ACRS Plant License Renewal Subcommittee Meeting - October 8, 2002
ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
PLANT LICENSE RENEWAL SUBCOMMITTEE MEETING:
MCGUIRE, UNITS 1 & 2 AND CATAWBA UNITS, 1 & 2
OCTOBER 8, 2002
ROCKVILLE, MARYLAND
Contact: Tim Kobetz (301/415-8716 tjk1@nrc.gov)
-PROPOSED SCHEDULE-
Topics | Presenters | Time | ||
---|---|---|---|---|
I. | Opening Remarks | M. Bonaca, ACRS | 8:30-8:35 a.m. | |
II. | Staff Introduction | P. T. Kuo, NRR | 8:35-8:45 a.m. | |
III. | Overview of the draft SER Related to License Renewal of McGuire (1 & 2) and Catawba (1 & 2) | R. Franovich C. Julian | 8:45-9:30 a.m. | |
IV. | Duke Energy Company, Presentation | G. Robison R. Gill | 9:30-10:00 a.m. | |
A. Background | ||||
B. License Renewal Application Scoping and Screening Process (IPA) | ||||
C. Aging Effects | ||||
D. Aging Management Programs | ||||
E. Time Limited Aging Analyses | ||||
***BREAK*** | 10:00-10:15 a.m. | |||
V. | SER Chap. 2: Scoping and Screening of Structures and Components Subject to an Aging Management Review | B. Rogers H. Walker T. Eaton J. Knox G. Hatchett | 10:15-11:00 | |
VI. | SER Chap. 3: Aging Management Programs | M. Khanna C. Munson S. Bailey | 11:00-11:30 | |
A. Reactor Coolant System | J. Medoff | 11:30-12:00 | ||
B. Engineered Safety Features | J. Medoff or G. Georgeiv | 12:00-12:15 | ||
***LUNCH*** | 12:15-1:15 p.m. | |||
VI. | SER Chap. 3: Aging Management Programs | |||
C. Auxiliary Systems | Z. Fu | 1:15-1:30 | ||
D. Steam and Power Conversion Systems | J. Tsao | 1:30-1:45 | ||
E. Containment, Structures and Component Supports | D. Jeng or C. Munson | 1:45-2:00 | ||
F. Electrical Components | D. Nguyen | 2:00-2:30 | ||
***BREAK*** | 2:30-2:45 p.m. | |||
VII. | SER Chap. 4: Time Limited Aging Analyses | |||
A. Overview | R. Franovich | 2:45-2:55 | ||
B. Reactor Vessel Neutron Embrittlement | J. Medoff | 2:55-3:25 | ||
C. Thermal Fatigue | J. Fair | 3:25-3:45 | ||
D. Leak-before-break | S. Sheng | 3:45-3:55 | ||
VIII. | Subcommittee Discussion | 3:55-4:15 | ||
IX. | Adjourn | 4:15 p.m. |
NOTE:
- Presentation time should not exceed 50 percent of the total time allocated for specific item. The remaining 50 percent of the time is reserved for discussion.
- 25 copies of the presentation materials to be provided to the Subcommittee
Page Last Reviewed/Updated Tuesday, October 03, 2017