Purpose
The purpose of this meeting is to discuss the alternatives proposed in the September 30, 2021 application which requests an extension to the time allowed to repair identified damage on the Unit 3 intake cooling water discharge line.
Meeting Feedback
Meeting Dates and Times
10/05/21, 2PM - 3PM EDT
Meeting Location
Webinar
Webinar
Webinar Meeting Number: N/A
Webinar Password: N/A
Contact
Eva Brown
(301) 415-2315
Participation Level
Observation
NRC Participants
Office of Nuclear Reactor Regulation
External Participants
NextEra Energy, FPL
et al.
Matthew Mitchell
Ray Hoffman
Jarrett Mack
Stavroula Mihalakea
Docket Numbers - Facility Names
05000250 - Turkey Point 3
Teleconference
Bridge Number: 3015762978