES R. OGLE      R2      |

|                                                |DOUG BROADDUS        NMSS    |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  SHARN JEFFRIES               |                             |

|  HQ OPS OFFICER:  STEVE SANDIN                 |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|NAGR                     AGREEMENT STATE        |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| DAMAGED TROXLER DENSITY GAUGE                                                |

|                                                                              |

| At 1020 EDT on 6/25/03, the NC Radiation Protection Section was notified     |

| that a portable nuclear gauge being used was run over by a passenger van at  |

| the intersection of Faivon and Bucchaneer Roads (near Hwy 40 and the 55      |

| interchange).  The Authorized User is on site and has the gauge cordoned off |

| as per emergency procedures require.  The van involved in the collision is   |

| being detained..  Both the RSO and Alt RSO are enroute to perform surveys (1 |

| hour).                                                                       |

|                                                                              |

| NC Radiation Protection Section personnel are responding to the scene to     |

| perform surveys (30 mins).                                                   |

|                                                                              |

| The device is described as a Troxler Gauge containing 8 millicuries Cs-137.  |

| NC Incident Report No.: 03-27.                                               |

|                                                                              |

| * * * UPDATE 0952 EDT ON 6/26/03 FROM NC RAD PROTECTION VIA FAX * * *        |

|                                                                              |

| The following additional information was provided by NC:                     |

|                                                                              |

| Incident Location: Chapel Hill, NC . Intersection of Faison and Buckner      |

| Roads. Take 40 West from Raleigh to the NC54 exit towards Chapel Hill. Take  |

| a right onto Meadowmont, then a left onto Sprunt. Follow Sprunt to Weaver    |

| Lane and take a right onto Weaver Lane. Take a right on Faison off of Weaver |

| lane, go downhill to the intersection of Faison and Buckner.                 |

|                                                                              |

| Brief Description of Incident: Paving contractor in a commercial van was not |

| watching where he was driving and ran over the instrument panel part of a    |

| Troxler model 4640B thin lift density gauge. The licensee was performing a   |

| standardization count on the gauge at the time of the accident so the source |

| was in the shielded position when it was run over. The gauge was pushed off  |

| the standardization plate and dragged about 3 feet. The gauge then rolled    |

| onto it's side and the source handle was shoved into the asphalt. The        |

| licensee stopped the van and detained it and the driver until the gauge      |

| could be surveyed and it was determined that there were no loose source or   |

| contamination concerns. The area was cordoned off with pink surveyors' tape  |

| and controlled until the gauge and accident area was surveyed and the gauge  |

| returned to the Troxler shipping container. Survey results of the gauge done |

| by both the licensee and the NCDENR RAM Branch were consistent with an       |

| undamaged gauge. The licensee placed the gauge into the Troxler              |

| transportation case for delivery to Troxler for leak testing and servicing.  |

| The damage appears to be cosmetic with some damage to be expected to the     |

| electronics.                                                                 |

|                                                                              |

| Radiological Information: Isotope(s): Cesium-137, Activity: 8 millicuries,   |

| Device: Troxler Gauge, model 4640B                                           |

|                                                                              |

| Notified R2DO (C. Ogle) and NMSS (Broaddus).                                 |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   39965       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: COLUMBIA GENERATING STATIREGION:  4  |NOTIFICATION DATE: 06/30/2003|

|    UNIT:  [2] [] []                 STATE:  WA |NOTIFICATION TIME: 14:39[EDT]|

|   RXTYPE: [2] GE-5                             |EVENT DATE:        06/30/2003|

+------------------------------------------------+EVENT TIME:        09:18[PDT]|

| NRC NOTIFIED BY:  SCOTT BURTON                 |LAST UPDATE DATE:  06/30/2003|

|  HQ OPS OFFICER:  HOWIE CROUCH                 +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |CHARLES MARSCHALL    R4      |

|10 CFR SECTION:                                 |                             |

|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|2     A/R        Y       79       Power Operation  |0        Hot Shutdown     |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| VALID REACTOR PROTECTION SYSTEM ACTUATION                                    |

|                                                                              |

| The following information was obtained from the licensee via facsimile:      |

|                                                                              |

| "This event notification is being made to report the valid actuation of the  |

| reactor protection system when the reactor was critical, and subsequent      |

| reactor scram.  On June 30, 2003, [at 0918 PDT], the plant was in Mode 1 at  |

| 79% power, when a turbine trip occurred, followed by a reactor scram.  The   |

| cause of the turbine trip is unknown at this time.  All plant systems        |

| functioned properly in response to the scram.  Operators are proceeding to   |

| bring the plant to Mode 4, Cold Shutdown, while investigation into the cause |

| of the transient is completed."                                              |

|                                                                              |

| During the scram, all rods inserted into the core.  There were no lifts of   |

| power-operated or manual relief valves during the transient.  The electrical |

| grid is stable and powering all safety equipment.  There were no other       |

| specified system actuations.  Decay heat is being removed via the bypass     |

| valves to the main condenser.                                                |

|                                                                              |

| The licensee has informed the NRC Resident Inspector.                        |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   39966       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: PERRY                    REGION:  3  |NOTIFICATION DATE: 06/30/2003|

|    UNIT:  [1] [] []                 STATE:  OH |NOTIFICATION TIME: 15:54[EDT]|

|   RXTYPE: [1] GE-6                             |EVENT DATE:        06/30/2003|

+------------------------------------------------+EVENT TIME:        15:41[EDT]|

| NRC NOTIFIED BY:  DAVE BLOUNT                  |LAST UPDATE DATE:  06/30/2003|

|  HQ OPS OFFICER:  HOWIE CROUCH                 +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |BRENT CLAYTON        R3      |

|10 CFR SECTION:                                 |TIM MCGINTY          IRO     |

|AAEC 50.72(a) (1) (i)    EMERGENCY DECLARED     |BOB DENNIG           NRR     |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       100      Power Operation  |100      Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| UNUSUAL EVENT DECLARED DUE TO SEISMIC EVENT IN THE AREA                      |

|                                                                              |

| At 1541 EDT on 6/30/03,  Perry Nuclear Plant declared an Unusual Event due   |

| to a seismic event.  No immediate issues were noticed.  The operating-basis  |

| earthquake/safe-shutdown annunciator did not alarm, however the plant did    |

| receive a seismic panel alarm.  The set point for the alarm is 0.005g.       |

| There were no unplanned radioactive releases.  No protective action          |

| recommendations are advised by the licensee.  State and local counties       |

| (Lake, Geauga and Ashtabula) have been informed.                             |

|                                                                              |

| The National Earthquake Information Center has preliminary indications that  |

| the earthquake measured 3.4 on the Richter scale at 41.7 N latitude and 81.2 |

| W longitude near Painesville, OH.                                            |

|                                                                              |

| The licensee has notified the NRC Resident Inspector                         |

|                                                                              |

| * * *  UPDATE AT 2242 ON 06/30/03 CARMAN TO GOTT * * *                       |

|                                                                              |

| Licensee terminated from unusual event.  Action needed to terminate from the |

| unusual event was a plant walk down.  The licensee completed same with no    |

| plant damage identified, no unplanned radiological release, and no planned   |

| corrective actions.                                                          |

|                                                                              |

| The licensee notified the NRC Resident and Senior Resident Inspectors.       |

|                                                                              |

| Notified NRR EO (Ruland), DIRO Manager (McGinty), DHS (Murray), FEMA         |

| (Stiendurf), and R3DO (Clayton)                                              |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   39967       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: SEABROOK                 REGION:  1  |NOTIFICATION DATE: 06/30/2003|

|    UNIT:  [1] [] []                 STATE:  NH |NOTIFICATION TIME: 17:20[EDT]|

|   RXTYPE: [1] W-4-LP                           |EVENT DATE:        06/30/2003|

+------------------------------------------------+EVENT TIME:        14:59[EDT]|

| NRC NOTIFIED BY:  RON STRICKLAND               |LAST UPDATE DATE:  06/30/2003|

|  HQ OPS OFFICER:  BILL GOTT                    +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |RICHARD BARKLEY      R1      |

|10 CFR SECTION:                                 |DIANE SCRENCI        R1PA    |

|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |WILLIAM BEECHER      PAO     |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       100      Power Operation  |100      Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| OFFSITE NOTIFICATION DUE TO FIRE                                             |

|                                                                              |

| "At 1459 EDT 06/30/03 a fire was reported on Unit II containment.  The fire  |

| was on wooden staging, and was about the size of a normal campfire.  The     |

| fire was a result of the disassembly of the Unit II containment dome.  Per   |

| procedure, the Seabrook Fire Department was called and responded.  The fire  |

| was extinguished by the Unit II disassembly crew (the onsite fire brigade    |

| did not respond because the fire was outside of the Unit I protected area).  |

| The Seabrook Fire Department was not used to extinguish the fire.  Corporate |

| Communications Group have been in contact with Channel 9 and with the        |

| Associated Press.  The fire was extinguished at 1535 using prestaged hoses.  |

| The fire water was provided by Hydrant #15 of Seabrook Station's Fire        |

| Protection System."                                                          |

|                                                                              |

| The NRC Resident Inspector was notified.                                     |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   39968       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: BRUNSWICK                REGION:  2  |NOTIFICATION DATE: 06/30/2003|

|    UNIT:  [1] [] []                 STATE:  NC |NOTIFICATION TIME: 17:30[EDT]|

|   RXTYPE: [1] GE-4,[2] GE-4                    |EVENT DATE:        06/30/2003|

+------------------------------------------------+EVENT TIME:        17:10[EDT]|

| NRC NOTIFIED BY:  D. W. BAIN                   |LAST UPDATE DATE:  06/30/2003|

|  HQ OPS OFFICER:  ERIC THOMAS                  +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |CHARLES R. OGLE      R2      |

|10 CFR SECTION:                                 |                             |

|ASHU 50.72(b)(2)(i)      PLANT S/D REQD BY TS   |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       93       Power Operation  |92       Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| TECH SPEC REQUIRED SHUTDOWN                                                  |

|                                                                              |

| On June 30, 2003, at 1710 EDT, Unit 1 reactor power was decreased,           |

| initiating a reactor shutdown required by                                    |

| Technical Specification (TS) Limiting Condition for Operation (LCO) 3.4.4    |

| due to Reactor Coolant System (RCS)                                          |

| operational leakage exceeding a TS LCO limit.  At 0615 hours, TS LCO 3.4.4   |

| was entered due to an increase in                                            |

| unidentified leakage of greater than 2 gpm (gallons per minute) within the   |

| previous 24 hour period.  Leakage increased from 0.63 gpm on June 29, 2003   |

| at 2000 EDT, to 2.69 gpm on June 30, 2003 at 0615 EDT.  Required Actions     |

| from LCO 3.4.4 are to reduce leakage to within TS limits within 8 hours or   |

| be in Mode 3 (Hot Shutdown) in 12 hours and Mode 4 (Cold Shutdown) in 36     |

| hours.  As of 1700 EDT, leakage could not be reduced to exit the TS LCO      |

| Condition.                                                                   |

|                                                                              |

| The licensee notified the NRC Resident Inspector.                            |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Research Reactor                                 |Event Number:   39969       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: MASSACHUSETTS INSTITUTE OF TECH      |NOTIFICATION DATE: 06/30/2003|

|   RXTYPE: 5000 KW TANK RESEARCH HW             |NOTIFICATION TIME: 17:44[EDT]|

| COMMENTS:                                      |EVENT DATE:        06/30/2003|

|                                                |EVENT TIME:        06:45[EDT]|

|                                                |LAST UPDATE DATE:  06/30/2003|

|    CITY:  CAMBRIDGE                REGION:  1  +-----------------------------+

|  COUNTY:  MIDDLESEX                 STATE:  MA |PERSON          ORGANIZATION |

|LICENSE#:  R-37                  AGREEMENT:  N  |RICHARD BARKLEY      R1      |

|  DOCKET:  05000020                             |ALEXANDER ADAMS      NRR     |

+------------------------------------------------+                             |

| NRC NOTIFIED BY:  JOHN BERNARD                 |                             |

|  HQ OPS OFFICER:  BILL GOTT                    |                             |

+------------------------------------------------+                             |

|EMERGENCY CLASS:          NON EMERGENCY         |                             |

|10 CFR SECTION:                                 |                             |

|NINF                     INFORMATION ONLY       |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

|                                                |                             |

+------------------------------------------------------------------------------+



                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| OPERATOR ASLEEP AT REACTOR CONTROLS                                          |

|                                                                              |

| The following was emailed from the licensee to the NRC Project Manager:      |

|                                                                              |

| "The licensee Facility Director called the NRC project manager to report     |

| that on 6/29/03 between 0605 EDT and 0645, the operator at the control       |

| console fell asleep for approximately 25 minutes.  The operator had logged   |

| console operations at 0605 and 0645.  Other licensee personnel had tried to  |

| contact the console operator during this time period without success.  The   |

| licensee is investigating the event and will review this situation with all  |

| reactor operators."                                                          |

|                                                                              |

| This is in violation of 10 CFR 50.54 (k).                                    |

+------------------------------------------------------------------------------+



+------------------------------------------------------------------------------+

|Power Reactor                                    |Event Number:   39970       |

+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+

| FACILITY: MONTICELLO               REGION:  3  |NOTIFICATION DATE: 07/01/2003|

|    UNIT:  [1] [] []                 STATE:  MN |NOTIFICATION TIME: 00:04[EDT]|

|   RXTYPE: [1] GE-3                             |EVENT DATE:        06/30/2003|

+------------------------------------------------+EVENT TIME:        15:45[CDT]|

| NRC NOTIFIED BY:  DAVID BARNETT                |LAST UPDATE DATE:  07/01/2003|

|  HQ OPS OFFICER:  MIKE RIPLEY                  +-----------------------------+

+------------------------------------------------+PERSON          ORGANIZATION |

|EMERGENCY CLASS:          NON EMERGENCY         |BRENT CLAYTON        R3      |

|10 CFR SECTION:                                 |                             |

|AINA 50.72(b)(3)(v)(A)   POT UNABLE TO SAFE SD  |                             |

|AINB 50.72(b)(3)(v)(B)   POT RHR INOP           |                             |

|AINC 50.72(b)(3)(v)(C)   POT UNCNTRL RAD REL    |                             |

|AIND 50.72(b)(3)(v)(D)   ACCIDENT MITIGATION    |                             |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |

+-----+----------+-------+--------+-----------------+--------+-----------------+

|1     N          Y       100      Power Operation  |100      Power Operation  |

|                                                   |                          |

|                                                   |                          |

+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   

+------------------------------------------------------------------------------+

| HIGH ENERGY LINE BREAK (HELB) DOOR NOT LATCHED                               |

|                                                                              |

| "On June 30, 2003 at approximately 1545 [CDT] it was identified that a High  |

| Energy Line Break (HELB) door separating Divisional Motor Control Centers    |

| was not latched as required.  It was determined that this condition existed  |

| for a maximum of 15 minutes.  This condition is being reported as an event   |

| or condition that could have prevented the fulfillment of a safety function  |

| in accordance with 10 CFR 50.72(b)(3)(v)."                                   |

|                                                                              |

| The licensee notified the NRC Resident Inspector and the State Emergency     |

| Management Agency.                                                           |

+------------------------------------------------------------------------------+

          

Page Last Reviewed/Updated Thursday, March 25, 2021