Purpose
The purpose of this meeting is for VEPCO to discuss its proposed amendments to Technical Specifications (TS) 3.7, “Instrumentation Systems,” and TS 3.14, Circulating and Service Water Systems,” at Surry Power Station, Unit 1 and 2. The licensee proposes to extend the allowed outage times and use temporary equipment to complete maintenance and apply carbon fiber-reinforced polymer on the inside surface of service water system piping.
Meeting Feedback
Meeting Dates and Times
07/17/24, 1PM - 3PM EDT
Meeting Location
Teleconference
Webinar
Webinar Meeting Number: 301-576-2978
Webinar Password: 577 970 119#
Contact
John Klos
(301) 415-5136
Ed Miller
(301) 415-2481
Participation Level
Observation
NRC Participants
Office of Nuclear Reactor Regulation
External Participants
Virginia Electric and Power Company
Gary Miller
Docket Numbers - Facility Names
05000280 - Surry 1
05000281 - Surry 2