The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Event Notification Report for March 6, 2002

                         
                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           03/05/2002 - 03/06/2002

                              ** EVENT NUMBERS **

38610  38634  38732  

!!!!!!!!! THIS EVENT HAS BEEN RETRACTED. THIS EVENT HAS BEEN RETRACTED  !!!!!!!
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38610       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: WOLF CREEK               REGION:  4  |NOTIFICATION DATE: 01/06/2002|
|    UNIT:  [1] [] []                 STATE:  KS |NOTIFICATION TIME: 08:43[EST]|
|   RXTYPE: [1] W-4-LP                           |EVENT DATE:        01/06/2002|
+------------------------------------------------+EVENT TIME:        05:15[CST]|
| NRC NOTIFIED BY:  HUBBARD                      |LAST UPDATE DATE:  03/05/2002|
|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |BLAIR SPITZBERG      R4      |
|10 CFR SECTION:                                 |                             |
|AIND 50.72(b)(3)(v)(D)   ACCIDENT MITIGATION    |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| EMERGENCY DIESEL GENERATORS DECLARED INOPERABLE                              |
|                                                                              |
| At 1347 on 1/4/2002, the "A" emergency diesel generator (EDG) was declared   |
| inoperable due to tube degradation identified in the lube oil, intercooler   |
| and jacket water heat exchangers.  Technical Specification 3.8.1 was         |
| entered, the affected heat exchanger tubes were plugged and the "A" EDG was  |
| restored to operable status at 1134 on 1/5/2002.                             |
|                                                                              |
| At 1301 on 1/5/2002, the "B" EDG was taken out of service to perform         |
| inspections of its lube oil, intercooler, and jacket water heat exchangers.  |
| Inspection of the heat exchanger tubes and analysis of the inspection data   |
| found similar results, subsequently resulting in the need to plug heat       |
| exchanger tubes to restore the "B" EDG to operable status.                   |
|                                                                              |
| Based upon the similarity and extent of the tube degradation in both the "A" |
| and "B" EDG heat exchangers, prior to implanting the tube plugging           |
| corrective action, the possibility exists that the degradation of the EDG    |
| heat exchangers' tubes could have prevented the fulfillment of the safety    |
| function of the onsite standby class 1E power source following a design      |
| basis earthquake.                                                            |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| * * * UPDATE ON 01/06/02 AT 1927 EST BY HUBBARD TAKEN BY MACKINNON * * *     |
|                                                                              |
| "B" EDG was restored to operable status.  R4DO (B. Spitzberg) notified.      |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| * * * RETRACTED AT 1826 EST ON 3/5/02 BY STEVE HENRY TO FANGIE JONES * * *   |
|                                                                              |
| Subsequent evaluation of the heat exchangers by the licensee determined that |
| the degradation was not severe enough to interfere with the proper operation |
| of the EDGs.  The licensee is retracting the event notification, as the EDGs |
| were operational and fully available.                                        |
|                                                                              |
| The licensee notified the NRC Resident Inspector.  The R4DO (Linda Smith)    |
| was notified.                                                                |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38634       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SAINT LUCIE              REGION:  2  |NOTIFICATION DATE: 01/17/2002|
|    UNIT:  [1] [2] []                STATE:  FL |NOTIFICATION TIME: 13:07[EST]|
|   RXTYPE: [1] CE,[2] CE                        |EVENT DATE:        01/17/2002|
+------------------------------------------------+EVENT TIME:        11:45[EST]|
| NRC NOTIFIED BY:  KELLY KORTH                  |LAST UPDATE DATE:  03/05/2002|
|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |ROBERT HAAG          R2      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| OFFSITE NOTIFICATION  INVOLVING RECOVERED SEA TURTLE FROM INTAKE CANAL    
  |
|                                                                              |
| At approximately 1130 EST on 01/17/02, a green sea turtle was retrieved from |
| the intake canal and a determination was made that it was in need of         |
| rehabilitation.  As required by the Plant's Sea Turtle Permit, the Florida   |
| Fish and Wildlife Conservation Commission (FFWCC) was notified at 1145 EST.  |
|                                                                              |
| The licensee notified the NRC Resident Inspector.                            |
|                                                                              |
| See EN #38513 for 2001 occurrences.                                          |
|                                                                              |
| * * * UPDATE ON 1/28/02  @ 1243 BY KORTH TO GOULD * * *                      |
|                                                                              |
| At approximately 1115 on 1/28/02 a loggerhead turtle was retrieved from the  |
| plant's  intake canal.  The turtle was determined to be in need of           |
| rehabilitation.  Per the licensee's turtle permit, the Florida Fish and      |
| Wildlife Conservation Commission (FWCC) was notified at 1125.                |
|                                                                              |
| The NRC Resident Inspector was notified.   Notified Reg 2 RDO (Ninh)         |
|                                                                              |
| * * * UPDATE ON 2/6/02 @ 0853 BY MERRILL TO GOULD * * *                      |
|                                                                              |
| At approximately 0745 on 2/6/02 an injured green sea turtle was rescued from |
| the plant's intake canal.  The turtle was alive, but in need of              |
| rehabilitation.  The turtle will be transported to a facility in Clearwater  |
| for treatment.  The Florida Department of Environmental Protection has been  |
| notified of the event.                                                       |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Notified Reg 2 RDO(Fredrickson)                                              |
|                                                                              |
| * * * UPDATE 1025 3/2/2002 BY R. DIEHL TAKEN BY R. STRANSKY * * *            |
|                                                                              |
| "At approximately 0830 3/2/02 a Loggerhead turtle was retrieved from the     |
| plant's intake canal. The turtle was determined to be in need of             |
| rehabilitation. Per the plant's turtle permit, the Florida Fish and Wildlife |
| Conservation Commission (FWCC) was notified at 0845."                        |
|                                                                              |
| The NRC resident inspector has been informed of this report. HOO notified    |
| R2DO (Julian).                                                               |
|                                                                              |
| * * * UPDATE 1040EST ON 3/5/02 FROM GEORGE TULLIDGE TO S. SANDIN * * *       |
|                                                                              |
| "At Approximately 1000 on 3/5/02, a Loggerhead turtle was retrieved from the |
| plant intake canal.  The turtle was determined to be in need of              |
| rehabilitation.  Per the plant's turtle permit, the Florida Fish and         |
| Wildlife Conservation Commission (FWCC) was notified."                       |
|                                                                              |
| The NRC resident inspector has been informed of this report. HOO notified    |
| R2DO (Julian).                                                               |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38732       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: DAVIS BESSE              REGION:  3  |NOTIFICATION DATE: 02/27/2002|
|    UNIT:  [1] [] []                 STATE:  OH |NOTIFICATION TIME: 15:42[EST]|
|   RXTYPE: [1] B&W-R-LP                         |EVENT DATE:        02/27/2002|
+------------------------------------------------+EVENT TIME:        13:30[EST]|
| NRC NOTIFIED BY:  DALE MILLER                  |LAST UPDATE DATE:  03/05/2002|
|  HQ OPS OFFICER:  LEIGH TROCINE                +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |CHRISTINE LIPA       R3      |
|10 CFR SECTION:                                 |TOM KOSHY            NRR     |
|ADEG 50.72(b)(3)(ii)(A)  DEGRADED CONDITION     |JOSEPH HOLONICH      IRO     |
|NBNL                     RESPONSE-BULLETIN      |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          N       0        Refueling        |0        Refueling        |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| IDENTIFICATION OF AXIAL THROUGH-WELD INDICATIONS (REACTOR COOLANT
SYSTEM     |
| PRESSURE BOUNDARY LEAKAGE) ON ONE CONTROL ROD DRIVE MECHANISM
NOZZLE         |
|                                                                              |
| The following text is a portion of a facsimile received from the licensee:   |
|                                                                              |
| "On February 26, 2002, following shutdown for a scheduled refueling outage,  |
| the Davis-Besse Nuclear Power Station performed a qualified visual           |
| examination of the Reactor Vessel head per NRC Bulletin 2001-01.  This       |
| examination revealed evidence of boric acid build up around Control Rod      |
| Drive Mechanism (CRDM) nozzles but was inconclusive due to the previous      |
| known boric acid deposits.  At approximately 1330 hours on February 27,      |
| 2002, Ultrasonic Testing (UT) data identified axial through weld indications |
| on one CRDM.  Engineering evaluation of this data confirmed Reactor Coolant  |
| System pressure boundary leakage exists.  Technical Specification 3.4.6.2.a  |
| states that Reactor Coolant System leakage shall be limited to no pressure   |
| boundary leakage.  As a result this is being reported as a non-emergency,    |
| 8-hour report in accordance with 10CFR50.72(b)(3)(ii)(a), a condition that   |
| resulted in the nuclear power plant, including its principal safety barriers |
| being seriously degraded."                                                   |
|                                                                              |
| The licensee stated that UT inspections are continuing on other nozzles.     |
|                                                                              |
| The licensee plans to notify the NRC resident inspector.                     |
|                                                                              |
| * * * UPDATED AT 1921 EST ON 3/5/02 BY TERRY PLOEGER TO FANGIE JONES * * *   |
|                                                                              |
| "All inspections have been completed at this time. UT data for CRDM nozzles  |
| 1 and 2 (locations H-8 and G-7, respectively) has been evaluated to exhibit  |
| axial indications that represent pressure boundary leakage. This completes   |
| evaluation of the extent of the condition for the report communicated on     |
| February 27."                                                                |
|                                                                              |
| The licensee notified the NRC Resident Inspector.  The R3DO (John Madera),   |
| NRR EO (David Matthews), and IRO (Tim McGinty) have been informed.           |
+------------------------------------------------------------------------------+


Page Last Reviewed/Updated Wednesday, March 24, 2021