Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Event Notification Report for November 28, 2001

                         
                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           11/27/2001 - 11/28/2001

                              ** EVENT NUMBERS **

38518  
.
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   38518       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: POINT BEACH              REGION:  3  |NOTIFICATION DATE: 11/26/2001|
|    UNIT:  [1] [2] []                STATE:  WI |NOTIFICATION TIME: 13:37[EST]|
|   RXTYPE: [1] W-2-LP,[2] W-2-LP                |EVENT DATE:        11/26/2001|
+------------------------------------------------+EVENT TIME:        12:32[CST]|
| NRC NOTIFIED BY:  ROBERT ADAMS                 |LAST UPDATE DATE:  11/27/2001|
|  HQ OPS OFFICER:  JOHN MacKINNON               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |BRUCE JORGENSEN      R3      |
|10 CFR SECTION:                                 |                             |
|NONR                     OTHER UNSPEC REQMNT    |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| ERDS INOPERABLE DUE TO PLANNED OUTAGE OF THE PLANT PROCESS COMPUTER
SYSTEM   |
| (PPCS)                                                                       |
|                                                                              |
| AT 1232 CT, the Point Beach Nuclear Plant ERDS became inoperable as a result |
| of modifications to change out the plant process computer system (PPCS).     |
| This is a planned evolution.  ERDS will remain inoperable until              |
| approximately, December 18, 2001.                                            |
|                                                                              |
| This information was verbally provided to a representative of NRR during the |
| week of 10/15/2001.  The senior resident inspector has also been briefed on  |
| the modifications and schedule.  NMC to NRC letter (NRC 01-0080) dated       |
| 11/21/2001 stated we would be submitting this Non-Emergency report.          |
|                                                                              |
| ***** UPDATE FROM RICK ROBBINS TO LEIGH TROCINE AT 2006 EST ON 11/27/01      |
| *****                                                                        |
|                                                                              |
| The following additional information is a portion of a facsimile received    |
| from the licensee:                                                           |
|                                                                              |
| "As part of the PPCS modification, several inputs to the SPDS monitor were   |
| also made unavailable.  Any out-of-service indications on the SPDS can be    |
| obtained by control room control board indications."                         |
|                                                                              |
| The licensee notified the NRC resident inspector.  The NRC operations center |
| notified the R3DO (Bruce Jorgensen).                                         |
+------------------------------------------------------------------------------+
.

Page Last Reviewed/Updated Thursday, March 25, 2021