Event Notification Report for May 20, 2003
U.S. Nuclear Regulatory Commission Operations Center Event Reports For 05/19/2003 - 05/20/2003 ** EVENT NUMBERS ** 39680 39850 39857 39858 39859 39860 39861 39862 !!!!!!!!! THIS EVENT HAS BEEN RETRACTED. THIS EVENT HAS BEEN RETRACTED !!!!!!! +------------------------------------------------------------------------------+ |Power Reactor |Event Number: 39680 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | FACILITY: CALLAWAY REGION: 4 |NOTIFICATION DATE: 03/19/2003| | UNIT: [1] [] [] STATE: MO |NOTIFICATION TIME: 18:16[EST]| | RXTYPE: [1] W-4-LP |EVENT DATE: 03/19/2003| +------------------------------------------------+EVENT TIME: 11:04[CST]| | NRC NOTIFIED BY: E. HENSEN |LAST UPDATE DATE: 05/19/2003| | HQ OPS OFFICER: MIKE RIPLEY +-----------------------------+ +------------------------------------------------+PERSON ORGANIZATION | |EMERGENCY CLASS: NON EMERGENCY |CLAUDE JOHNSON R4 | |10 CFR SECTION: | | |AUNA 50.72(b)(3)(ii)(B) UNANALYZED CONDITION | | | | | | | | | | | +-----+----------+-------+--------+-----------------+--------+-----------------+ |UNIT |SCRAM CODE|RX CRIT|INIT PWR| INIT RX MODE |CURR PWR| CURR RX MODE | +-----+----------+-------+--------+-----------------+--------+-----------------+ |1 N Y 100 Power Operation |100 Power Operation | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | HATCH MODIFICATION COULD HAVE IMPACTED COMPLETION OF A CONTROL ROOM | | EVACUATION | | | | "At 1104, 3/19/03, while operating at 100% power, Callaway Plant discovered | | that a modification performed on an equipment hatch impacted the ability to | | complete a Control Room evacuation in the event of a fire. The modification | | had installed a hatch in a floor penetration between elevations that had a | | latching mechanism installed on the bottom side of the hatch but the | | associated T-handle was not initially installed on top of the hatch. The | | latch mechanism could still be operated from the top via a large opening in | | the hatch where a ladder passed through the hatch. This modification could | | have resulted in the inability to access the area and valves below the hatch | | that would require manipulation during a Control Room evacuation. When | | this problem was identified, a T-handle was installed on top of the hatch | | for operating the latching mechanism and resolved the situation. | | | | "This event affects our commitment for the Control Room Fire Safe Shutdown | | analysis and is being reported as an unanalyzed condition per | | 10CFR50.72(b)(3)(ii)(B)." | | | | The licensee has notified the NRC Resident Inspector. | | | | Notified R4DO (C. Johnson) | | | | * * * RETRACTION ON 5/19/03 AT 1451 EDT FROM TIM HOLLAND TO E. THOMAS * * * | | | | "This event is being retracted. Upon further Engineering evaluation, it was | | determined that there was sufficient time to allow using an alternate route | | to access and operate the valve located on the elevation below the equipment | | hatch. Thus this event did not represent an unanalyzed condition and is not | | reportable." | | | | Notified R4DO (T. Pruett) | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |General Information or Other |Event Number: 39850 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | REP ORG: TEXAS DEPARTMENT OF HEALTH |NOTIFICATION DATE: 05/15/2003| |LICENSEE: BLAZER INDUSTRIAL RADIOGRAPHY |NOTIFICATION TIME: 12:18[EDT]| | CITY: PASADENA REGION: 4 |EVENT DATE: 05/14/2003| | COUNTY: STATE: TX |EVENT TIME: 18:48[CDT]| |LICENSE#: LO4619 AGREEMENT: Y |LAST UPDATE DATE: 05/16/2003| | DOCKET: |+----------------------------+ | |PERSON ORGANIZATION | | |WILLIAM JOHNSON R4 | | |TOM ESSIG NMSS | +------------------------------------------------+ | | NRC NOTIFIED BY: HELEN WATKINS | | | HQ OPS OFFICER: ERIC THOMAS | | +------------------------------------------------+ | |EMERGENCY CLASS: NON EMERGENCY | | |10 CFR SECTION: | | |NAGR AGREEMENT STATE | | | | | | | | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | AGREEMENT STATE REPORT | | | | The licensee reported a potential overexposure to a radiographer who was | | x-raying some pipes at a worksite. After completing a section of piping, | | the radiographer should have cranked his source back in, but was interrupted | | by another technician and left his work area. When he returned, the | | radiographer changed out his film, and moved the guide tube to another | | section of piping to begin more x-rays. At this point, he realized that his | | survey meter had pegged high, and remembered that he had not cranked the | | source back in prior to moving it. He proceeded to immediately crank the | | source back to its fully shielded position. The exact time and distance | | from the source for the radiographer's exposure is unknown, and the licensee | | is attempting to re-create the scenario. | | | | The source was 26 Curies of Iridium 192, model number INC-32. The serial | | number is unknown at this time. A preliminary investigation by the licensee | | estimates the radiographer's exposure to 800-900 millirem whole body. There | | is currently no exposure estimate for his hands/extremities. | | | | The radiographer's badge was sent off for processing. Results will be | | reported on 5/16/03 to the NRC. The Texas Department of Health is sending | | an additional inspector to the site to investigate. | | | | | | * * * UPDATE ON 5/16/03 @ 1120 BY WATKINS TO GOULD * * * | | | | Blazer Industrial Radiography brought in a consultant to perform preliminary | | dose calculations for the whole body and the right hand of the radiographer. | | The results were 1.3R for the whole body and 37.1R for the right hand, | | neither of which exceeds the annual regulatory limit. | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Power Reactor |Event Number: 39857 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | FACILITY: PILGRIM REGION: 1 |NOTIFICATION DATE: 05/19/2003| | UNIT: [1] [] [] STATE: MA |NOTIFICATION TIME: 05:57[EDT]| | RXTYPE: [1] GE-3 |EVENT DATE: 05/19/2003| +------------------------------------------------+EVENT TIME: 04:24[EDT]| | NRC NOTIFIED BY: MARTIN MANPENFEL |LAST UPDATE DATE: 05/19/2003| | HQ OPS OFFICER: HOWIE CROUCH +-----------------------------+ +------------------------------------------------+PERSON ORGANIZATION | |EMERGENCY CLASS: NON EMERGENCY |BRIAN MCDERMOTT R1 | |10 CFR SECTION: |TERRY REIS NRR | |ARPS 50.72(b)(2)(iv)(B) RPS ACTUATION - CRITICA|RICHARD WESSMAN IRO | |AESF 50.72(b)(3)(iv)(A) VALID SPECIF SYS ACTUAT| | | | | | | | +-----+----------+-------+--------+-----------------+--------+-----------------+ |UNIT |SCRAM CODE|RX CRIT|INIT PWR| INIT RX MODE |CURR PWR| CURR RX MODE | +-----+----------+-------+--------+-----------------+--------+-----------------+ |1 A/R Y 3 Startup |0 Startup | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | AUTOMATIC REACTOR SCRAM RESULTING IN PRIMARY CONTAINMENT AND REACTOR | | BUILDING ISOLATIONS | | | | At 0424 EDT, during startup operations, the Main Turbine Bypass valves | | unexpectedly opened and depressurized the reactor vessel. After | | depressurization, the reactor level increased due to swell and caused an | | automatic reactor scram. Additionally, there was a Reactor Building | | Isolation Signal and Group I, II, and VI Primary Containment Isolation | | Signal generated. Immediately after the automatic scram, five control rods | | failed to insert into the core. Plant operations personnel performed | | actions in accordance with their Emergency Operating Procedures to drive the | | control rods into the core. According to the licensee, adequate shutdown | | margin was always maintained. | | | | The plant electrical system is stable with plant equipment being powered | | from offsite and the startup transformer. Reactor pressure and level are | | being maintained via steam line drains to the main condenser. | | | | Troubleshooting of the Main Turbine Bypass valves/control system is in | | progress. | | | | The licensee will be notifying the NRC Resident Inspector. | | | | * * * UPDATE ON 5/19/03 @ 0957 EDT FROM ERIC OLSON TO CROUCH * * * | | | | The following clarification of the above information was received from the | | licensee via facsimile: | | | | "At 04:24 EDT, during startup operations, the Main Turbine Bypass Valves | | failed open. At the beginning of the event reactor pressure was | | approximately 880 psig. When the Main Turbine Bypass Valves opened, reactor | | pressure lowered to approximately 820 psi and reactor water level swelled | | (due to voiding) from 28 inches to approximately 55 inches. This resulted | | in a Group I PCIS [Primary Containment Isolation Signal] being generated as | | designed and automatically closing the MSIV's [Main Steam Isolation Valves]. | | MSIV closure terminated the depressurization, however initiated an automatic | | RPS [Reactor Protection System] signal as designed. Termination of | | depressurization resulted in reactor level lowering to approximately 7 | | inches which in turn initiated a Group II (Containment Isolation) and Group | | VI (Reactor Water Cleanup Isolation) PCIS signals. All rods inserted during | | the scram, however five control rods went beyond full in. Actions were | | taken in accordance with EOP's [Emergency Operating Procedures] and plant | | operating procedures to verify the five control rods were beyond full in. | | This is an indication issue with control rods that can occur when a scram | | signal is present and the Control Rod Drive System charging water flow | | drives the control rods beyond the [zero] and full in reed switches. | | | | "The plant electrical system is stable with plant equipment being powered | | from offsite power via the startup transformer. Reactor pressure is being | | maintained by steam line drains to the main condenser. Reactor water level | | is being maintained with normal feed and condensate system. | | | | "Troubleshooting of the Main Turbine Bypass Valve/Control system is in | | progress. | | | | "The [NRC] Resident Inspector has been notified." | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Power Reactor |Event Number: 39858 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | FACILITY: KEWAUNEE REGION: 3 |NOTIFICATION DATE: 05/19/2003| | UNIT: [1] [] [] STATE: WI |NOTIFICATION TIME: 09:43[EDT]| | RXTYPE: [1] W-2-LP |EVENT DATE: 05/19/2003| +------------------------------------------------+EVENT TIME: 05:18[CDT]| | NRC NOTIFIED BY: JONATHAN ROBB |LAST UPDATE DATE: 05/19/2003| | HQ OPS OFFICER: HOWIE CROUCH +-----------------------------+ +------------------------------------------------+PERSON ORGANIZATION | |EMERGENCY CLASS: NON EMERGENCY |ANNE MARIE STONE R3 | |10 CFR SECTION: | | |ASHU 50.72(b)(2)(i) PLANT S/D REQD BY TS | | | | | | | | | | | +-----+----------+-------+--------+-----------------+--------+-----------------+ |UNIT |SCRAM CODE|RX CRIT|INIT PWR| INIT RX MODE |CURR PWR| CURR RX MODE | +-----+----------+-------+--------+-----------------+--------+-----------------+ |1 N Y 100 Power Operation |97 Power Operation | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | PLANT COMMENCED TECH SPEC REQUIRED SHUTDOWN | | | | The following information was received from the licensee via facsimile: | | | | "At 0323 [CDT] on May 19th an Individual Rod Position Indication (IRPI) of | | control bank D exceeded 12 steps from its bank demand position. At 0418 an | | additional IRPI of control bank D exceeded 12 steps from its bank demand | | position, at which time the two IRPI indications were declared inoperable. | | At 0518 the plant initiated a Standard Shutdown Sequence as required by the | | plant's Technical Specifications (TS 3.10.f.2) since two IRPI's in a group | | were out of service. At 0530 the two IRPI were within 12 steps of the bank | | demand position and therefore the shutdown sequence was exited. Power is | | being held at 97% to investigate. | | | | "This is a 4-hour. Notification made in accordance with | | 10CFR50.72(b)(2)(i)." | | | | Initially, rod G-3 indication was greater than 12 steps from the bank demand | | position. Then rod G-11 indication drifted greater than 12 steps from the | | bank demand position. Currently, power in stable at 97% with G-3 indicating | | 198 steps and G-11 indicating 204 steps and bank demand position at 202 | | steps. | | | | The licensee has notified the NRC Resident Inspector. | | | | * * * UPDATE AT 1540 EDT ON 5/19/03 FROM JONATHAN ROBB TO E.THOMAS * * * | | | | Mr. Robb called back to clarify that IRPI indication deviated gradually from | | bank rod position as the bank was withdrawn, and as power and Tavg were | | increased. | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Power Reactor |Event Number: 39859 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | FACILITY: SAINT LUCIE REGION: 2 |NOTIFICATION DATE: 05/19/2003| | UNIT: [1] [2] [] STATE: FL |NOTIFICATION TIME: 10:32[EDT]| | RXTYPE: [1] CE,[2] CE |EVENT DATE: 05/19/2003| +------------------------------------------------+EVENT TIME: 09:05[EDT]| | NRC NOTIFIED BY: GEORGE TULLIDGE |LAST UPDATE DATE: 05/19/2003| | HQ OPS OFFICER: HOWIE CROUCH +-----------------------------+ +------------------------------------------------+PERSON ORGANIZATION | |EMERGENCY CLASS: NON EMERGENCY |ROBERT HAAG R2 | |10 CFR SECTION: | | |APRE 50.72(b)(2)(xi) OFFSITE NOTIFICATION | | |NONR OTHER UNSPEC REQMNT | | | | | | | | +-----+----------+-------+--------+-----------------+--------+-----------------+ |UNIT |SCRAM CODE|RX CRIT|INIT PWR| INIT RX MODE |CURR PWR| CURR RX MODE | +-----+----------+-------+--------+-----------------+--------+-----------------+ |1 N Y 100 Power Operation |100 Power Operation | |2 N N 0 Refueling |0 Refueling | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | MANATEE TRAPPED IN THE INTAKE CANAL | | | | The following information was received from the licensee via facsimile: | | | | "Notification being made due to a State Notification (Florida Fish and | | Wildlife Commission - Bureau of Protected Species) at 0905 [EDT]. (10 CFR | | 50.72 (b)(2)). | | | | "State notification made due to a Manatee trapped in the Intake Canal. The | | animal appears to be in good condition and State personnel are [en route] to | | assist in removal and release. | | | | "This notification includes requirements per St. Lucie Environmental | | Protection Plan Technical Specifications, Appendix B, section 4.1. This is | | a 72-hr notification for unusual occurrence of any species protected by the | | Endangered Species Act of 1973." | | | | The licensee has notified the NRC Resident Inspector. | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Other Nuclear Material |Event Number: 39860 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | REP ORG: GIBRALTAR PLASTIC CORPORATION |NOTIFICATION DATE: 05/19/2003| |LICENSEE: GIBRALTAR PLASTIC CORPORATION |NOTIFICATION TIME: 12:58[EDT]| | CITY: LODI REGION: 1 |EVENT DATE: 05/19/2003| | COUNTY: STATE: NJ |EVENT TIME: 09:30[EDT]| |LICENSE#: 29-18454-02 AGREEMENT: N |LAST UPDATE DATE: 05/19/2003| | DOCKET: |+----------------------------+ | |PERSON ORGANIZATION | | |ANTHONY DIMITRIADIS R1 | | |THOMAS ESSIG NMSS | +------------------------------------------------+ | | NRC NOTIFIED BY: JERRY WIZA | | | HQ OPS OFFICER: ARLON COSTA | | +------------------------------------------------+ | |EMERGENCY CLASS: NON EMERGENCY | | |10 CFR SECTION: | | |BSUR 20.1906(d)(1) SURFACE CONTAM LEVELS >| | | | | | | | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | SURFACE CONTAMINATION LEVELS ON SOURCE IS GREATER THAN LIMITS | | | | The licensee was packaging eleven cesium sources for shipment to Adco | | Services Incorporated. Upon surveying the sources, the contractor found | | that one Cs-137 source, Model No.S-4, Serial No.485 indicated field testing | | contaminations above 0.005 microcuries (exposure rate greater than 0.5 | | mR/h). The source activity is believed to be approximately 10.2 | | millicuries. This contaminated source will be packaged as dry waste in | | certified type A containers and will be shipped for disposal . The cabinet | | where the source was stored was contaminated and will also be packed and | | shipped for disposal. | | | | The licensee contacted Region 1 (D. White). | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Other Nuclear Material |Event Number: 39861 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | REP ORG: ILLINOIS DEPARTMENT OF NUC. SAFETY |NOTIFICATION DATE: 05/19/2003| |LICENSEE: NELSON LEASING |NOTIFICATION TIME: 16:30[EDT]| | CITY: WHEELING REGION: 3 |EVENT DATE: 05/17/2003| | COUNTY: STATE: IL |EVENT TIME: 18:45[CDT]| |LICENSE#: IL-01828-01 AGREEMENT: Y |LAST UPDATE DATE: 05/19/2003| | DOCKET: |+----------------------------+ | |PERSON ORGANIZATION | | |ANNE MARIE STONE R3 | | | | +------------------------------------------------+ | | NRC NOTIFIED BY: JOE KLINGER | | | HQ OPS OFFICER: ARLON COSTA | | +------------------------------------------------+ | |EMERGENCY CLASS: NON EMERGENCY | | |10 CFR SECTION: | | |NAGR AGREEMENT STATE | | | | | | | | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | AGREEMENT STATE REPORT - STOLEN TROXLER MOISTURE DENSITY GAUGE | | | | "On Saturday, May 17, at approximately 1845 hrs a Troxler moisture/density | | gauge Model # 3440, serial no. 21948, was stolen from a licensee's locked | | truck while it was parked in a parking lot at 105 N. Des Plaines, in | | Chicago. The licensee's technician stopped on his way home from work at | | this location and noticed, upon returning to his vehicle, that the rear hard | | cover, locked hatch had been broken into. Upon further inspection, the | | technician noticed that the locked and chained nuclear gauge had been taken. | | Immediately following this discovery, the Chicago Police Department was | | notified along with the licensee's Radiation Safety Officer/President, Scott | | R. Nelson. Scott Nelson mobilized to the crime scene. En route he notified | | the Illinois Department of Nuclear Safety's Radiological Duty Officer, Larry | | Haskell. Upon arrival at the scene, Mr. Nelson informed the police of the | | gauges operations, potential health issues and completed filing a police | | report. It apparently was evident that the truck was broken into. The | | police report number is HJ-369907. The station is Area 4." | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ |Power Reactor |Event Number: 39862 | +------------------------------------------------------------------------------+ +------------------------------------------------------------------------------+ | FACILITY: OYSTER CREEK REGION: 1 |NOTIFICATION DATE: 05/20/2003| | UNIT: [1] [] [] STATE: NJ |NOTIFICATION TIME: 02:47[EDT]| | RXTYPE: [1] GE-2 |EVENT DATE: 05/20/2003| +------------------------------------------------+EVENT TIME: 00:30[EDT]| | NRC NOTIFIED BY: JEFF DOSTAL |LAST UPDATE DATE: 05/20/2003| | HQ OPS OFFICER: HOWIE CROUCH +-----------------------------+ +------------------------------------------------+PERSON ORGANIZATION | |EMERGENCY CLASS: NON EMERGENCY |ANTHONY DIMITRIADIS R1 | |10 CFR SECTION: |MICHAEL CASE NRR | |ASHU 50.72(b)(2)(i) PLANT S/D REQD BY TS |RICHARD WESSMAN IRO | | |SAM COLLINS NRR | | |JIM WIGGINS R1 | | |NEAL PERRY R1 | +-----+----------+-------+--------+-----------------+--------+-----------------+ |UNIT |SCRAM CODE|RX CRIT|INIT PWR| INIT RX MODE |CURR PWR| CURR RX MODE | +-----+----------+-------+--------+-----------------+--------+-----------------+ |1 N Y 100 Power Operation |100 Power Operation | | | | | | | +------------------------------------------------------------------------------+ EVENT TEXT +------------------------------------------------------------------------------+ | PLANT SHUTDOWN REQUIRED BY TECHNICAL SPECIFICATIONS | | | | The plant experienced a trip of the "C" 4160 V electrical bus. This | | condition required entry into multiple technical specifications the most | | limiting being 3.3.D.5.B due to the loss of the capability to determine the | | rate of identified containment leakage. This required the reactor to be | | placed in a shutdown condition within the next 12 hours. | | | | The licensee believes that the cause of the "C" bus trip is a fault on the | | bus that is indicated as a lockout, however, the specific fault is unknown | | at this time and is under investigation. Due to the faulted bus, the | | station's emergency diesel generator did not start and will not be able to | | power any equipment on the "C" bus until the fault is repaired. Significant | | safety equipment lost due to loss of the bus is as follows: | | | | Emergency Service Water pump and Containment spray system #1 | | Service Water pump #1 | | Reactor Building Closed Cooling pump #1 | | Standby Gas Treatment system #1 | | Core spray and Core spray booster pumps "A" & "D" (4 pumps total) | | Standby Liquid Control pump #1 | | Control Rod Drive pump #1 | | | | The plant is commencing the required shutdown and expect to be at 60% | | reactor power by 0430 EDT. | | | | The licensee will be notifying the NRC Resident Inspector. | +------------------------------------------------------------------------------+
Page Last Reviewed/Updated Thursday, March 25, 2021
Page Last Reviewed/Updated Thursday, March 25, 2021