Skip to main content

The NRC is modernizing nrc.gov with an updated design and improved navigation to enhance usability. We are committed to a smooth transition and will work to minimize any disruption. The site may be briefly unavailable at times during launch. Thank you for your patience.

Advisory Committee on Reactor Safeguards Plant License Renewal Subcommittee Meeting, October 30, 2002

ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
PLANT LICENSE RENEWAL SUBCOMMITTEE MEETING
PEACH BOTTOM UNITS, 2 & 3
OCTOBER 30, 2002
ROCKVILLE, MARYLAND

Contacts: Tim Kobetz (301-415-8716, tjk1@nrc.gov)
  Ramin Assa (301-415-6885, rra@nrc.gov)

PROPOSED SCHEDULE

TOPIC PRESENTER TIME
I. Opening Remarks G. Leitch, ACRS 8:30-8:35 a.m.
II. Staff Introduction P. T. Kuo, NRR 8:35-8:45 a.m.
III. Overview of the SER with Open Items and Inspections
Related to License Renewal of Peach Bottom Units 2 & 3
D. Solorio
J. Yerokun
M. Modes, RI
8:45-9:30 a.m.
IV. Exelon, Presentation
A. Background
B. License Renewal Application Scoping and Screening Process (IPA)
C. Aging Effects
D. Aging Management Programs
E. Time Limited Aging Analyses
F. Polaski 9:30-10:15 a.m.
***BREAK***   10:15-10:30 a.m.
V. SER Chapter 2: Scoping and Screening of Structures and Components
Subject to an Aging Management Review
R. Pettis
G. Hatchett
M. Razzaque
, J. Raval
D. Nguyen,
D. Frumpkin,
D. Cullison
10:30-11:15
VI. SER Chapter 3: Aging Management Programs S. Bailey
M. Khanna
J. Rajan, C. Munson,
B. Elliot,
R. Pettis
11:15-11:45
A. Reactor Coolant System B. Elliot 11:45-12:15
BWRVIP 38 & 75
   
B. Engineered Safety Features J. Medoff 12:15-12:30
***LUNCH***   12:30-1:30 p.m.
SER Chapter 3: Aging Management Programs    
C. Auxiliary Systems Z. Fu 1:30-1:45
D. Steam and Power Conversion Systems G. Georgiev 1:45-2:00
E. Containment, Structures and Component Supports C. Munson
H. Ashar
2:00-2:20
F. Electrical Components D. Solorio
D. Nguyen
2:20-2:50
***BREAK***   2:50-3:05 p.m.
VII. SER Chapter 4: Time Limited Aging Analyses    
A. Identification of TLAAs D. Solorio
J. Rajan
, R. Li
, J. Fair
3:05-3:20
B. Reactor Vessel Neutron Embrittlement, and Reactor
Vessel Internals Fatigue and Embrittlement
B. Elliot 3:20-3:50
C. Metal Fatigue J. Fair 3:50-4:10
VIII. Subcommittee Discussion   4:10-4:35 p.m.
IX. Adjourn   4:35 p.m.

NOTE:

  • Presentation time should not exceed 50 percent of the total time allocated for specific item. The remaining
    50 percent of the time is reserved for discussion.

  • 25 copies of the presentation materials to be provided to the Subcommittee

Plant License Renewal Subcommittee Meeting Peach Bottom Units, 2 & 3

Page Last Reviewed/Updated Monday, July 18, 2016

Page Last Reviewed/Updated Monday, July 18, 2016