Purpose
The purpose of this meeting is for Dominion Energy Nuclear Connecticut, Inc. (Dominion) to present to the Nuclear Regulatory Commission (NRC) staff, their planned submission of proposed changes to support the transition to 24-month fuel cycles at Millstone Power Station Unit No. 3. The proposed changes would seek to revise to technical specifications regarding spent fuel pool criticality, dose consequence analyses, and fuel performance methods.
Meeting Dates and Times
05/20/26, 9:30AM - 11:30AM EDT
Meeting Location
Teleconference
Webinar
Contact
Theo Edwards
(301) 415-1721
Participation Level
Observation Meeting
NRC Participants
Nuclear Reactor Regulation
External Participants
Dominion Energy
Docket Numbers - Facility Names
05000423 - Millstone 3
Teleconference
Bridge Number: 301-576-2978
Passcode: SD7xm3Mv
Conference ID: 233 378 486 300 503