The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Event Notification Report for May 11, 2000

                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           05/10/2000 - 05/11/2000

                              ** EVENT NUMBERS **

36921  36987  36988  

!!!!!!!!! THIS EVENT HAS BEEN RETRACTED. THIS EVENT HAS BEEN RETRACTED  !!!!!!!
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   36921       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: COOK                     REGION:  3  |NOTIFICATION DATE: 04/23/2000|
|    UNIT:  [1] [2] []                STATE:  MI |NOTIFICATION TIME: 06:49[EDT]|
|   RXTYPE: [1] W-4-LP,[2] W-4-LP                |EVENT DATE:        04/23/2000|
+------------------------------------------------+EVENT TIME:        03:35[EDT]|
| NRC NOTIFIED BY:  BRIAN MOTZ                   |LAST UPDATE DATE:  05/10/2000|
|  HQ OPS OFFICER:  FANGIE JONES                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |MARK RING            R3      |
|10 CFR SECTION:                                 |                             |
|AESF 50.72(b)(2)(ii)     ESF ACTUATION          |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          N       0        Refueling        |0        Refueling        |
|2     N          N       0        Cold Shutdown    |0        Cold Shutdown    |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| UNIT 1 TRAIN 'B' ESSENTIAL SERVICE WATER PUMP STARTED AUTOMATICALLY          |
|                                                                              |
| While setting up for testing the Solid State Protection System (SSPS) on     |
| Unit 2, the clearance permit did not anticipate the start of the Unit 1      |
| train 'B' Essential Service Water (ESW) Pump.                                |
|                                                                              |
| "To perform maintenance on the SSPS, a clearance to deenergize the SSPS      |
| cabinets in Unit 2 was written.  The Unit 2 SSPS was in inhibit at this      |
| time.  During the deenergization per this clearance, an automatic start of   |
| the Unit 1 East ESW Pump occurred.  The ESW Pump autostart was not           |
| anticipated or described in the clearance.                                   |
|                                                                              |
| "A Safety Injection (SI) signal through SSPS in either Unit 1 or Unit 2 will |
| cause the ESW Pumps in both units to autostart for the train effected.       |
| Similarly, the removal of power from the control room instrumentation        |
| distribution circuit, which is what occurred here, will cause the autostart  |
| of the ESW pumps.                                                            |
|                                                                              |
| "There were no adverse consequences as a result of the auto pump start and   |
| the actuation was per the system design.  No SI signal was generated."       |
|                                                                              |
| The licensee notified the NRC Resident Inspector.                            |
|                                                                              |
| * * * UPDATE AT 1822 ON 5/10/00 BY WOODS RECEIVED BY WEAVER * * *            |
|                                                                              |
| "The original report was made regarding an automatic start of the Unit 1     |
| East Essential Service Water (ESW) Pump during maintenance, and was          |
| conservatively reported as an automatic actuation of an Engineered Safety    |
| Feature (ESF).  Subsequent reviews of the pump start event and the           |
| reportability requirements of 10 CFR 50.72 and 50.73 have confirmed that     |
| this event is not reportable.                                                |
|                                                                              |
| "In the case of the start of the 1 E ESW Pump, the ESF actuation slave relay |
| never was actuated, but was deenergized and would not have actuated.  No     |
| other portion of the associated ESF actuation circuitry was completed.       |
| Additionally, the ESW pump was not manually started in an emergency response |
| to plant conditions that would have required the pump to be operating.       |
|                                                                              |
| "NUREG-1022, Revision 1,  Event Reporting Guidelines: 10CFR50.72 and 50.73,  |
| Part 3.3.2,  Actuation Of An Engineered Safety Feature Or The RPS,  provides |
| guidance for the reporting requirements of an ESF actuation event as listed  |
| in 10 CFR 50.72 and 50.73.  The NUREG states that actuation of certain       |
| single ESF components of complex systems need not be reported.  Single       |
| components of complex systems, by themselves, usually do not mitigate the    |
| consequences of significant events.                                          |
|                                                                              |
| "Based on the facts that this event was an inadvertent start of a single     |
| component that would not mitigate the consequences of a significant event,   |
| and that the minimum amount of ESF actuation logic, i.e., the slave relay,   |
| did not actuate, the event is not reportable under 10 CFR 50.72 or 50.73.    |
| Therefore, the 4 hour non-emergency report, event number 36921, is being     |
| retracted."                                                                  |
|                                                                              |
| The licensee informed the NRC resident inspector of this report.  The        |
| Operations Center notified the R3DO (CLAYTON).                               |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   36987       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: FERMI                    REGION:  3  |NOTIFICATION DATE: 05/09/2000|
|    UNIT:  [2] [] []                 STATE:  MI |NOTIFICATION TIME: 21:19[EDT]|
|   RXTYPE: [2] GE-4                             |EVENT DATE:        05/09/2000|
+------------------------------------------------+EVENT TIME:        20:39[EDT]|
| NRC NOTIFIED BY:  DAVID COSEO                  |LAST UPDATE DATE:  05/10/2000|
|  HQ OPS OFFICER:  DOUG WEAVER                  +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |BRENT CLAYTON        R3      |
|10 CFR SECTION:                                 |                             |
|DDDD 73.71               UNSPECIFIED PARAGRAPH  |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|2     N          N       0        Cold Shutdown    |0        Cold Shutdown    |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| COMPENSATORY MEASURES TEMPORARILY SUSPENDED DUE TO INCLEMENT WEATHER.        |
| CONTACT THE OPERATIONS CENTER FOR ADDITIONAL DETAILS.                        |
|                                                                              |
| * * * Updated on 5/10/00 to reflect correct reactor mode of cold shutdown    |
| vice hot shutdown * * *                                                      |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Other Nuclear Material                           |Event Number:   36988       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| REP ORG:  UNIVERSITY OF CONNECTICUTT           |NOTIFICATION DATE: 05/10/2000|
|LICENSEE:  UNIVERSITY OF CONNECTICUTT           |NOTIFICATION TIME: 11:56[EDT]|
|    CITY:  STORRS                   REGION:  1  |EVENT DATE:        05/05/2000|
|  COUNTY:                            STATE:  CT |EVENT TIME:        09:30[EDT]|
|LICENSE#:                        AGREEMENT:  N  |LAST UPDATE DATE:  05/10/2000|
|  DOCKET:                                       |+----------------------------+
|                                                |PERSON          ORGANIZATION |
|                                                |JOHN ROGGE           R1      |
|                                                |DON COOL             NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  KEN PRICE                    |                             |
|  HQ OPS OFFICER:  FANGIE JONES                 |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          N/A                   |                             |
|10 CFR SECTION:                                 |                             |
|BAB1 20.2201(a)(1)(i)    LOST/STOLEN LNM>1000X  |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| POSSIBLE LOSS OF A TRITIATED EXIT SIGN                                       |
|                                                                              |
| During final walkthrough for renovation of the Waring Chemistry Building,    |
| one tritiated exit sign appears to be missing.  Eleven signs were collected, |
| but there appeared to be a "spot" on the wall at one exit where it appears a |
| sign had hung.  A search was conducted of the building without finding any   |
| indication of the sign.  There is no inventory of the signs so there is no   |
| positive way of determining that a sign is actually missing.  The sign would |
| by a model 101 by Shield Source Incorporated if it matches the rest of the   |
| signs.  The sign contained 7 curies of tritium on 1/93 and would contain     |
| about 5 curies now.  The university plans to send out a flyer looking for    |
| the sign and provide warning of the hazards involved.                        |
+------------------------------------------------------------------------------+
