|Power Reactor                                    |Event Number:   38518       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: POINT BEACH              REGION:  3  |NOTIFICATION DATE: 11/26/2001|
|    UNIT:  [1] [2] []                STATE:  WI |NOTIFICATION TIME: 13:37[EST]|
|   RXTYPE: [1] W-2-LP,[2] W-2-LP                |EVENT DATE:        11/26/2001|
+------------------------------------------------+EVENT TIME:        12:32[CST]|
| NRC NOTIFIED BY:  ROBERT ADAMS                 |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |BRUCE JORGENSEN      R3      |
|10 CFR SECTION:                                 |                             |
|NONR                     OTHER UNSPEC REQMNT    |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| ERDS INOPERABLE DUE TO PLANNED OUTAGE OF THE PLANT PROCESS COMPUTER
SYSTEM   |
| (PPCS)                                                                       |
|                                                                              |
| AT 1232 CT, the Point Beach Nuclear Plant ERDS became inoperable as a result |
| of modifications to change out the plant process computer system (PPCS).     |
| This is a planned evolution.  ERDS will remain inoperable until              |
| approximately, December 18, 2001.                                            |
|                                                                              |
| This information was verbally provided to a representative of NRR during the |
| week of 10/15/2001.  The senior resident inspector has also been briefed on  |
| the modifications and schedule.  NMC to NRC letter (NRC 01-0080) dated       |
| 11/21/2001 stated we would be submitting this Non-Emergency report.          |
|                                                                              |
| ***** UPDATE FROM RICK ROBBINS TO LEIGH TROCINE AT 2006 EST ON 11/27/01      |
| *****                                                                        |
|                                                                              |
| The following additional information is a portion of a facsimile received    |
| from the licensee:                                                           |
|                                                                              |
| "As part of the PPCS modification, several inputs to the SPDS monitor were   |
| also made unavailable.  Any out-of-service indications on the SPDS can be    |
| obtained by control room control board indications."                         |
|                                                                              |
| The licensee notified the NRC resident inspector.  The NRC operations center |
| notified the R3DO (Bruce Jorgensen).                                         |
|                                                                              |
| * * * UPDATE 1259EST ON 12/22/01 FROM RYAN RODE TO S. SANDIN * * *           |
|                                                                              |
| The licensee provided the following information as an update:                |
|                                                                              |
| "On 11/26/01 at 12:32, the PBNP ERDS and SPDS were declared out of service   |
| for the PPCS upgrade project.  EN #38518 indicated to the NRC that the       |
| systems would remain unavailable until approximately December 18, 2001.  Due |
| to reliability issues with the newly installed PPCS, that expected date has  |
| been delayed to approximately January 3, 2002."                              |
|                                                                              |
| The licensee informed the NRC Resident Inspector.  Notified R3DO(Phillips).  |
|                                                                              |
| * * * UPDATE ON 01/03/02 @1430 BY MEYER TO GOULD * * *                       |
|                                                                              |
| During the installation of the new PPCS, issues were identified which need   |
| to be resolved to allow SPDS and ERDS to be placed back in service fully.    |
| Currently, the new PPCS is only partially operable.  Work is continuing on   |
| the new PPCS to allow full operability.  The current estimate for return to  |
| service of SPDS and ERDS is 01/19/02.  This date may need to be extended     |
| again due to parts availability.                                             |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Notified Reg 3 RDO(Shear)                                                    |
|                                                                              |
| * * * UPDATE ON 1/17/02 @ 1855 BY HARRSCH TO GOULD * * *                     |
|                                                                              |
| Update to 1/3/02 update (see below).  Work continues on the Plant Process    |
| Computer System (PPCS) to allow full operability. The Safety Parameter       |
| Display System (SPDS) is still out of service, however the Emergency         |
| Response Data System (ERDS) is now available. As mentioned in the 1/3/02     |
| update, parts availability has been a problem and the date for returning     |
| SPDS to service is now estimated to be 2/16/02.                              |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Reg 3 RDO(Vegel) was informed                                                |
|                                                                              |
| ***UPDATE ON 2/15/02 @ 1323 EST BY ADAMS TO NORRIS***                        |
|                                                                              |
| Update to 1/17/02 update.  Work continues on the Plant Process Computer      |
| System (PPCS) to allow full operability. The Safety Parameter Display System |
| (SPDS) is still out of service.  Due to parts availabilty, the date for      |
| returning SPDS to service is now estimated to be 3/09/02.                    |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Reg 3 RDO(Vegel) was informed.                                               |
|                                                                              |
| ***UPDATE ON 3/1/02 @ 1145 EST BY MILLEN TO NORRIS***                        |
|                                                                              |
| Update to 1/17/02 event notification.  As part of the upgade to the Plant    |
| Process Comuter System (PPCS), the Safety Parameter Display System (SPDS)    |
| has been accepted for use and is considered fully operational.               |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Reg 3 RDO (Lipa) was informed.                                               |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38602       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: CRYSTAL RIVER            REGION:  2  |NOTIFICATION DATE: 01/01/2002|
|    UNIT:  [3] [] []                 STATE:  FL |NOTIFICATION TIME: 10:08[EST]|
|   RXTYPE: [3] B&W-L-LP                         |EVENT DATE:        01/01/2002|
+------------------------------------------------+EVENT TIME:        09:19[EST]|
| NRC NOTIFIED BY:  BILL BANDHAUER               |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  FANGIE JONES                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |ANNE BOLAND          R2      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|3     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| OFFSITE NOTIFICATION DUE RESCUED SEA TURTLE                                  |
|                                                                              |
| EN #37902 started the biennial report period.                                |
|                                                                              |
| On January 1, 2002 at 0919, a rescued sea turtle was identified as a green   |
| sea turtle.  This is the 62nd rescue of a live sea turtle at Crystal River   |
| Unit 3 (CR-3) in this biennial period. Notification to the National Marine   |
| Fisheries Service and the Florida Fish and Wildlife Conservation Commission. |
|                                                                              |
|                                                                              |
| The licensee intends to notify the NRC Resident Inspector.                   |
|                                                                              |
| * * *  UPDATE ON 1/05/02 @ 1002 BY RAWLS TO GOULD  * * *                     |
|                                                                              |
| On January 5, 2002, at 0720, a rescued sea turtle was identified as a        |
| Loggerhead Sea Turtle. This is the 63rd rescue of a live sea turtle at       |
| Crystal River Unit 3 (CR3) in this biennial period.  This is reportable as a |
| 4-hour report under 10 CFR 50.72(b)(2)(xi) as this event is related to the   |
| protection of the environment for which a notification to other government   |
| agencies (National Marine Fisheries Service and Florida Fish and Wildlife    |
| Conservation Commission) has been or will be made.                           |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Reg 2 RDO (Decker) was notified.                                             |
|                                                                              |
| * * * UPDATE ON 01/09/02 @ 1107 EST BY ANDY BARNES TAKEN BY MACKINNON * * *  |
|                                                                              |
| On January 9, 2002, at 0838, a rescued sea turtle was identified as a Kemp's |
| Ridley Sea Turtle. This is the 64th rescue of a live turtle at Crystal River |
| Unit 3 (CR-3) in this biennial period. This is reportable as a 4-hour 10 CFR |
| 50.72 (b)(2)(xi) as this event is related to the protection of the           |
| environment for which a notification to other government agencies (National  |
| Marine Fisheries Service and Florida Fish and Wildlife Conservation          |
| Commission) has been or will be made.                                        |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Reg 2 (Brian Bonser) was notified.                                           |
|                                                                              |
| * * * UPDATE ON 02/17/02 at 0940 EST BY RICKY RAWLS TO FANGIE JONES * * *    |
|                                                                              |
| "On February 17, 2002 at 0820, a rescued injured sea turtle was identified   |
| as a Kemp's Ridley Sea Turtle. The injury will require transportation to     |
| Clearwater Marine Science Center or Florida Fish and Wildlife Conservation   |
| Refuge. The Injury appears to be from a boat propeller. This is the 65th     |
| rescue of a live sea turtle at Crystal River Unit 3 (CR-3) in this biennial  |
| period. This is Reportable as a 4-Hour Report under 10 CFR 50.72(b) (2) (xi) |
| as this event is related to the protection of the environment for which a    |
| notification to other government agencies (National Marine Fisheries Service |
| and Florida Fish and Wildlife Conservation Commission) has been or will be   |
| made. This Is an update to event 38602."                                     |
|                                                                              |
| The NRC Resident Inspector will be notified.  R2DO (Stephen Cahill) has been |
| notified.                                                                    |
|                                                                              |
| * * * UPDATE ON 03/01/02 AT 1122 EST BY RICKY RAWLS TO GERRY WAIG * * *      |
|                                                                              |
| "On March 1, 2002 at 0952, a healthy rescued sea turtle was identified as a  |
| Green Sea Turtle. This is the 66th rescue of a live sea turtle at Crystal    |
| River Unit 3 (CR-3) in this biennial period. This is Reportable as a 4-Hour  |
| Report under 10 CFR 50.72 (b) (2) (xi) as this event is related to the       |
| protection of the environment for which a notification to other government   |
| agencies (National Marine Fisheries Service and Florida Fish and Wildlife    |
| Conservation Commission) has been or will be made. This is an update to      |
| event 38602."                                                                |
|                                                                              |
| The NRC Resident Inspector was notified. R2DO (Julian) was notified.         |
+------------------------------------------------------------------------------+

!!!!!!!!! THIS EVENT HAS BEEN RETRACTED. THIS EVENT HAS BEEN RETRACTED  !!!!!!!
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38611       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: HOPE CREEK               REGION:  1  |NOTIFICATION DATE: 01/06/2002|
|    UNIT:  [1] [] []                 STATE:  NJ |NOTIFICATION TIME: 21:42[EST]|
|   RXTYPE: [1] GE-4                             |EVENT DATE:        01/06/2002|
+------------------------------------------------+EVENT TIME:        14:10[EST]|
| NRC NOTIFIED BY:  PARKER                       |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |MOHAMED SHANBAKY     R1      |
|10 CFR SECTION:                                 |                             |
|AIND 50.72(b)(3)(v)(D)   ACCIDENT MITIGATION    |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| HIGH PRESSURE COOLANT INJECTION (HPCI) SYSTEM DECLARED INOPERABLE           
|
|                                                                              |
| During the performance of the quarterly valve surveillance test for the HPCI |
| system, a testable check valve, 1FD-V032, related to the HPCI Barometric     |
| Condenser Discharge Line, failed.  This failure rendered the HPCI system     |
| inoperable at 1410 EST on 01/06/02. The licensee entered an active 14 day    |
| Limiting Condition of Operation that expires on 01/20/02 at 1410 EST.  All   |
| other safety systems are operable.  Current plans to return plant to normal  |
| configuration include the development of corrective maintenance work         |
| package.                                                                     |
|                                                                              |
| The NRC Resident Inspector will be notified of this event by the licensee.   |
|                                                                              |
| ***3/1/02 0952 Event was retracted by Licensee;  Jim Priest to Mike          |
| Norris.***                                                                   |
|                                                                              |
| "PSEG Nuclear retracts the event notification made on 1/6/02 (event number   |
| 38611).                                                                      |
|                                                                              |
| "Barometric condenser condensate pump discharge check valve 1 FD-V032 was    |
| opened and inspected. The valve internals were cleaned and the valve was     |
| reassembled and retested satisfactorily.                                     |
|                                                                              |
| "Subsequent evaluation determined that failure of 1 FD-V032 to close would   |
| not have prevented the HPCI system from performing its safety function.      |
| Reverse flow through 1 FD-V032 would not degrade the flow that HPCI supplies |
| the reactor vessel during a postulated accident.                             |
|                                                                              |
| "Since the HPCI system remained capable of performing its safety function,   |
| this event is not reportable.                                                |
|                                                                              |
| "The NRC Resident Inspector has been notified of this event by the           |
| licensee."                                                                   |
|                                                                              |
| Notified R1DO (Linville)                                                     |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38634       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SAINT LUCIE              REGION:  2  |NOTIFICATION DATE: 01/17/2002|
|    UNIT:  [1] [2] []                STATE:  FL |NOTIFICATION TIME: 13:07[EST]|
|   RXTYPE: [1] CE,[2] CE                        |EVENT DATE:        01/17/2002|
+------------------------------------------------+EVENT TIME:        11:45[EST]|
| NRC NOTIFIED BY:  KELLY KORTH                  |LAST UPDATE DATE:  03/02/2002|
|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |ROBERT HAAG          R2      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| OFFSITE NOTIFICATION  INVOLVING RECOVERED SEA TURTLE FROM INTAKE CANAL    
  |
|                                                                              |
| At approximately 1130 EST on 01/17/02, a green sea turtle was retrieved from |
| the intake canal and a determination was made that it was in need of         |
| rehabilitation.  As required by the Plant's Sea Turtle Permit, the Florida   |
| Fish and Wildlife Conservation Commission (FFWCC) was notified at 1145 EST.  |
|                                                                              |
| The licensee notified the NRC Resident Inspector.                            |
|                                                                              |
| See EN #38513 for 2001 occurrences.                                          |
|                                                                              |
| * * * UPDATE ON 1/28/02  @ 1243 BY KORTH TO GOULD * * *                      |
|                                                                              |
| At approximately 1115 on 1/28/02 a loggerhead turtle was retrieved from the  |
| plant's  intake canal.  The turtle was determined to be in need of           |
| rehabilitation.  Per the licensee's turtle permit, the Florida Fish and      |
| Wildlife Conservation Commission (FWCC) was notified at 1125.                |
|                                                                              |
| The NRC Resident Inspector was notified.   Notified Reg 2 RDO (Ninh)         |
|                                                                              |
|                                                                              |
| * * * UPDATE ON 2/6/02 @ 0853 BY MERRILL TO GOULD * * *                      |
|                                                                              |
| At approximately 0745 on 2/6/02 an injured green sea turtle was rescued from |
| the plant's intake canal.  The turtle was alive, but in need of              |
| rehabilitation.  The turtle will be transported to a facility in Clearwater  |
| for treatment.  The Florida Department of Environmental Protection has been  |
| notified of the event.                                                       |
|                                                                              |
| The NRC Resident Inspector was notified.                                     |
|                                                                              |
| Notified Reg 2 RDO(Fredrickson)                                              |
|                                                                              |
| * * * UPDATE 1025 3/2/2002 BY R. DIEHL TAKEN BY R. STRANSKY * * *            |
|                                                                              |
| "At approximately 0830 3/2/02 a Loggerhead turtle was retrieved from the     |
| plant's intake canal. The turtle was determined to be in need of             |
| rehabilitation. Per the plant's turtle permit, the Florida Fish and Wildlife |
| Conservation Commission (FWCC) was notified at 0845."                        |
|                                                                              |
| The NRC resident inspector has been informed of this report. HOO notified    |
| R2DO (Julian).                                                               |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38741       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: LIMERICK                 REGION:  1  |NOTIFICATION DATE: 03/01/2002|
|    UNIT:  [1] [2] []                STATE:  PA |NOTIFICATION TIME: 02:29[EST]|
|   RXTYPE: [1] GE-4,[2] GE-4                    |EVENT DATE:        03/01/2002|
+------------------------------------------------+EVENT TIME:        02:16[EST]|
| NRC NOTIFIED BY:  PHILIP CHASE                 |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  STEVE SANDIN                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |JAMES LINVILLE       R1      |
|10 CFR SECTION:                                 |                             |
|DDDD 73.71               UNSPECIFIED PARAGRAPH  |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       87       Power Operation  |87       Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| SECURITY REPORT                                                              |
|                                                                              |
| Unescorted access granted inappropriately to contract employee.  Immediate   |
| compensatory measures taken upon discovery.  The licensee will inform the    |
| NRC resident inspector.  Contact the Headquarters Operations Officer for     |
| additional details.                                                          |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|General Information or Other                     |Event Number:   38742       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| REP ORG:  TEXAS DEPARTMENT OF HEALTH           |NOTIFICATION DATE: 03/01/2002|
|LICENSEE:  PROTECHNICS                          |NOTIFICATION TIME: 08:52[EST]|
|    CITY:  HOUSTON                  REGION:  4  |EVENT DATE:        02/14/2002|
|  COUNTY:  HARRIS                    STATE:  TX |EVENT TIME:             [CST]|
|LICENSE#:  LO3835                AGREEMENT:  Y  |LAST UPDATE DATE:  03/01/2002|
|  DOCKET:                                       |+----------------------------+
|                                                |PERSON          ORGANIZATION |
|                                                |DAVID GRAVES         R4      |
|                                                |FRED BROWN           NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  JAMES H. OGDEN JR.           |                             |
|  HQ OPS OFFICER:  MIKE NORRIS                  |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          NON EMERGENCY         |                             |
|10 CFR SECTION:                                 |                             |
|NAGR                     AGREEMENT STATE        |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| AGREEMENT STATE REPORT INVOLVING A STUCK LOGGING WELL SOURCE                 |
|                                                                              |
| "Well logging tool became stuck at 17,125 feet, top of tool is 17,106 feet.  |
| Attempted fishing on 3 consecutive days,  unsuccessful.  Pumped 466 feet of  |
| red cement to secure source on February 14, 2002, to plug well.  Top of plug |
| is 16,640 feet.  Permanent identification plaque is under construction for   |
| emplacement on the wellhead.  Abandoned at Frank Bell #1 RE, Leon County,    |
| Texas, AP# 42-289-30432.  Source abandoned IAW Texas Regulations.            |
|                                                                              |
| "Isotope Products Laboratory, sealed logging source (Capsule Type), Model #  |
| HEG-241, Serial # NN-082, 250 microcuries Am-241.  Last leak tested 09/07/01 |
| (No leakage).  Manufactured September 25, 1998, pressure tested to 25,000    |
| psi."                                                                        |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38743       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: WATTS BAR                REGION:  2  |NOTIFICATION DATE: 03/01/2002|
|    UNIT:  [1] [] []                 STATE:  TN |NOTIFICATION TIME: 10:20[EST]|
|   RXTYPE: [1] W-4-LP,[2] W-4-LP                |EVENT DATE:        03/01/2002|
+------------------------------------------------+EVENT TIME:        02:59[EST]|
| NRC NOTIFIED BY:  R. Kimbrough                 |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  GERRY WAIG                   +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |CAUDLE JULIAN        R2      |
|10 CFR SECTION:                                 |                             |
|AINB 50.72(b)(3)(v)(B)   POT RHR INOP           |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          N       0        Refueling        |0        Refueling        |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| UNIT EXPERIENCED MOMENTARY LOSS OF RHR COOLING                               |
|                                                                              |
| "At approximately 0259 on March 1, 2002, with the Watts Bar Unit 1 reactor   |
| in Mode 6 with RCS temperature at approximately 100 degrees, during a        |
| refueling outage, operators isolated the common flowpath to the residual     |
| heat removal (RHR) pumps on two occasions over a 2 minute span. At the time  |
| of the event, operators were performing full flow testing of ECCS lines in   |
| conjunction with reactor cavity fill for refueling activities.               |
|                                                                              |
| The circumstances of the event are currently under investigation by the Site |
| staff."                                                                      |
|                                                                              |
| No observable RCS heatup occurred during the period that RHR was isolated.   |
|                                                                              |
| The NRC resident inspector was notified.                                     |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|General Information or Other                     |Event Number:   38744       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| REP ORG:  LOUISIANA RADIATION PROTECTION DIV   |NOTIFICATION DATE: 03/01/2002|
|LICENSEE:  METCO SULPHUR                        |NOTIFICATION TIME: 15:05[EST]|
|    CITY:                           REGION:  4  |EVENT DATE:        02/22/2002|
|  COUNTY:                            STATE:  LA |EVENT TIME:        18:30[CST]|
|LICENSE#:  LA-8043-L01           AGREEMENT:  Y  |LAST UPDATE DATE:  03/01/2002|
|  DOCKET:                                       |+----------------------------+
|                                                |PERSON          ORGANIZATION |
|                                                |DAVID GRAVES         R4      |
|                                                |FRED BROWN           NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  SCOTT BLACKWELL              |                             |
|  HQ OPS OFFICER:  GERRY WAIG                   |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          NON EMERGENCY         |                             |
|10 CFR SECTION:                                 |                             |
|NAGR                     AGREEMENT STATE        |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| AGREEMENT STATE REPORT - LOCK MALFUNCTION ON CAMERA                          |
|                                                                              |
| "On Friday February 22, 2002, a radiographer from METCO discovered that the  |
| lock on the Amersham 660 radiography camera with 60 curies of Ir-192 would   |
| not release to allow  an exposure. The Environmental Manager from LA Pigment |
| believed the auto-lock on the exposure device failed. The RSO at METCO       |
| responded within 30 minutes. The RSO stated that he cleaned the lock with    |
| WD-40 and the lock functioned after that. The RSO believes the lock was just |
| dirty."                                                                      |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38745       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: HARRIS                   REGION:  2  |NOTIFICATION DATE: 03/01/2002|
|    UNIT:  [1] [] []                 STATE:  NC |NOTIFICATION TIME: 18:14[EST]|
|   RXTYPE: [1] W-3-LP                           |EVENT DATE:        03/01/2002|
+------------------------------------------------+EVENT TIME:             [EST]|
| NRC NOTIFIED BY:  MARK ELLINGTON               |LAST UPDATE DATE:  03/01/2002|
|  HQ OPS OFFICER:  FANGIE JONES                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |CAUDLE JULIAN        R2      |
|10 CFR SECTION:                                 |                             |
|AUNA 50.72(b)(3)(ii)(B)  UNANALYZED CONDITION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| UNANALYZED CONDITION DUE TO FIRE BARRIERS NOT INSTALLED PER DESIGN          
|
|                                                                              |
| "On March 1, 2002, Harris Nuclear Plant personnel determined that an         |
| unanalyzed condition existed due to a required three-hour fire barrier not   |
| installed per design. The applicable fire barrier was designed to provide    |
| required separation between redundant train cables supplying A-SA Emergency  |
| Diesel Generator and B-SB Emergency Diesel Generator. Harris Nuclear Plant   |
| has initiated a continuous fire watch as a compensatory measure until the    |
| affected barrier could be restored to the design configuration. This issue   |
| is being reported in accordance with 10 CFR 50.72 as an unanalyzed           |
| condition."                                                                  |
|                                                                              |
| The licensee notified the NRC Resident Inspector.                            |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38746       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SALEM                    REGION:  1  |NOTIFICATION DATE: 03/03/2002|
|    UNIT:  [1] [] []                 STATE:  NJ |NOTIFICATION TIME: 04:25[EST]|
|   RXTYPE: [1] W-4-LP,[2] W-4-LP                |EVENT DATE:        03/03/2002|
+------------------------------------------------+EVENT TIME:        02:18[EST]|
| NRC NOTIFIED BY:  VAN FORD                     |LAST UPDATE DATE:  03/03/2002|
|  HQ OPS OFFICER:  BOB STRANSKY                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |JAMES LINVILLE       R1      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |45       Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| OFFSITE NOTIFICATION DUE TO OIL SPILL INTO DELAWARE RIVER                    |
|                                                                              |
| "On March 3, 2002 at 0218 a cooling line to 12B circulating water pump upper |
| motor bearing ruptured inside the upper oil reservoir. Oil was displaced     |
| from the oil reservoir and approximately 50 gallons of oil entered the       |
| Delaware River. 12B circulating water pump was removed from service and the  |
| leak was terminated. Cleanup efforts by onsite personnel are in progress. A  |
| 15 minute report was made to the New Jersey Department of Environmental      |
| Protection. A two hour report was made to the National Response Center in    |
| accordance with the site spill plan.                                         |
|                                                                              |
| Salem Unit 1 was initially at 100% power with 13B circulating water pump out |
| of service for scheduled maintenance. Power reduction is currently in        |
| progress in response to the loss of 12B circulating water pump with a target |
| power level of 40%."                                                         |
|                                                                              |
| The NRC resident inspector has been informed of this notification by the     |
| licensee.                                                                    |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38747       |
+------------------------------------------------------------------------------+
                         
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SUSQUEHANNA              REGION:  1  |NOTIFICATION DATE: 03/03/2002|
|    UNIT:  [1] [] []                 STATE:  PA |NOTIFICATION TIME: 06:04[EST]|
|   RXTYPE: [1] GE-4,[2] GE-4                    |EVENT DATE:        03/03/2002|
+------------------------------------------------+EVENT TIME:        03:00[EST]|
| NRC NOTIFIED BY:  GORDON ROBINSON              |LAST UPDATE DATE:  03/03/2002|
|  HQ OPS OFFICER:  BOB STRANSKY                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |JAMES LINVILLE       R1      |
|10 CFR SECTION:                                 |                             |
|ADEG 50.72(b)(3)(ii)(A)  DEGRADED CONDITION     |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          N       0        Cold Shutdown    |0        Cold Shutdown    |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| MSIV LEAKAGE EXCEEDS ALLOWABLE LIMIT                                         |
|                                                                              |
| "Leak Rate Testing on Unit 1 Main Steam Isolation Valves has identified that |
| the total minimum pathway leak rate exceeds the required limit of 300 scfh.  |
| The MSIV pathway combined leak rate was 1051 scfh. The identified degraded   |
| condition is reportable as a condition of the nuclear power plant, including |
| its principal safety barriers being seriously degraded per                   |
| 10CFR50.72(b)(3)(ii)."                                                       |
|                                                                              |
| The NRC resident inspector will be informed of this notification by the      |
| licensee.                                                                    |
+------------------------------------------------------------------------------+
